Download presentation
Presentation is loading. Please wait.
Published byHerbert McCormick Modified over 9 years ago
1
Status of HO Installation and Commissioning Shashikant Dugad (DHEP, TIFR) India-CMS Meeting BARC, 20-21 July 2007
2
YB+2 All the surface installation work completed Pre-commissioning of the YB+2 completed during MTCC in 2006 YB+2 lowered in 2006 HV cables laid from control room to the detector and terminate into the splice box Signal and slow control cables laid from control room to the optical patch panel
3
YB+1 All the surface installation of work on this ring completed YB+1 lowered in Jan-2007 HV cables laid from control room to the detector and terminate into the splice box Signal and slow control cables laid from control room to the detector hall and terminated into the optical patch panel
4
YB0 All the surface installation of work completed YB0 lowered in March-2007 HV cables laid from control room to the detector and terminate into the splice box for 8 out of 12 RBXes Megatiles cable protection panels partly installed for 8 RBXes
5
YB-1 All the surface installation work completed Pre-commissioning completed in June-2006 To be lowered in October 2007
6
YB-2 5 out of 6 RBXes installed LV, JV, Signal and DCS cable instaleed for 5 out of 6 RBXes YB-2 to be lowered in October 2007
7
Future plans Commissioning of YB0 –July-Aug. 2007 Installation and pre-commissioning of YB-2 –July-Sep. 2007 Commissioning of YB+1 and YB+2 –Sep.-Oct. 2007? Commissioning of YB-1 and YB-2 –Nov.-Dec 2007
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.