1 RIKEN Nishina Center for Accelerator-based Science
RI Beam Factory Project at RIKEN H.Sakurai RIKEN Nishina Center for Accelerator-based Science

2 Overview of RIBF facility and physics with exotic nuclei
Introduction of Phase-I facility and Experimental programs Recent achievements and future plan Summary

3 RIBF Facility Layout Phase-II Experimental Installations
2007~2010 (plan) Existing facility RIPS SHE GARIS ~100 MeV/u ~5 MeV/u RILAC AVF fRC RRC SRC IRC BigRIPS/ZeroDegree CRIB (CNS) ~10 MeV/u MeV/nucleon New facility Phase–I SRC + BigRIPS/ZeroDegree 440 M$ (1$=100JPY) 350 MeV/nucleon up to U 1st beam in 2006

4 Exploration of the limits of nuclear existence
- towards the drip-lines - 3rd generation of RI beam facility “Fission fragment of U” SRC high energy and intense heavy ion beams upto U 350 – 400 A MeV Goal of intensity 1 p-micro A BigRIPS high acceptance for fission fragments Projectile fragmentation 48Ca, 58Ni, 78Ge, 78Kr, 112Sn, 204, 208Pb, 238U, ... 350~400A MeV proton-rich side neutron-rich A<50 or A>160 limit of production 1 particle/day Fission 238U 350A MeV neutron-rich side 20<Z<60 wide dynamic range 78Ni ~10 particles/sec goal

5 Phase-II construction 2007-2010
To maximize the potentials of intense RIBs available at RIBF 60 M$ SCRIT - e-RI collision Wakasugi, Suda et al. SAMURAI - large acceptance Kobayashi et al. Rare RI Ring – mass   Ozawa et al. SHARAQ - high resolution Shimoura et al. in 2008 SLOWRI- slow beams Wada et al. RI Spin Lab. at RIPS –pol. RI beam Ueno et al. About 2M $ was approved in FY2007 for the infrastructure, radiation shields, ZeroDegree electronics.

6 Acceleration Flow in RI Beam Production
RILAC RRC fRC IRC SRC BigRIPS ZDS by Narumasa Miyauchi 6

7 BigRIPS /ZeroDegree Exploration into “Isospin Frontier” toward the drip-lines Reaction study fit for high energy domain A MeV operated by Kubo group BigRIPS Fragment Separator high acceptance for fission fragments pid for RI beams at the second section ZeroDegree Multi-function BT line pid for ejectiles in inclusive- and semi-exclusive measurement medium resolution (p/dp ~ 2000 – 4000) Experimental set-ups PID section RIB production PID section

8 Basic parameters of BigRIPS
T. Kubo et al. Configuration Two-stage separator First stage Two bends Second stage Four bends Energy degrader Achromatic wedge Quadrupoles Superconducting Angular acceptance Horizontal mr Vertical mr Momentum acceptance % Max. magnetic rigidity Tm Total length m Momentum dispersion* First stage m Second stage m Momentum resolution**(1st order) First stage Second stage*** In-flight fission of 238U at 350 MeV/u ~ 100 mr ~ 10 % * At the mid-focus of the stage. ** Those in the case when a 1 mm beam spot is assumed.

9 Specifications of optical modes
(I) Achromatic: Large acceptance mode Maximum magnetic rigidity = 7.3 Tm Angular acceptance Horizontal = +/-45 mrad, Vertical = +/-30 mard Momentum acceptance = +/-3 % Momentum dispersion = 2.24 cm/% Momentum resolution = (X,P)/(X,X) =1240 (II) Achromatic: High resolution mode Maximum magnetic rigidity = 9.0 Tm Angular acceptance Horizontal = +/-20 mrad, Vertical = +/-30 mard Momentum acceptance = +/-3 % Momentum dispersion = 2.12 cm/% Momentum resolution = (X,P)/(X,X) = 2120 (III) Dispersive spectrometer mode Maximum magnetic rigidity = 9.0 Tm Angular acceptance Horizontal = +/-20 mrad, Vertical = +/-30 mard Momentum acceptance = +/-2 % Momentum dispersion = 4.13 cm/% Momentum resolution = (X,P)/(X,X) = 4130 (IV) Transmission mode

10 Phase-I programs at BigRIPS/ZeroDegree 2007~
Rare-Isotope Physics Programs Fast RI beam production to search for new isotopes Global survey to search for anomalous regions Specific programs with deuteron beams BigRIPS in-flight production of fast rare-isotope beams Ground state properties and low lying excited states via decay spectroscopy / transmission method: particle stability, T1/2, Qb, sR, Ex.(2+)... Deeply bound pionic states via (d, 3He) at 500 MeV Three-body force via pol. d+p elastic scattering at 700 MeV ZeroDegree multi-function beam line for inclusive/semi-inclusive measurements   production of 3rd RI beams Collectivity and matter distribution via in-beam gamma / missing mass spectroscopy One step energy regime 200~300 A MeV B(E2), B(M1), (p,p), (p,p’), Ex....

