DeFoor Greenhouse Network Project
Group 2 Members: Jaris Tilstra Meir Shapiro
2
Outline Project Overview Employee Labor Costs Project Deliverables
Project Charter Stakeholder Registry Risk Register Probability/Impact Matrix Project Scope Statement Employee Labor Costs Project Cost Estimate Responsibility Matrix Comm. Management Plan Lessons Learned Project Assessment Questions * There is a notes section on some slides *
3
Project Overview Greenhouse is located at Tucumcari, New Mexico
Includes environmentally friendly energy sources Need to provide a computer for each office 10 monitors to measure temperature, humidity, and sunlight Needs to be operational in 12 weeks The budget is $100,000 The DeFoors were recently awarded a state grant that will enable them to set up a state-of-the-art greenhouse in Tucumcari, New Mexico. This greenhouse will include wind-generated electricity, geothermic heat exchangers, and light from solar tracking devices. The company has located a 27,000 square foot building to use as their first greenhouse. The building will contain one office for the bookkeeper, one for the sales manager, one for the greenhouse manager and a reception area. There will also be an internet connection to meet future company needs. There are 5 employees working on the project. 1 project manager, 2 full-time employees and 2 part-time employees.
4
Project Deliverables Project Charter Work Breakdown Structure (WBS)
Gantt Chart Cost Estimate Resource Assignments Communications Plan Risk Register and Matrix
5
Project Charter Project Sponsor: Mr. and Mrs. DeFoor
Project Start Date: 09/16/13 Projected Finish Date: 12/09/13 Project Manager: Jaris Tilstra Budget Information: $100k for labor and network components procurement. Project Team: Jaris Tilstra, Meir Shapiro, Tanishia Brown, Steve Williams, Elizabeth Smith Project Objectives To have a functional network set up within 12 weeks and under the $100k budget. The network will allow the company to monitor temperature, humidity, and sunlight in the greenhouse. 3 functional workstations for employees need to be connected to the network. Coordinate with the website project team to determine what web servers and internet connections will be available. Coordinate with the network construction team to determine if physical changes are necessary to implement the network.
6
Stakeholder Registry Name Role Position
Contact Information Mr. & Mrs. DeFoor Sponsor Owners Jaris Tilstra Project Manager Manager Meir Shapiro Team Member Network Engineer Tanishia Brown Steve Williams Elizabeth Smith Kevin Pham Consultant IT Director Jason Stanley PR Head Leslie Taylor HR Director Hailey Bucket Consultant Admin Assist.
7
Risk Register Rank Risk Description Category 1 Outdated wiring
The wiring and/or WAN is not suitable for the building Technology 2 Customers go elsewhere Customers could potentially go elsewhere for their produce Project 3 Installation takes too long Installation can take longer than expected Human Resources 4 Lack of experience The team members may have a limited amount of experience with this type of project 5 Shortage of network engineers With multiple projects going on there may be a shortage in network engineers 6 Monitor placement issues The setup of the greenhouse may not support the proper placement of monitors Hardware
8
Probability/Impact Matrix
High Risk 1 Risk 3 Risk 6 Risk 4 Risk 5 Probability Medium Low Risk 2 Low Medium High Impact
9
Project Scope Statement
Project Summary and Justification Summary of Project Deliverables Project Success Criteria Project Summary and Justification: Project charter was approved by the sponsors – Mr. & Mrs. DeFoor. Based on the recent grant received from the state we have been allocated $100,000 to design a network and procure the necessary hardware & software for the recently purchased building in Tucumcari, New Mexico. Summary of Project Deliverables: Management related: project charter, project scope statement, WBS, WBS dictionary, schedule, cost estimate, status reports, risk register & matrix, final project presentation, final project report, lessons-learned report Technology related: network design document, 3 workstations, 10 monitors, web servers, printers, support schedule for the onsite team Success Criteria: Design and support an attainable network plan that will stay within the $100,000 budget and will finish no later than 12/09/13 . Procure, setup and validate that all hardware and software for the workstations and greenhouse monitoring is functional. The Network should satisfy the needs and requirements of the project sponsor and stakeholders.
