1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.

Similar presentations


Presentation on theme: "1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007."— Presentation transcript:

1 1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007

2 2 Contents What we’ve achieved… Current View/s of hall Status: –Q35 Refurb –Baseplates/Magnet stands –MLCR –Magnetic shielding walls –Hall Water supply –Platforms and Baseplates –Electrical

3 3 What we’ve achieved… …CMS finished at last! -space used immediately.

4 4 JUNE: North Wall start

5 5 JUNE:Upstream shield

6 6 JUNE:view of Hall

7 7 What we’ve achieved… Solenoid plinth:First concrete pour: 26Jun07

8 8 What we’ve achieved… D2 mounted in position

9 9 What we’ve achieved… -Buffer tank and Platform -Enclosed Shielded area

10 10 What we’ve achieved… Concrete shield wall

11 11 Hall Progress Summary Shielded area in use – waiting radiation Survey –Background refinements –SW corner blocks on order –West wall replacement blocks at RAL –Extra wall near Door, and roof, subject to survey Buffer tank and platform installed- Linde have started Electrical work started in earnest (containment & cabling) Triplet build-up started, baseplates New full time Hall manager Significantly more technician effort

12 12 Current View/s of hall

13 13 Current View/s of hall2

14 14 Layout of hall 1

15 15 Layout of hall 2

16 16 Q35 Refurbishment Q35 stands: Lower girder bases at RAL

17 17 Q35s Q35 Refurbishment –2 complete –Program being accelerated with more technician effort Stands –Baseplates ready for grouting –Lower girder bases at RAL –Upper girder bases due this week –Remaining parts due end October –Accelerating trial build

18 18

19 19 located ready for levelling/aligning

20 20 MLCR Rack bases delivered beginning on this week. DPM for the floor completed by Friday. Network rack delivered next week. PPS rack, populated and tested delivered the week after (15th) Remaining racks the week of the 23rd. Walls delivered week of the 8th and installed by the end of the following week at the latest. Air con and power to start as soon as the walls are constructed and estimated to take three weeks so complete by 9th November. Construction of the roof to occur in parallel. Network connection to RAL site to start as soon as the racks have been Delivered. A wireless access point to be set up as soon as possible. Further wiring into the hall to follow. Too much civil still going on to start too early.

21 21 Electrical Infra-structure Drawings for distribution design complete –Final checks in progress, issue next week MICE Hall cable route design including LCR complete –Busbar trunking removed –AC supply re-used as LCR feed Cable schedule for magnet power converters complete –Installation plan for DC and control cables to be agreed Specification for power converters AC distribution scheme complete –Installation in progress –Accelerator Dipole Power Converter requires direct feed – Budget price received Specification for RF System AC distribution scheme complete –Awaiting price for installing distribution board –Installation to commence within next 2 weeks LCR tray work design complete –Rack support frames delivered –Tray work to be installed Sequence of installation to be agreed –Raised floor to be installed Cryogenic Soleniod –Compressor supply installed –Distribution Board installed –AC temporary supply agreed for tests Phase 2 electrical requirements under review –Detailed information for all systems required

22 22 Magnetic Shield South Wall: Drgs complete Support structure requote- Ready to build Material identified Preparations to start procurement North wall: Design being finished. Overall schedule to be prepared

23 23 MICE – platforms and baseplates CONCEPT – PLATFORM WITH AIR SKATES CLAMPED TO BASEPLATE IN INSTALLED LOCATION. WHEN ACCESS IS REQ’D THE CLAMPS ARE RELEASED AND THE TRACKER IS FLOATED TO A PARKED POSITION.

24 24 Platform review Design review last week: Supported mass up by 25% (7-9t) Clarification of cables esp. ‘live’ Not yet ready for production Clear issues before re-reviewing

25 25 Mechanical Services Water- Chiller order placed last Friday? Other services/gases –Need for detector groups to request any required services Compressed air line for when Linde equipment in use Nitrogen for CKOV (bottle/gas line)?

26 26 Conclusion: Next High Priority! -Concrete plinth for MICE Experiment -False floor