Meditation Pavilion Eagle Project Tim Wolfe Troop 125
2
Project Overview Build a meditation pavilion for Covenant Presbyterian Church Pavilion will be 6 ft. x 8 ft. with a roof Located in secluded, wooded area overlooking a brook Path to be built from edge of woods to pavilion
3
Benefiting Organization Covenant Presbyterian Church, Simsbury Pavilion to be located near Center for Renewal To be used by –Retreat participants –Church members –Community members
4
Site Condition
6
Finances Approximate cost: $573.80 Fundraiser: Selling First Aid Kits 192 Kits @ $6 each 50% profit Funds raised: $576
8
Fundraising Plan Kits to be sold by 15 scouts and youth group members Each person to sell 10 kits Remaining kits to be sold on the green at Memorial Day and in front of local supermarkets
9
Construction Plan Clear site Build foundation Install posts Cut roof pieces Install deck Assemble roof Construct Path (simultaneous)
13
Timeline May 24 – Project approval, fundraising begins June 7 – Fundraising complete, materials purchased June 11-12 – Construction June 21 – Project report completed