Presentation is loading. Please wait.

Presentation is loading. Please wait.

April 19, 2006A.Klebaner Cryogenics for ILC TA Current Status Plans and issues.

Similar presentations


Presentation on theme: "April 19, 2006A.Klebaner Cryogenics for ILC TA Current Status Plans and issues."— Presentation transcript:

1 April 19, 2006A.Klebaner Cryogenics for ILC TA Current Status Plans and issues

2 April 19, 2006A.Klebaner Current Status ILCTA MDB CapCav II CM conversion for 2K operation - 80% complete HTC cryogenics Feed box - done Pumping line - done Supply transfer line – 90% complete Controls – 60% Start the ILCTA_MDB vacuum pump commissioning – done Finish CTF purifier compressor commissioning - done

3 April 19, 2006A.Klebaner Current Status (cont’d) ILCTA NML Finish NML refrigerator room cleanout – 90% complete Send Lab B Mycom compressor piping contract out for bid – done Send out a bid package for He storage tanks repair - 90% complete Send out a bid package for He purifier - 90% complete Install NML heat exchanger – done done Refurbish FRICK compressor - 90% complete 90% complete Finish LN2 bayonet can design - done done

4 April 19, 2006A.Klebaner Plans and issues Plans –Finalize resource loaded project schedule –Finish the ILCTA_MDB vacuum pump commissioning –Finish NML refrigerator room cleanout and move in equipment (valve box, engines, etc.) –Start Lab B Mycom compressor piping –Send out a bid package for He storage tanks repair –Send out a bid package for He purifier –Start to connect NML heat exchanger to the valve box –Finish refurbishing of the FRICK compressor Issues –Resource availability

5 April 19, 2006A.Klebaner CCM as staging area

6 April 19, 2006A.Klebaner Frick compressor

7 April 19, 2006A.Klebaner NML LN2 bayonet can


Download ppt "April 19, 2006A.Klebaner Cryogenics for ILC TA Current Status Plans and issues."

Similar presentations


Ads by Google