Key learning from recent service strikes Planning for future works; Designated team (group) to visit / assess each location prior to commencement of works.

Similar presentations


Presentation on theme: "Key learning from recent service strikes Planning for future works; Designated team (group) to visit / assess each location prior to commencement of works."— Presentation transcript:

1 Key learning from recent service strikes Planning for future works; Designated team (group) to visit / assess each location prior to commencement of works Teams to visit existing as well as new areas Consider sterilisation of work areas, typically where multiple operations and/or sub-contractors are to be working Use of Area Tag to identify ownership of current / future known hot spots? Identify (produce a log) of hot spots Review of protocol for extension of PTE, and by whom? Task lighting (provision, use and agreement for positioning of same prior to commencement of tasks)

2 Good Examples of Area inspection tags The area inspection tags are put in place at specific locations on site defined by a site supervisor or person in charge (PIC) of a work area. Form Ref: bmJV/TBT/12, dated: Apr 15 refers

3 Planning for future works; CAT scanning equipment; Review of training delivered to users (i.e. Site engineers and ground workers) Delivery of additional / refresher training Monitoring of compliance – i.e. Trained and competent user to monitor and provide feedback to user (akin to NVQ type assessment) Mentoring of company and sub-contract site engineers; Suggest a series of short “site based” workshops, typically at existing and new locations, and involving personnel key to works to be undertaken

4 In addition; Provision and use of Permit to Work (1) Board, (2) Controller, (3) Office Log of cable spikes to be produced / maintained – Task to be assigned to nominated personnel by site management Produce a library of key information including photographs, by time, location and group – a.k.a. As built records Use of safe system of work (SSOW) doc packs


Download ppt "Key learning from recent service strikes Planning for future works; Designated team (group) to visit / assess each location prior to commencement of works."