PHOS progress in LS1 Alexander Vinogradov 11 August 2014
2
Work done since 28.07.2014 See PHOS LS1 planning: https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/PHOS_LS1_schedule-20140513.pdf Modules M2 and M3: - Transported to P2 July, 31
3
Module M1: - Lab test is over https://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/0802_Module1_Commissioning.pdfhttps://twiki.cern.ch/twiki/pub/ALICE/PhosSRU/0802_Module1_Commissioning.pdf - Moved to B-167 store area, need the air-tightness test (The test is planning for end of August, Yannick) Module M4: - Moved to testing area. - Readout test of opened module in progress. Cooling station: - Lab test is over. - Transported to P2 and installed to UX25 August,5:
4
Work at P2 Cable trays installing in progress. Fixation trays production for ethernet cables in progress. Additional power cables laying for PHOS/DCAL STU modules in progress. LV cables from Patch panel to PHOS modules is planning nearest time. Note: Updates on SRU/STU/TRU problems and common firmware development for PHOS/EMCAL/DCAL to be discussed at 18.08.14
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.