Download presentation
Presentation is loading. Please wait.
Published byAlison Lynch Modified over 9 years ago
1
The Ottawa Hills Dam Decommissioning Project. Constructed: August 2008
2
Existing riffle constructed by ODOT Conceptual Design Illustration of Restoration Site by Matt Horvat of TMACOG At the request of the Village of Ottawa Hills we did not work in this bend even though the vertical bank is 7 ft tall and the water over 7 ft deep!! US Project Limit DS Project Limit This project will encompass the bends immediately upstream and downstream of the former dam site
3
The Ottawa Hills Dam Decommissioning Project The dam was removed by Ohio-DOT in November 2007. The project described in this PowerPoint is designed to reduce bank erosion and protect public infrastructure (two roads), create aquatic & riparian habitat, improve streamside vegetation, assist with improving the riparian area, provide benches & stepping stones for public stream enjoyment and access, and still have the existing mowed floodplain recreation areas for public use!
5
OHIO DOT REMOVING THE SECOR ROAD DAM NOV-DEC 2007
6
Looking from left bank at the Secor Road dam. OTTAWA R-DAM REMOVAL @ OTTAWA HILLS-PIX BY MATT HORVAT-2007
7
Typical condition US of the Secor Road dam. OTTAWA R-DAM REMOVAL @ OTTAWA HILLS-PIX BY MATT HORVAT-2007
8
Looking from left bank @ trackhoe removing the dam. OTTAWA RIVER-DAM REMOVAL @ OTTAWA HILLS-PIX-LAWRENCE-2007
9
Looking US @ trackhoes removing dam OTTAWA RIVER-DAM REMOVAL @ OTTAWA HILLS-PIX-LAWRENCE-2007
10
Looking US. Dam out, right bank sheetpile out, concrete riffle in. Left bank sheetpile will stay. OTTAWA RIVER-DAM REMOVAL @ OTTAWA HILLS-PIX-HORVAT - 2007
11
PRE-PROJECT PHOTOS STARTING FROM UPSTREAM TO DOWNSTREAM by Dave Derrick AUGUST 20, 2008
12
Looking DS. High velocity current is eroding the right bank, then crosses over & erodes the left bank in the crossing. Note how deep Matt is. Matt went in over his head when he ventured near the right bank. At the request of the Village of Ottawa Hills, the right bank was not stabilized. PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008
13
Looking DS @ left eroded bank in the crossing & the upper portion of the US project bend. PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008
14
Looking US @ the lower end of the US project bend PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008
15
At the former dam site, looking US into the US bend PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008
16
Looking DS @ the DS project bend. Hill Ditch tributary comes in just US of the bend. PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008
17
Looking DS @ the DS project bend & the Secor Road bridge. PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008
18
Looking DS. The protection will tie into the existing bridge abutment protection right here. PRE-PROJECT-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-20-2008
19
THE PLAN
21
Existing riffle constructed by ODOT Conceptual Design Illustration of Restoration Site by Matt Horvat of TMACOG At the request of the Village of Ottawa Hills we did not work in this bend even though the vertical bank is 7 ft tall and the water over 7 ft deep!! US Project Limit DS Project Limit This project will encompass the bends upstream and downstrea m of the former dam site
22
EQUIPMENT
23
The Cat 330 tracked back hoe with a 4 ft wide bucket, 25 ft reach, weight about 70,000 pounds CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
24
STONE & STONE STAGING
25
SUITABLE STONE Stone used for keys and LPSTP was a well-graded, self-adjusting, self- filtering Class A Stone with a size of 18” to 36” on the “B” axis. Stone for the Bendway Weirs & Traffic Control Stones was a specially produced armor stone that varied from 2’ by 2’ by 3’ to 4’ by 4’ by 5’.
26
Dumping “A”stone-18 to 36 inch sized stone CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
27
Staged “A”-stone and armor stone CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
28
THE BEND IMMEDIATELY UPSTREAM OF THE FORMER DAM LOCATION
29
Methodologies for the Upstream Bend Traffic Control Stones with short Bendway Weirs Vegetated keys Transplanted clumps of shrubs Hydraulic Cover Stones Planned fall 2008: Container plantings of dogwoods, fast and slow growing shade trees, chokecherry, buttonbush, & other shrubs for food, pollinators, etc.