10
Gantt Chart
11
Employee Labor Costs 1.1 Initiation All Members $738 1.2 Planning
$5,715 1.3 Execution $44,492 1.4 Control $2,144 1.5 Closeout $1,191 Total: $54,280
12
Project Cost Estimate Subtotals WBS Level 1 Totals % of Total
Subtotals WBS Level 1 Totals % of Total WBS Items 1. Initiation $738 1% 1.1 Project manager $378 1.1 Project team members $360 2. Planning $5,715 6% 1.2 Project manager $3,965 1.2 Project team members $1,750 3. Execution $73,546 74% 1.3 Project manager $13,027 1.3 Project team members $31,465 1.3.3 Workstations Cost $4,500 1.3.3 Monitors Cost $8,053 1.3.3 Web Servers Cost $3,000 1.3.3 Printers Cost $1,500 1.3.3 Software Cost $12,000 4. Control $2,144 2% 1.4 Project manager $944 1.4 Project team members $1,200 5. Closeout $1,191 1.5 Project manager $566 1.5 Project team members $625 6. Reserves (20% of total estimate) $16,667 17% Total project cost estimate $100,000
13
Responsibility Matrix
WBS Activities 1.1.1 1.1.2 1.1.3 1.2.1 1.2.2 1.2.3 1.2.4 1.2.5 1.3.1 1.3.2 1.3.3 1.3.4 1.4.1 1.4.2 1.4.3 1.5.1 1.5.2 1.5.3 1.5.4 1.5.5 OBS Units Meir Shapiro P RP Tanishia Brown Elizabeth Smith Steve Williams p Jaris Tilstra Key: R = Responsible organizational unit P = Performing organizational unit 1 DeFoor Greenhouse - Network 1.1 Initiation Identifying Project Stakeholders Project Charter Kick-off Meeting 1.2 Planning Requirement Gathering Preliminary Scope Statement Develop WBS Identify Risks Develop Schedule 1.3 Executing Verify & validate User Requirements Design Building Network Procure Hardware / Software Contact vendors for quotes Order Software & Hardware Support On-Site Team Greenhouse Operational 1.4 Controlling Project Status Meetings Progress Reports Control Changes 1.5 Closing Client Acceptance Lessons Learned Meeting Lessons Learned Report Archive Project Documentation Project completed
14
Communications Management Plan
Stakeholders Document Name Document Format Contact Person Due Date DeFoor Network Project Team Weekly Schedule Box Jaris Tilstra Mondays Bi-Weekly updates to the communications plan 1st and 3rd Mondays of the month Internal management Monthly status reports and meeting First of the month Internal technical staff Steve Williams Customer business staff Hard copy Tanishia Brown Customer technical staff Tanisha Brown Network Installer Network Implementation Plan Meir Shapiro November 10, 2013 Comments: Put titles and date of all documents in headings and have all recipients acknowledge receipt. Change headings and subject lines as necessary. Introduction – The purpose of this communications plan is to describe the means with which information will be shared regarding the DeFoor Network project. This plan details the different aspects of communication regarding the project and should be used as a guide for communicating with the right people at the right time in the right format. Target Audiences – DeFoor Network Project Team – Includes the members actively involved in the project. Internal Management – DeFoor Managers Internal Technical Staff - Staff in charge of internal IT. Customer Business Staff – Staff in charge of business matters. Customer Technical Staff – Staff in charge of customer technical issues. Network Installer –Person in charge of installing the new network. Collection and filing structure – The file collaboration website that will be used for this project is the “Box” ( Jaris Tilstra will be sending out Box invites for this project. Simply follow the instructions in the invite. This will be the site that holds all relevant files and reports related to this project. Distribution structure – Follow the Stakeholder Communications Analysis table below which depicts which information goes to whom and when. See the media choice table document that is under the communication folder on the Box for choosing the correct media for the correct situation. Format, content, and level of detail of key project information – We will be using the communications templates found under the communications folder on the Box. This template will tell you what format, content, and level of detail to use. If a section is not relevant for the report leave it in the proper place with a notation why there is no relevant information. Production schedule and resources for producing key project information – The schedule and resources will be found on the Box that is updated every Monday. Technologies, access methods, and frequency of communications – We will be using the following communication tools for this project: Box - For file sharing – For collaboration, reports and plans. Hard Copy – For specific reports and plans. Meetings – For weekly meetings, monthly meetings, collaboration & Microsoft Lync (instant messaging & video chat) – Daily discussions & collaboration. Phone – As necessary (See the media choice table document). The frequency of communications is variable depending on needs. There are also set dates in the stakeholder communications analysis below. Method for updating the communications management plan – The communications management plan will be reviewed and/or modified on a bi-weekly basis. If you have any input to the plan, please add to the punch list on the Box and it will be reviewed and either accepted or declined. Escalation procedures – We will run all external issues from Mr. and Mrs. DeFoor through our customer service team. Depending on the severity of the issue, the customer service team will then send out an to the appropriate people so the issue can be resolved.
15
Lessons Learned Make sure everyone involved in the project understands and agrees with the objectives an requirements of the project. Set deadlines for review and signoff of weekly deliverables Make sure to subscribe to the forum as soon as possible Be active in the forum early on every week so you are not rushed at the end. Get to know your team members better
16
Project Assessment Hardest Parts Easiest Parts
Understanding the project requirements Learning MS Project Assigning resources in MS Project Losing a team member during the project Communicating with group team members Team members each put their fair share of workload to the project Were able to have our deliverables submitted on time
17
Questions?