Download presentation
Presentation is loading. Please wait.
Published byCleopatra Montgomery Modified over 9 years ago
1
Soil Excavation and Concrete Penetration Permitting Process at LLNL Dennis Chew Plant Engineering Department September, 2006 UCRL-PRES-224319 This work performed under the auspices of the U.S. Department of Energy by the University of California, Lawrence Livermore National Laboratory, under Contract No. W-7405-ENG-48
5
Brief History Began with the purchase of LLNL’s first Audio Frequency instrument in the early 1990. Proactive step taken by LLNL as a result of an increasing number of utility strikes Locates were performed out of the Craft Shop of Plant Engineering External building Locates Between 1990 and 1998 Permit Process Documents Internal & External building Locates 30” No Dig rule Ferromagnetic scanners & Ground Penetrating Radar (GPR) Between 1999 and 2000 Established Permit Database – issuing paper permits LLNL “One Call” center concept Mindset / Purpose Preventing unplanned outages Reducing unplanned project costs Safety
6
Where we are at today Permit Office has grown Size and responsibility Improved database tracking methods Two types of permits Soil Excavation and Concrete Penetration Mindset / Purpose Preventing unplanned outages and reducing unplanned project costs Safety Culture shift Today the permit office issues an average of 60 permits per month Education/Training 3 rd party certification required Safety Video Incorporating new technologies Radio/Audio, GPR, and ferro-magnetic scanning Marker Ball program (open trench) Integrating with the Facility Information Center
7
The Permit Process Responsible Individuals LLNL employees who serve as the point of contact Partnering with the Permit Office to ensure compliance Annual training requirement Permit Office Locators Perform the locates and add any comments they may have on the permit – resources include As-builts / construction drawings / Utility drawings, etc… Issue the permit upon receiving all approvals Regulatory approvals Utility Owner approvals Signature Approvals Job site field visits Compliance Inspections Permit Closure Archived into the Permit database
8
The Permit Process Utility Location Database Locate Findings / Field Markings
9
Locating Instruments
10
Programmable Marker Ball Program
11
Documentation and Configuration Management Governing procedures for the permit process Continually evolving Lessons Learned & Process Improvement Customer feedback Staying ahead of the game On-going Communication Roll-out meetings and newsletters Eyes and Ears in the field Partnering with the Utility owners Provide up to date utility documentation Involve them in the approval process as owners PROC-CON 0002 Concrete PenetrationPROC-CON 0003 Soil Excavation
12
Safety Integration * * Safety Video * * * * Job Safety Analysis * * * * Locator Field Survey * * * * Pre-Task Hazard Analysis * * * * Compliance Inspections * * * * Compliance Inspections * * * * Outage Requirement * * * * 30” No Dig Zone * * * * 30” No Dig Zone * *
13
Closing Thoughts Innovative Thinking Continued Awareness Of the Safety Culture Partnering
14
Q & A
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.