Centralised Traffic Control Working On Dhamra line of ECoR

Similar presentations


Presentation on theme: "Centralised Traffic Control Working On Dhamra line of ECoR"— Presentation transcript:

1 Centralised Traffic Control Working On Dhamra line of ECoR
P. Venkata Ramana, Senior Professor (Signal) Indian Railway Institute of Signal Engg & Telecommunication, Secunderabad Railway Convention on 3Cs Systems Manekshaw Convention Centre, New Delhi 28th & 29th August, 2015

2 DHAMRA PORT BAY OF BENGAL
Dhamra Port – Deep draught, All Weather, Multiuser Sea Port At the mouth of River Dhamra On East Coast of India located between Haldia & Paradeep Ports In Bhadrak District of Odisha State

3 DHAMRA LINE Ranital Link Bhatatira Bhadrak Tihiri Gurudaspur Bansara
PPP Model 62KMs Railway Line from Port to Nearest Railhead Bhadrak Connectivity to HWH-CEN Trunk Route Opened for Freight Traffic in May, 2011 Today – 10 rakes per day Dhamra

4 DHAMRA LINE

5 SYSTEM OF WORKING Ranital Link: Special Class Station
Bhatatira Jn: B Class 6 line Station Tihiri: C Class Station Gurudaspur: B Class 4 line Station Bansara: C Class Station Dhamra Terminal: B Class 8 line Station Port Bulb 1: Special Class Station Port Bulb 2: Special Class Station

6 SYSTEM OF WORKING Multiple Aspect Colour Light Signalling (MACLS)
Interlocking Controller Single Processor with Diverse Software Hot Standby Keyboard, Video, Mouse (KVM) Data logging & Diagnostics Track detection by track circuits LED Signals

7 SYSTEM OF WORKING Conventional Double line Block:
Bhatatira – Bhadrak -- Ranital link junction cabin Inter-cabin Slot working Dhamra Terminal - Port Bulb 1 & Port Bulb 2  Electronic Block: Bhatatira – Tihiri – Gurudaspur – Bansara –Dhamra Terminal Block Section Proving by Axle Counters

8 WAYSIDE STATION Interlocking Controllers – Main and Standby
Interlocking Controller – certified for ATM or CTC working Diagnostic Terminal KVMs for Panel Operation Optical Fibre Switches for CTC Connectivity to adjacent stations Westrace – Westinghouse Train Radio Advanced Control Equipment Marik 1 VLM6

9 CTC CONFIGURATION Application Servers – CTC, in duplicate
WestCAD: Westinghouse Control And Display system Control Terminals – Controller Workstation, Supervisory Workstation, Operations Manager Workstation GPS based Time Servers - with GPS Antenna in duplicate for synchronising the clocks of all central and wayside systems Network Devices – Switches & Routers for dark fibre connectivity and local Ethernet Diagnostic & Maintenance Panel – Video Replay, Data logging and diagnostics

10 CTC NETWORK Bhathatira – Dhamra terminal – Port Bulb stations
Centralised Operations - Dhamra Control Centre Network Connectivity to all stations over 2 dark fibres on Ring topology to achieve redundancy paths Single Mode fibres, Full duplex – Separate Tx/Rx

11 CTC FEATURES Application Servers Control Terminals
In duplicate Control Terminals Controller, Supervisory, Operations GPS based Time Servers GPS Antenna Network Devices Industrial Grade Switches & Routers for Dark fibre & Local Ethernet Diagnostic & Maintenance Panel Video Replay, Data logging & Diagnostics

12 CTC FEATURES Application Modules Alarms & Enunciators Algorithm
Station Layouts Status of Interlocking Controllers Alarms & Enunciators Local & Remote Faults Algorithm Application Data design User Authentication Route Stacking Fleet mode KVM NMS

13 CTC FEATURES Local/Remote Operation All Emergency Cancellations
Signals, Switches, Crank Handle & Gate Controls Block Operation All Emergency Cancellations Except Emergency Switch Operation

14 CTC NETWORK

15 CTC NETWORK Bhathatira – Dhamra terminal – Port Bulb stations
Centralised Operations - Dhamra Control Centre Network Connectivity to all stations over 2 dark fibres on Ring topology to achieve redundancy paths Single Mode fibres, Full duplex – Separate Tx/Rx

