Weddell Power Station unit three
Industry briefing Weddell Power Station unit three Johannes Rickermann Senior Development Engineer
2
Weddell Power Station Overview
3
Current view
4
Proposed expansion
5
Water treatment plant (RO-EDI)
6
Planned works packages
Main engineer, procure and construct (EPC) contract for supply installation and commissioning of heat recovery system including steam turbine Contract to integrate control system into Channel Island Power Station Yokogawa CS3000 system Contract to supply, install and commissioning 66 kV interface, station black start system and auxiliary electrical system Contract to augment the water demineralisation plant to add capacity and / or polish demineralised water
7
Local opportunities Electrical contract Control system integration
Subcontracting to main contractor for: Civil, earthworks, roads and foundations Piping / mechanical Electrical Steel works and structures others
8
Envisaged timeline Heat recovery and steam system advertised early July 2009 Control system integration contract advertised end of July 2009 Electrical contract planned to be advertised October 2009 Water demineralisation plant augmentation planned to be advertised October 2009 Plant completion planned for September 2011
9
Contract conditions Design and construct packages according to new NT-works contract EPC contract specifically tailored for this job Fixed lump sum turn key contract Milestone payments No Superintendent, Principal’s Representative Hard obligation to achieve time line and performance Risk of site condition on contractor except for latent conditions 2 years defects liability period Working under PWC permit system
10
Useful hints Register your capabilities with NTICN, www.nticn.com.au
Checkout tenders online on to become aware of future tender opportunities to know who downloaded the tender information