30
A KEY HAS ONE MAIN JOB, TO CONNECT THE RIVER TRAINING STRUCTURE TO THE REST OF THE WORLD (DON’T LET THE STREAM GET BEHIND {FLANK} RIVER TRAINING STRUCTURES)
31
CONSTRUCTION PHOTOS by Dave Derrick & Matt Horvat August 20-25, 2008
32
Detail for key Cross-section for keyway Flow
33
Looking uphill at the dug key trench CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008 Flow
34
Detail for key Place some stone & soil in the trench Flow
35
Placing some graded “A” stone and soil in the trench CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008 Flow
36
Place Willow Poles against DS side of trench. Detail for key Flow
37
Placing willow poles in the key trench CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
38
Key will be extended uphill where the hoe is parked CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008 Flow
39
Place the remainder of the stone in the trench Detail for key Flow
40
Placing “A” stone within 1 ft of the surface of the trench CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
41
Choke stone with soil & water in. Detail for key Flow
42
Backfill with native soils. CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
43
Backfill and overfill with native soils, then compact (some settling will still occur) Detail for key Flow
44
Compacting soil over key. Note poles on DS side of key CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
45
TRAFFIC CONTROL STONES
46
WHAT IS THE LOWER LIMIT OF HARD BANK PROTECTION? AND MORE IMPORTANT, HOW CAN WE REACH IT?
47
TRAFFIC CONTROL STONES (TCS) WITH SINGLE-STONE OR SHORT BENDWAY WEIRS
48
Drawn by Matt Horvat, TMACOG Traffic Control Stones for the US project bend
49
Drawn by Matt Horvat, TMACOG
50
Large stones (3 ft by 3 ft by 3 ft) designed to “kick” flow off the bank, must be keyed into the bed & bank, spaced 6 to 8 ft apart, every 3rd one should be keyed into the bank. Every 3rd stone has a Single Stone or short Bendway Weir. Traffic Control Stones with Single Stone Bendway Weirs Key TCS Key TCS SSBW TCS SSBW
51
Willow, dogwood, & buttonbush Live Stakes & poles were installed along with the TCS. Rooted stock plants will be installed this fall or spring Traffic Control Stones with Single Stone Bendway Weirs Key TCS Key TCS SSBW TCS SSBW
52
Track hoe digs a pit. Willow, dogwood, & buttonbush poles are placed around backside of pit CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
53
Looking DS @ Traffic Control Stone being placed in pit CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
54
Looking DS @ key, TCS, BW, & adventitious rooting poles CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008 BW TCS
56
How Do Bendway Weirs Work? Water flowing over the weir is redirected at an angle perpendicular to the longitudinal axis of the weir. With weirs angled upstream the erosive flow (energy) is directed away from the outer bank and toward the inner part of the bend. Strong secondary currents (helical flow) in bend are broken up. A set of weirs are designed to act as a system to capture, control, and redirect current directions and velocities through the bend and into the downstream crossing. Last weir in system can aim flow (and channel thalweg) where you need it.
57
Looking DS @ TCS. Hoe is stuck in unconsolidated muck CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
58
Looking DS @ hoe filling tracks. CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
59
Looking US @ the row of TCS @ the upper end of the bend. CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
60
Looking US @ center of bend (impact area). No mature vegetation on bank, so TCS are placed closer together. CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
61
Looking DS toward the former dam location. Placing TCS CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
62
Looking US @ the TCS near the DS end of the bend. CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
63
Looking US. Dense brush & trees make TCS placement difficult CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-2008
64
Resting rocks in the upper bend. CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-2008
65
Raking, seeding, and spreading weed-free straw. CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-2008
66
Spreading straw. CONSTRUCTION-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-2008
67
THE UPSTREAM BEND CONSTRUCTION IS COMPLETE (let’s look from upstream to downstream)
68
FROM THE OPPOSITE BANK (inner bank), LOOKING AT THE COMPLETED UPPER BEND
69
Looking US @ US key, veg poles & transplants & TCS CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-08
70
Looking US @ TCS, Live Poles, Bendway Weirs, & Live Stakes CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08
71
Looking @ center of bend (impinging impact area) CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08
72
Looking across @ outer bend just DS of the apex (center). CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-HORVAT 8-08
73
Looking DS @ outer bank TCS, Bendway Weirs, & poles. CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08
74
Looking DS @ lower end of bend (dam sheetpile visible) CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08
75
Looking DS @ end of bend TCS, Poles, & Live Stakes.