16 Essentials of Absolute Block Working
For Single line provided with MACLS Line Clear has been received from the Block Station in advance The line is clear of trains running in the same direction, up to the first stop signal and an adequate distance beyond it The line is clear of trains running in the opposite direction The adequate distance shall not be less than 180 meters in MACLS Essentials of Absolute Block System for Single line provided with mutli-aspect signalling as per General & Subsidiary Rules: Where trains are worked on the Absolute Block System, no train shall be allowed to leave a block station unless Line Clear has been received from the Block Station in advance, and on Single Line such Line Clear shall not be given unless the line is clear of trains running in the same direction, not only up to the first stop signal at the Block Station at which such Line Clear is given, but also for an adequate distance beyond it, and is clear of trains running in the direction towards the block station to which such Line Clear is given. Unless otherwise directed by approved special instructions, the adequate distance shall not be less than 180 meters in case of multiple aspect colour light signalling

17 Special Requirements - Indications
LINE CLOSED At both the stations When the instruments are normal and there is no train in the block section TRAIN COMING FROM At the receiving station When Line Clear for a train to leave the Block station in rear has been given TRAIN GOING TO At the sending station When Line Clear for a train to leave a Block station has been received from the Block station ahead TRAIN ON LINE For Token less Block Instruments Special requirements for Single Line Block Instruments as per Signal Engineering Manual: The instruments shall be provided with visual indication clearly giving the-following indications : ·  When the instruments are normal and there is no train in the block section, ‘Line Closed’ at both the stations. ·  When Line Clear for a train to leave the Block station in rear has been given, ‘Train Coming From’ at the receiving station ·  When Line Clear for a train to leave a Block station has been received from the Block station ahead, ‘Train Going To’ at the sending station. In addition to the fixed indications in Token less Block Instruments, the instrument shall be provided with means to indicate ‘Train On Line’ at both the sending and receiving stations when a train has entered the block section.

18 Special Requirements – Push Button
TRAIN GOING TO & COMING FROM Button for TRAIN GOING TO Co-operation of the Station Masters be dispensed with TRAIN ON LINE be automatic LINE CLOSED Button for LINE CLOSED Can be dispensed with where an automatic device of closing the Block section is provided

19 BLOCK WORKING

20 BLOCK WORKING Steps Involved Establishment of Direction of Traffic
Obtaining ‘Line Clear’ Closing of Block Section

21 DIRECTION SETTING Bhattathira Tihiri Gurudaspur Signals S1 RECR Up
Bhattathira Tihiri Gurudaspur Signals S1 RECR Up S22 RECR Up S2 RECR Up S2 RCER Up S17 RECR Up Track Circuits 1T Up BAXT Up 2T Up Bhathatira-Tihiri-Gurudaspur Section Single line Bhathatita and Gurudaspur B Class stations – Loop lines Tihiri C Class Station – No Loop line for giving Precedence or arranging crossing of two trains

22 DIRECTION SETTING

23 LINE CLEAR Bhatatira Tihiri Signals S1 RECR up S22 RECR up S1 RECR Up
Track Circuits 1T Up BAXT Up 2T Up ZR1 Up, ZR2 Up, ZR3 Up Bhathatira-Tihiri-Gurudaspur Section Single line Bhathatita and Gurudaspur B Class stations – Loop lines Tihiri C Class Station – No Loop line for giving Precedence or arranging crossing of two trains

24 LINE CLEAR

25 LINE CLOSED CONDITIONS FOR LINE CLOSED Bhatatira Tihiri Signals
S1 RECR Up S22 RECR Up S2 RECR Up Track Circuits 1T Up BAXT Up 2T Up ZR1 Up ZR2 Up ZR3 Up SEQUENTIAL RELAY PROVING FOR TRAIN TIHIRI ZR1 Up ZR2 Up ZR3 Up BAXT Dn 2T Dn 1T Dn S2 SET 2T Up BAXT Up 1T Up

26 BLOCK WORKING IMPLEMENTATION
Block Control Chart Application Data design & Logic

27 CONCLUSION Showcase Integration of Absolute Block Working with Interlocking Controllers at Wayside stations Centralized Remote Operation Traffic operations are found to be economical & efficient Less manpower & NMS Throughput, Fleet mode Marginal cost - next phase of expansion 30MTPA freight traffic – Current Year 57MTPA freight traffic – Year 2020 Loading rakes Unloaded MT rakes MT July rakes 4.6 MT Calculated Line Capacity – 16 trains Demonstrated trains Additional Line Capacity Trains with loops at Bansara and Tihiri

28 WAY AHEAD 15% Electronic Interlocking Systems in IR (880/5944 block stations) Multiple Vendors Requirement for Networking Standards for interoperability for Centralised Monitoring & Opeartion

29 Dhamra Line – CTC Working
Any Questions?

30 Dhamra Line – CTC Working
Thank You