Red Light Running April 29, 2008
2
Red Light Running Outline Pilot Project System Used Cost Warning Notices Violation Photos Results Keys for a Successful Program Legislative Activity Questions/Comments
3
Approved 10/23/07 Implemented 2/29/08 Project Ends 8/08 Three Locations –W Colonial Dr at Hiawassee Rd –Orange Blossom Tl at Holden Av –Central Florida Parkway and John Young Parkway PILOT PROJECT
4
Red Light Running Outline Pilot Project System Used Cost Warning Notices Violation Photos Results Keys for a Successful Program Legislative Activity Questions/Comments
5
System Used Digital vehicle detection and digital imaging technology Records red light violations Shows violating vehicles and license plates Includes integrated Internet video recording system to record and transmit video segments
6
Red Light Running Outline Pilot Project System Used Cost Warning Notices Violation Photos Results Keys for a Successful Program Legislative Activity Questions/Comments
7
Cost Labor $51,000 Camera Systems $93,000 County Staff Time $2,500 Total Cost $146,000 ($18,250 per approach)
8
Red Light Running Outline Pilot Project System Used Cost Warning Notices Violation Photos Results Keys for a Successful Program Legislative Activity Questions/Comments
9
Orange County Courtesy Warning Notice
10
Red Light Running Outline Pilot Project System Used Cost Warning Notices Violation Photos Results Keys for a Successful Program Legislative Activity Questions/Comments
11
Violation Photos Date of Violation Time of the Violation Approximate Vehicle Travel Speed Signal Phase (R=Red) Length of Time that the Signal was Red Traffic Lane of Violator Zoom Image of License Plate
12
HIAWASSEE AND W. COLONIAL 1st Image
13
HIAWASSEE AND W. COLONIAL 2nd Image
14
John Young Pkwy and Central Florida Pkwy 1st Image
15
John Young Pkwy and Central Florida Pkwy 2nd Image
16
Holden Avenue at OBT 1st Image
17
Holden Avenue at OBT 2nd Image Vehicle Crossed Stop Bar
18
Red Light Running Outline Pilot Project System Used Cost Warning Notices Violation Photos Results Keys for a Successful Program Legislative Activity Questions/Comments
19
Results (1 st 8 wks) 3,843 Photos Taken
20
Results (1 st 8 wks) 1,371 Photos Rejected No Match to DMV, No Plate, Temp. Plate, Unreadable EMT/Police/Fire/V ehicle stopped, Other
21
Results (1 st 8 wks) 1,944 Letters Mailed
22
Results (1 st 8 wks) 80 Letters Returned to Public Works Reason for ReturnTotal # % By Reason Attempted - Not known810% Insufficient Address1519% Moved - Forward Time Expired911% Moved - Left No Address79% Return to Sender - No such Number23% Refused23% Undeliverable as Addressed3240% Vehicle Sold11% Rental Car45% Total Returns80100%
23
Red Light Running Outline Pilot Project System Used Cost Warning Notices Violation Photos Results Keys for a Successful Program Legislative Activity Questions/Comments
24
Keys for a Successful Program Man Power Quality Data Updated Technology Funding
25
Man Power –County Dedicated Staff Review Video & Photos Mail Notices/Citations Install/Maintain Equipment Process Citations Maintain Internet Site Collect Fines Appeal Process Summarize Data & Create Reports –Dedicated Vendor Staff (If Contracted) Keys for a Successful Program
26
Quality Data –DMV Database –Data Entry –Photos –Video –Internet –Reports –(If Contracted – Similar Challenges) Keys for a Successful Program
27
Updated Technology –Hardware To View Photos & Video Digital Photo Equipment –Software Data Reporting Reviewing Information –Access to Updated DMV Information Keys for a Successful Program
28
Funding –Pilot Project Cost $146,000 $18,250 per camera (8) $5,615.38 per week Results – 243 Warnings / week –@$60/citation = $14,280 –@ $30/citation = $7, 290 Significant Cost if County Owned and Managed Keys for a Successful Program
29
Red Light Running Outline Pilot Project System Used Cost Warning Notices Violation Photos Results Keys for a Successful Program Legislative Activity Questions/Comments
30
Legislative Activity Three Sponsored Bills –SB 816 –SB 2220 –HB 351
31
Red Light Running Outline Pilot Project System Used Cost Warning Notices Violation Photos Results Keys for a Successful Program Legislative Activity Questions/Comments
32
Red Light Running April 29, 2008