76
From the US crossing, looking DS into the project bend CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08
77
Looking DS into the impinging flow impact zone of the bend. CONSTRUCTION DONE-OTTAWA RIVER @ OTTAWA HILLS. PIX-DERRICK 8-08
78
Ottawa River Dam Removal 8-10-2009 Update Pix & words by Matt Horvat, TMACOG
79
Increased public use Pix & words by Matt Horvat, TMACOG
80
Pix by Matt Horvat, TMACOG
81
Left Bank in the spring Bank protection stones and willow, dogwood, buttonbush stakes are visible 6-5-2009 photo, Horvat
82
SIGNIFICANT PLANTING EFFORT 500 PLANTS INSTALLED THE WEEK OF JULY 27, 2009 ON BANKS & RIPARIAN AREAS Photos & words by Matt Horvat
83
Another view of the same area - Left Bank in the spring Bank protection stones and willow, dogwood, buttonbush stakes are visible Pix & words by Matt Horvat, TMACOG
84
Close up, leafing of stakes is visible. Stakes were installed when stones were placed in 8-2008 Pix & words by Matt Horvat, TMACOG
85
Materials to be used for restoration and stabilization Photos taken week of 7-27-2009 Pix & words by Matt Horvat, TMACOG
86
Wetland and riparian species of shrubs will be placed to in-fill between the stabilization stones. Nine-bark and buttonbush will be planted in the lowest areas.. They love having wet roots. Their roots will spread forming a dense network, holding the bank and soil during flood events. Photos taken by Matt Horvat week of 7-27-2009
87
Some of the woody shrubs being staged for planting on a right bank. The shrubs will be staggered to maximize the benefit of their roots holding the soil. Photos taken by Matt Horvat week of 7-27-2009
88
Floodplain area on the right bank being reforested. The vegetated floodplain and riparian area will help to slow flood velocities and allow suspended soil to settle out as well as provide habitat and recreation opportunities. Photos taken by Matt Horvat week of 7-27-2009
89
An auger is used where possible to prepare the soil for the new plant. All bank areas will have to be hand planted. Photos taken by Matt Horvat week of 7-27-2009
90
Site prep done with the 24” auger Photos taken by Matt Horvat week of 7-27-2009
91
One of the woody shrubs Photos taken by Matt Horvat week of 7-27-2009
92
Photos taken week of 7-27-2009
93
Planting top of bank floodplain areas Photos taken by Matt Horvat week of 7-27-2009
94
Looking downstream Photos taken by Matt Horvat week of 7-27-2009
95
LDB, just downstream of first key, new plantings of buttonbush, ninebark and elderberry visible at the bamboo stakes Photos taken by Matt Horvat week of 7-27-2009
96
Ninebark Photos taken by Matt Horvat week of 7-27-2009
97
Newly planted maple severely browsed, planting was only one day old Photos taken by Matt Horvat week of 7-27-2009
98
Browsed Hackberry Photos taken by Matt Horvat week of 7-27-2009
99
One of the suspects What deer like: Opportunity Maple Hackberry Everything else Photos taken by Matt Horvat week of 7-27-2009
100
Smells bad enough, lets hope it works! Photos taken by Matt Horvat week of 7-27-2009
101
RDB, just upstream on the old dam on the inside bank. Note the buttonbush planted low along the bank Photos taken by Matt Horvat week of 7-27-2009
102
LDB, looking upstream toward key Photos taken by Matt Horvat week of 7-27-2009
103
LDB, looking upstream toward key Stakes mark each plant location Photos taken by Matt Horvat week of 7-27-2009
104
RDB, upstream of dam and undercut high bank visible just beyond the sign at the locust tree. Planted approx 750lf from dam upstream = 0.8 acre Photos taken by Matt Horvat week of 7-27-2009
105
RDB, nearest old dam Photos taken by Matt Horvat week of 7-27-2009
106
LDB, West of Secor Ave. 800 lf from dam upstream = 1 acre Photos taken by Matt Horvat week of 7-27-2009
107
LDB, looking upstream. Upstream key starts at big locust Photos taken by Matt Horvat week of 7-27-2009
108
Documented watershed scale fish distribution changes due to dam mitigation/removal (first fish passage connectivity in 80+ years) !! Fish community above both Secor Dam (removed) and Highland Dam (mitigated) have significantly changed for the better. Least Darter are now distributed throughout the lower Ottawa River, presumably following the new conveyance of sand. I think I forwarded the picture of the juvenile Rainbow Trout we caught right? We caught the first juvenile Golden Redhorse I've found above the dam this fall. Furthermore, sunfish are abundant around Sylvania, which never happened before. The result of having sunfish and Redhorse has been a shift in dominance to less tolerant, lithophilic-spawning species. I also talked to someone who lives by the Airport who has had white suckers in his ditch every spring since you put in the riffle at Highland. There have been other highlights, but you're probably all yawning with the fish talk by now :) Awesome part, most all this data was collected by undergraduates in our Ecology 3060 lab course (University of Toledo). Take home message: CONNECTIVITY = GOOD! From: Todd Crail
109
the Bassett as a mountain lion
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.