Presentation is loading. Please wait.

Presentation is loading. Please wait.

© 2008 Sterling Commerce. Confidential and Proprietary. How to Get Along with Project Using Microsoft Project so that it actually works for you, not against.

Similar presentations


Presentation on theme: "© 2008 Sterling Commerce. Confidential and Proprietary. How to Get Along with Project Using Microsoft Project so that it actually works for you, not against."— Presentation transcript:

1 © 2008 Sterling Commerce. Confidential and Proprietary. How to Get Along with Project Using Microsoft Project so that it actually works for you, not against you.

2 © 2008 Sterling Commerce. Confidential and Proprietary. Agenda The Formula Friends don’t let friends … Spaghetti Code Soft Coding vs. Hard Coding The Great Divide: Actuals Advanced Stuff: P&L

3 The Formula Work = Duration * Units Note: Work and Duration need to be in the same unit of measure (for calculation, but not for display) 100% = 1 unit Examples: 40 hours = 5 days * 100%  40 hours = (5 * 8h) * 1 20 hours = 5 days * 50%  20 hours = (5 * 8h) *.5

4 The Formula The original task: 40 hours = 5 days * 100% I need to assign a different resource, but the new resource is only available half-time: 40 hours = 10 days * 50% The resource will need to work overtime in order to complete the task on time. 48 hours = 5 days * 120% I need it done faster, so I will assign a more senior resource who will do the same job in less time: 32 hours = 4 days * 100%

5 The Formula Principle: 1 part stays the same and 2 parts change. The one that stays the same is said to be “fixed”. You change one of the non-fixed parts. And Project will automatically change the third part. You can change the fixed part, but if you know what you are doing, you probably wouldn’t.

6

7

8 The Formula The original task: 40 hours = 5 days * 100% I need to assign a different resource, but the new resource is only available half-time: 40 hours = 10 days * 50% The resource will need to work overtime in order to complete the task on time. 48 hours = 5 days * 120% I need it done faster, so I will assign a more senior resource who will do the same job in less time: 32 hours = 4 days * 100% Fixed Work – change units Fixed Duration – change units Fixed Units – change work

9 One Little Twist The original task: 8 hours = 1 day * 100% I need to add a second resource to this task, but it will still take the same amount of calendar time. 16 hours = 1 day * 100% + 100% Fixed Duration / Not Effort Driven Fixed Duration / Effort Driven 8 hours = 1 day * 50% + 50% Effort Driven: It only has an effect when you are adding or removing resources. It makes Work “Fixed” in addition to whatever else the task type has made “Fixed”.

10 Friends don’t let friends … Assign resources to summary tasks

11

12 Friends don’t let friends … Assign resources to summary tasks If you need a summary task, always create a new task specifically for the job. Give summary tasks noun-like names (e.g., Help File) Give detail tasks verb-like names (e.g., Create help file)

13 Spaghetti Code

14 Non-spaghetti Code

15 Writing non-spaghetti code Never link to or from a summary task. Use start and complete milestones instead. Try to link from top to bottom, like a waterfall. If you see links running uphill, try restructuring. Don’t use redundant links. If C must follow A and B, and B must follow A, then just say that C follows B. Keep the number of predecessors and successors as small as possible. If 20 tasks must finish before the 21 st can begin, try breaking the 20 tasks into smaller groups.

16

17 Soft Coding vs. Hard Coding Soft Coding: You enter the tasks, duration and dependencies. Project will predict the dates when the key milestones will be reached. Hard Coding: You enter the tasks, duration, dependencies, and dates. Project will draw a pretty picture of your plan.

18 The Benefits of Soft Coding When bad things happen to your project, the critical milestone may slip – but that’s a good thing. It is an early warning system that you must do something if you want to hit the milestone on time. If you have dates that you must hit, put a deadline on the milestone and monitor it whenever you update the project.

19

20

21 The Great Divide: Actuals

22 Percent Complete Works great if the project goes exactly as planned. When a task is marked as 100% complete, it started when it was supposed to start, it finished when it was supposed to finish, and it took exactly as many hours as we thought it would – whether it really did or not.

23 Actual and Remaining at Task Level Use one resource per task. Before entering the first actuals, enter the actual start date. The actual start and actual work can be compared to the planned start and planned work. The finish date and the hours worked per day may not be accurate. You may have to calculate remaining work if your resources report progress as percent complete. 40 hour task that now has 36 actual hours and is 75% complete Should have 13 hours remaining: (36/.75) – 36 New total work should be 48 hours

24 The Usage Views Task Usage or Resource Usage Can use multiple resources per task. Actual work is entered in the time-phased grid on the right. Remaining work is entered in the pane on the left.

25 Advanced Stuff: P&L Progressing the schedule: Moving unfinished work from the past to the future Leveling the schedule: Delaying some tasks to avoid over-allocation

26 Progressing the Schedule

27

28

29 Leveling the Schedule

30

31

32 © 2008 Sterling Commerce. Confidential and Proprietary. Review The Formula Friends don’t let friends … Spaghetti Code Soft Coding vs. Hard Coding The Great Divide: Actuals Advanced Stuff: P&L

33 © 2008 Sterling Commerce. Confidential and Proprietary. Contact Info ken_frei@stercomm.com


Download ppt "© 2008 Sterling Commerce. Confidential and Proprietary. How to Get Along with Project Using Microsoft Project so that it actually works for you, not against."

Similar presentations


Ads by Google