Construction Project Management Prepared By: Omar Al-Taher Supervised By: Dr Baraq Jum’aa
2
Graduation project consist of two parts : The first part include preparing a theoretical research. The second part includes the application of the principle in construction project management.
3
What is a Project? A project is a temporary endeavor undertaken to accomplish a unique product or service with a defined start and end point and specific objectives. PMBOK definition
4
The Scope Triangle
5
What is Project Management? Project management is the application of knowledge, skills, tools, and techniques applied to project activities in order to meet or exceed stakeholder needs and expectations from a project. PMBOK definition
6
Project Management Body Of Knowledge ( PMBOK®) The PMI has identified nine topic areas to define the scope of project management knowledge as follows: Project Integration Management Project Scope Management Project Time Management Project Cost Management Project Quality Management Project Human Resource Management Project Communication Management Project Risk Management Project Procurement Management
7
P ROJECT P HASES AND L IFE C YCLE :
8
Project Area
9
Project Information 2 The project Consists of 1-Ground Floor 263.92 m 2. 2-First basement 349.10 m 2. 3- second basement 236.28 m 2. 4-Entrance 5m 2 4 Location : Nablus Rafedia 1 Residential Building (Villa). 3 Owner: By Private sector ( individual ) Funded by : The owner himself
10
الواجهة الشمالية الشرقية
11
الواجهة الجنوبية الغربية
12
الواجهة الجنوبية الشرقية
13
الواجهة الشمالية الغربية
14
DESIGN Step Thickness of slabs compatibility
15
Design Criteria
16
Cont….CHECK DESIGN ( Columns ) footings
17
Design of Footings & Beams …
18
Design of Slab ( one way Ribbed )
19
Cont. …
20
Cont.
22
Work Break Down Structure
24
Scheduling by using Primavera® Assumptions Working day = 8 hours Working days are all days except Fridays and holidays. The electrical and mechanical work done by sub contractor. All money paid by New Israeli Shekel (NIS) and the fixed value of Dollar according to local coin was (1$=4 NIS).
25
523 Calendar Days 1,069,432 NIS Scheduling by using Primavera® Program Primavera results show The overall duration of the project was 523 Calendar Days from 01-Sep- 11 to 27-Oct-12, while the total budgeted cost will be equal 1,069,432 NIS.
26
Activity List ( Primavera ®)
27
Cont.
28
S-CURVE FOR WE HAVE USING PRIMAVERA
29
Results. ( percent of total price ) 100 (%)Description. 18.6 %Excavations 25.7 %Concrete works 17.5 %Stone works 3.4 %Plaster. 5.7 %Tiles. 3.2 %Blocks 25.9 %Finishing