Presentation is loading. Please wait.

Presentation is loading. Please wait.

HRM28-TCDI Updates June 24 th, 2015 Fausto Lorenzo Maciariello, F-X Nuiry, R. Ferriere, K. Karagiannis, M. Butcher, G. Vorraro, S. Le Fouest.

Similar presentations


Presentation on theme: "HRM28-TCDI Updates June 24 th, 2015 Fausto Lorenzo Maciariello, F-X Nuiry, R. Ferriere, K. Karagiannis, M. Butcher, G. Vorraro, S. Le Fouest."— Presentation transcript:

1 HRM28-TCDI Updates June 24 th, 2015 Fausto Lorenzo Maciariello, F-X Nuiry, R. Ferriere, K. Karagiannis, M. Butcher, G. Vorraro, S. Le Fouest

2 Outline Motivations Target Materials Manufacturing Plan Structural Verifications Cable Routing and Instrumentation Updates Alignment Procedure (Metrology and Survey) Schedule Global Budget Activities in Parallel 2

3 Motivations 1.Assess the Integrity of Graphite for TCDIs and TDIs during Run 3. The goal is to reproduce the worst accidental scenario that the TCDI and the TDI can see during their life time. 2.Test New Promising Materials for BIDs 3.Benchmark Simulations Temperature and Displacement Measurements foreseen. Boron Nitride 7000(???) Or Graphite R4710 Graphite R4550 3D C/C (Wrapping Process Technnique,1.7g/cm 3 ) 3D C/C (Plane Process Technique,1.7g/cm 3 ) 3

4 Manufacturing Plan Aluminum AW-6082 T6 Collimator support feet TCD Storage Aluminum AW-6082 T6 5 th axis TCD Storage Aluminum AW-6082 T6 Plug-in TCD Storage Stainless SteelVacuum tank MME Subcontracted Stainless SteelCollimator jaw housing and stiffener (Back Stiffeners and tightening clamps) MME Subcontracted/ TCD Workshop MaterialComponentsManufacturing Plan Rad-Hard GlassOptical windows Shott 4 BPMCERN - BI Electron Beam Welding for bellows carried out by the Main Workshop The assembly will be carried out by the TCD Workshop BPM SupportTCD Workshop

5 Plug Weld Verifications During Operation F ΔP=10 5 Pa The tank of the collimator is held by 4 plugs on its back. Those plugs are welded (TIG, not EBW like in the normal collimators), beads MUST be able to withstand the structural load coming from: 1.The weight of the collimator + tables (F) 2.The Atmospheric Pressure (ΔP) 5 Calculated Stresses [MPa] Limit Imposed By the Standards [MPa} S.F. 1034684.5

6 Screw Verifications During Tank Lifting F During the tank lifting the screws need to: a)Be able to withstand the structural load (max stresses below the ultimate strength) b)Assure there is not separation between the tank and the lifting plate The simulation allowed to calculate the maximum and the minimum preload to apply when fastening the screws. 6 Min Preload [KN] Max Preload [KN] 712

7 Weld Verifications During Tank Lifting The tank is welded internally (continuous TIG, a=2mm) and externally (tack welding: 40mm long beads every 80mm). The Equivalent V.M. Stress in the weld must be smaller than σ U.S. /1.25 Lifting Force 7 Calculated Stresses [MPa] Limit Imposed By the Standards [MPa} S.F. 846858

8 Weld Verification to Pressure Load ΔP=10 5 Pa 8 Calculated Stresses [MPa] Limit Imposed By the Standards [MPa} S.F. 624687.5

9 Subcontracted Tank-Functional Design Designer: R. Ferriere 9

10 Collimator Brakes Motors can create noises on the signal measured by the instrumentation, brakes will be integrated into the system in order to be able to switch off the motors during the measurement. 10

11 Cables Standard Electrical Cable: Experiment Specific Cables: Under Investigation by K. Karagiannis Responsible: M. Butcher 11

12 Instrumentation order status Vibrometer: Nearly ordered, then 10 weeks  1st September Fibres+feedthrough: 8 weeks from order Pyrometer: 5 weeks from order (supplier is now off work!) Radhard camera Delivered ! Brakes 5 weeks Responsible: M. Butcher 12

13 Adjustable Caliber The 3 screws of the adjustable caliber will allow positioning the Instrumentation perpendicularly to the target surface, guaranteeing the maximization of the signal received by the instrumentation during the measurements. Instrumentation Adjustable Caliber Jaws 13

14 Alignment Procedure Metrology: 1.Probe the Sphere 2.Measure the Theoretical Beam 3.Align the Jaw with the theoretical beam 4.Probe the instrumentation head 5.Instrumentation Angle Alignment (Instrumentation Head Axis need to be pointing to a line // to the theoretical beam): Output: Horizontal offset between the Instrumentation Head and theoretical beam 6.Alignment of the BPKG Axis with the theoretical beam Instrumentation BTV&BPKG BA7 Surface: 7.Align the theoretical beam with the beam (its supposed location) 14

15 Schedule 15 1 st TEST: Vacuum Jaw Movements Instrumentation …

16 Global Budget 16 ItemEstimated Budget [KCHF] Ordered or Received Items [KCHF] Tank703 Instrumentation190130 Tank Support10- Post Irradiation102 Test Tank303 Human Resources 14060 Targets10070 Total550268

17 Tank Remotely controlled valve to break the vacuum Pirani gauge Remotely controlled valve to insulate the pump form the tank Oil seal pump RV12 TPG300 PLC N2N2 Flexible pipe Pirani/Pirani card SEPARATEUR RV12 PC Responsible: Konstantinos Karagiannis Vacuum System

18 Tank Test 18 Responsible: Konstantinos Karagiannis

19 3D C/C Characterization Status Conclusions: X-Ray and Ultrasounds are not able to detect defects on these kind of materials Responsible: Sebastien Le Fouest 19

20 Conclusion 20 A decision needs to be taken on the target materials There is a clear manufacturing plan Structural calculations have been done for all the new features of the HRM collimator The most delicate point for the experiment is the alignment of the instrumentation Order and delivery of material is very well proceeding The Schedule and the Budget do not show discrepancies with the foreseen ones The tank test will be really useful for testing Instrumentation and acquiring experience 3D C/C characterization is on going

21 Thank you !

22 Device locations for HRMT 28 - TCDI 22 In the TJ7 bunker: The radiation-hard camera electronics + its PC In TT61: The PXI DAQ system The standard camera control box The vacuum pump A PLC for vacuum pump on/off control vacuum valve control (2) pressure readout eventual remote resetting of devices In the control room: User interfaces (Axis control, DAQ system control, PLC control, Camera control) The table control electronics The lighting power supply


Download ppt "HRM28-TCDI Updates June 24 th, 2015 Fausto Lorenzo Maciariello, F-X Nuiry, R. Ferriere, K. Karagiannis, M. Butcher, G. Vorraro, S. Le Fouest."

Similar presentations


Ads by Google