11 RIBF layout in 2007-2008 in-beam gamma spectroscopy
missing mass spectroscopy RIBF layout in (Phase-I layout) b-spectroscopy total reaction cross sections (d,3He) Pol.d+p ZeroDegree Spectrometer Experimental set-ups ZDS: Zero-Degree forward Spectrometer

12 RI beam intensities at BigRIPS for first two years 2007-2008
Primary beam energy 350AMeV 48Ca (200pnA), 86Kr (100pnA),136Xe (10pnA), 238U(2pnA) Secondary beam energy ~250A MeV Cross sections Fragmentation EPAX-II Fission GSI-data (U+Be), ABRABLA (Coulomb)

13 Collaboration One of the largest heavy-ion facilities in the Asia/world Open for the world-wide user community International Collaboration Workshop on Experiments at the RIBF 6th-9th November 2006 ~130 participants; ~30 from foreign institutes/universities Presentation and discussion of experimental projects to be done in collaboration To identify common interests To have “show case” for experimental technique, methods, detectors … To establish collaborations To prepare proposals MOU “Creation of the council for China-Japan Research Collaboration on Nuclear Physics” 10th November 2006 19 proposals submitted to PAC Feb (74% international) France-Japan collaboration will be established soon

14 Recent achievements / Future plan

15 Recent achievements 28th Dec. 2006 First Beam 27Al10+ at RIBF-SRC
Mar. 2007 12th Kr31+ beam at 345 A MeV several pnA. 13th First Production of RIBs at BigRIPS 23rd First successful acceleration of 238U beam 0.002pnA 27th First production of radioactive isotope beams via a U beam Last week 238U beam 0.02pnA max BigRIPS Commissioning; New isotope 125Pd

16 First beam accelerated at SRC K2600MeV
16:00 28th Dec., 2006 27Al MeV/u

17 First RIB 13th Mar. 2007 Kubo et al. 86Kr + Be(2mm) at 345 MeV/u DE
N=Z+2 N=Z+1 86Kr + Be(2mm) at 345 MeV/u N=Z+3 Zn Cu Ni Co 54Fe N=Z Fe Mn Cr V Ti 43Sc Sc K Ca Cl Ar P S Si Al TOF (F3-F7) Kubo et al.

18 PID for isotopes created via a 345 A MeV U beams w/o degrader
TOF(F3-F7) [ns] [MeV] Xe Mar. 27th, 2007 I Sn (Z=50) Sb 132Sn Cd In Pd 117Rh Ag Ru Rh (Z=45) Mo Zr (Z=40) Tc 104Zr Nb Sr 98Y Y Kr 91Br Rb Se Br (Z=35) Ge 82Ge As Zn (Z=30) Ga 76Zn Ni Cu Co 70Ni Fe T. Kubo et al.

19 Z Z A/Q A/Q The first test experiment at RIBF 238U86+ 345 MeV/u
~ 1enA on Target Z Bρ: Tm Target: Be 7mm Total dose: ~1×1013 Total time: 25.4 hours Z=46 Z A/Q A/Q M.Bernas et a. PLB 331(94)19; PLB 415(97) 111

20 Discovery of 125Pd A/Q Cf. 124Pd 19 counts, 125Pd(cand.) 1count
A/Q resolution(r.m.s): 0.07% At Z=40 A/Q Cf. 124Pd 19 counts, 125Pd(cand.) 1count at GSI, 1997 PLB 415, 111 (97) total dose ~1x108

21 Setup for May-2007 Commissioning
Double Achromatic PL 0.2mmt PPAC(x,y) x2 Silicon 0.33 mmt x2 for DE NaI for E Clover for isomeric states Setup to search for new isotopes Double Achromatic PL 0.2mmt PPAC(x,y) x2 Mom. Slit Dp/p=2% (Max 6%) W/o Wedge Br TOF Prod. Target Be 7mmt Beam-intensity monitor PL 1mmt x 3 Momentum Dispersive PPAC(x,y) x2

22 Collaborators RIKEN Nishina Center T. Kubo (Spokesman), T. Ohnishi,
K. Yoshida, A. Yoshida, K. Kusaka, N. Fukuda, M. Ohtake, Y.Yanagisawa, H. Takeda, Y. Yamaguchi, N. Aoi, K. Yoneda, H. Otsu, S. Takeuchi, D. Kameda, T. Sugimoto, Y. Kondo, K. Tanaka, H. Scheit, Y. Gono, T. Motobayashi, H.Sakurai OECU, Osaka Y. Mizoi Rikkyo Univ M. Matsushita Univ. of Tokyo H. Suzuki, T. Nakao, H. Kimura Saitama Univ T. Kuboki, T. Yamaguchi Tsukuba Univ A. Ozawa, T. Moriguchi, Y. Yasuda Tokyo Inst. Tech. T. Nakamura, T. Nannichi, T. Shimamura, Y. Nakayama GSI H. Geissel, H. Weick ANL J. Nolen NSCL/MSU O.Tarasov, T. Nettleton, D. Bazin, B. Sherrill, D. Morrissey GANIL W.Mittig

23 Future plan 2007 18th June- Accelerator + BigRIPS Commissioning w/ U beam Sept.(plan) RIBF PAC At the beginning of Oct. ZeroDegree Commissioning Oct.-Nov. MT for approved experiments at the first PAC 2008 Prototype of new linac injector coupled with 28GHz ECR is being installed. Increase of U intensity and decouple bet. SHE and BigRIPS

24 SUMMARY PAC Feb 2007 19 proposals at BigRIPS/ZD, 74 % International Collaboration Commissioning of Accelerator System and BigRIPS is going smoothly step by step Discovery of new isotope 125Pd Experiments will start in this Oct.-Nov at BigRIPS/ZD. Next PAC this Sep. You are welcome Come to RIKEN and see what is going on.