"The Realities of Developing and Implementing Capital Projects in Support of UK Infrastructure" Darren James, Managing Director – Infrastructure Costain.

Similar presentations


Presentation on theme: ""The Realities of Developing and Implementing Capital Projects in Support of UK Infrastructure" Darren James, Managing Director – Infrastructure Costain."— Presentation transcript:

1 "The Realities of Developing and Implementing Capital Projects in Support of UK Infrastructure" Darren James, Managing Director – Infrastructure Costain Group PLC

2  UK PLC  Moving Capitol and Resources Around  Sustainable Growth  Infrastructure Plan  Pipeline Meeting the Need 1

3 2 Planning and Statutory Process  Planning Act 2008  Nationally Significant Infrastructure Projects  Planning Process  Public Inquiry

4 3 Planning and Statutory Process  Consents  Statutory Requirements  European Regulations  Objections  Challenges  Judicial Reviews  Appeals

5 4 Developing the Solution  Meeting the Need  Specifying the Requirements  Developing the solution  Stakeholder Engagement  End User Consideration  Capex / Opex – Totex  Challenge

6 Delivery Certainty 5  Value Engineering  BIM  Scheduling  Safety  Forecasting  Community Engagement  Skills and Opportunities  Socio-economic Benefits  Learning  Innovation  Continuous Improvement

7 Case Study: Church Village By-Pass, Rhondda Cynnon Taf Original Aspiration  7Km – 2 Lane dual carriageway  4 No Intermediate junctions  1.5Km Side roads  9 No Road bridges  2 No Accommodation bridges  2 No Footbridges  1 No Equestrian bridge  2 No Pedestrian underpasses  1 No Cattle creep  11 No Reinforced concrete box culverts  500 Linm RC retaining walls  300 Linm Reinforced earth retaining walls  67 No items of utility works Delivered Solution  6Km – Single lane carriageway  4 No Intermediate junctions  1.5Km Side roads  2 No Road bridges  0 No Accommodation bridges  3 No Footbridges  0 No Equestrian bridge  1 No Pedestrian underpasses  2 No Cattle creep  7 No steel arch culverts  0 Linm RC retaining walls  0 Linm Reinforced earth retaining walls  53 No items of utility works

8 Working Together 7  Establishing the Real Need  Setting Outcome Objectives  Early Involvement  Stakeholder Engagement  Communicating the Value  Managing Delivery  Whole Life Cost and Value  Operations and Maintenance  Sustainability  Future Proof v Affordable  Positive Legacy

9 Rising to the Challenge 8  Plan  Process  People  Responsibility to make it happen

10 "The Realities of Developing and Implementing Capital Projects in Support of UK Infrastructure" Darren James, Managing Director – Infrastructure Costain Group PLC