Presentation is loading. Please wait.

Presentation is loading. Please wait.

Bob Dedalis, HST Payload Safety Manager

Similar presentations


Presentation on theme: "Bob Dedalis, HST Payload Safety Manager"— Presentation transcript:

1 Hubble Space Telescope Servicing Mission Four (HST SM4): Unique Challenges for STS-125
Bob Dedalis, HST Payload Safety Manager Miranda Cooter, HST Lead Flight Safety Engineer Patrick Mitchell, Payload Safety Review Panel Executive Secretary William Hill, HST Lead Ground Safety Engineer Phillip Adkins, Systems Safety Engineer

2 Introduction Mission Overview
SM4 first time in seven years HST serviced Nominal design called for once every 3 years More new hardware than any previous mission SIC&DH added very late First time since Columbia a shuttle was not used for ISS construction

3 Major Tasks Impact to Hubble Task Install WFC3 – Wide Field Camera 3
Installed a high-resolution/wide-field camera with continuous coverage of wavelengths or colors of light from the ultraviolet to the near-infrared. Install COS – Cosmic Origins Spectrograph Installed the most sensitive ultraviolet spectrograph ever to fly on HST. Repair STIS Restored the Space Telescope Imaging Spectrograph to operational status by replacing circuit boards. Repair ACS Restored critical scientific functionality to the Advanced Camera for Surveys by replacing power supply and circuit boards. Replace Rate Sensor Units (RSU) (gyroscopes) Completed change-out of all six gyroscopes, the heart of HST's pointing system, and HST's main wear-out items. FGS - Fine Guidance Sensor Last in a series of changed-out units that allow fine pointing of HST. Replace Batteries Replaced the six batteries originally launched with Hubble in 1990, which are steadily losing capacity as they age. Install Soft Capture and Rendezvous System Installed the Soft Capture Mechanism on the bottom of Hubble to enable NASA to pursue options for the safe disposal of Hubble. Install New Outer Blanket Layers (NOBLs) Installed NOBL covers to thermally protect the exterior blankets and maintain normal operating temperatures of Hubble's electronic equipment. Replace Science Instrument Control & Data Handler (SIC&DH) unit Replaced the original unit launched with Hubble in 1990 to insure redundancy of operations after September 2008 failure of Side A Control Unit/Science Data Formatter (CU/SDF).

4 Payload Bay Equipment Four Full Equipment Carriers
Science Instrument Control and Data Handling Unit Flight Support System pivots and rotates to enable in-bay servicing Four Full Equipment Carriers Included a servicing platform

5 Payload Safety Review Process
Hazard Report Verify Hardware As Built Implement Controls Payload Organization Concurrence NSTS Safety Review Phase III Delivery Flight Safety Verification Tracking Log Track Verification of Items To Be Conducted After Phase III Review Payload Organization Approval NSTS Review Hazard Report Verify Design Implement Controls Payload Organization Concurrence NSTS Safety Review Phase II CDR Hazard Report Identify Hazard Controls Payload Organization Concurrence NSTS Safety Review Phase I PDR Preliminary Hazard Reports Identification of Hazards Safety Review Phase 0 Design Concept Update Only Update Only For Each Hazard

6 Hazard Identification Process
Postulate Failure (PHA/FMEA/FTA) NSTS Requirements Change Design Not Approved System/ Sub-system/Interfaces Hazard to Crew/STS Requirements Met Perform Hazard Assessment Write HR Yes No Critical No Yes (Generic Hazard) Catastrophic Confirm Fault Tolerance or DFMR in Design/Operations No Hazard Write HR Review with JSC Approved 1 Fault-Tolerant 2 Fault-Tolerant Redesign Write HR Verify Controls * ARHR (Accepted Risk Hazard Report): New to the PSRP documentation process for SM4. Method for Shuttle program to accept the risk of safety non-compliant conditions ARHR * Document for CoFR 4/25/2017

7 Final Flight Safety Post Phase III/Part 4

8 Safety Challenges Soft Capture Mechanism (SCM) Batteries
Late addition of Science Instrument Control and Data Handler (SIC&DH) Complex on-orbit Repairs STIS Advanced Camera for Surveys (ACS) Lack of Shuttle Safe-Haven Increased chance of on-orbit debris

9 Soft Capture Mechanism and Battery Isolation Switch
Miranda Cooter

10 Soft Capture Mechanism
Designed to enable controlled de-orbit HST originally designed to be returned in payload bay HST does not have propulsion system Installed onto Aft Shroud Flew on FSS between HST and FSS support ring Was risk of connecting HST to FSS via SCM (inability to close shuttle payload bay doors) Systems Safety participated in initial design Performed Initiating Event Tree Analysis Insured that each major function included crew-activated override

11 Soft Capture Mechanism
Berthing Latch outside SCM attach mechanisms Servicing Platform Soft Capture Mechanism Berthing Latches and SCM Attach Points Crew-Activated Remote Drive Soft Capture Mechanism Detail on Next Slide

12 SCM Mechanism Detail Radial Out View Radial In View FSS Override Assy
HST Release Override HST Attach Override FSS Release Override FSS Override Assy FSS Attach Override Sill Plate Adapter

13 Final SCM Fault Tolerance
Separated Mission Success issues from Safety concerns Mission Success is single fault tolerant Flight Safety must be dual fault tolerant

14 Batteries Launched charged Battery Isolation Switch (BIS) Installed
88 amp-hour batteries Nickel Hydrogen Battery Isolation Switch (BIS) Installed COTS product Based on military headlight switch Not designed to be fail-safe Barrier Analysis applied Battery Isolation Switches (BIS)

15 BIS Design

16 Modifications to BIS BIS Not Fail-safe Conducted Hazard Analysis
Failure causes switch to be closed (i.e. ON) Identified as a safety issue Conducted Hazard Analysis No Backaway prevention on handle Possibility of Whiskers Cadmium and Zinc coatings Potential for “hot” handle if internal failure Not visually identifiable to crew Hazard process improved design Staked handle fastener to prevent backaway Detailed analysis of potential for whiskers Found whiskers in non-flight version of BIS Through analysis & test, determined that, for this design, whiskers cannot sustain arc Added non-conductive paint to handles

17 IMAX Accommodations and Science Instrument Control and Data Handling
Phillip Adkins

18 ORUC with IMAX Accommodations

19 Steps to Certify IMAX Previous IMAX flights reviewed with new analysis/testing done as needed Proof Pressure Testing Vibration Functional Test Thermal Vacuum Test New Carrier Electrical Harness IMAX presented as a separate reflown payload

20 MULE Picture

21 Late Addition of SIC&DH
Reduced time for final certification Six month certification cycle Flight safety closely integrated with design and development to insure success Safety documentation available from unit certifications

22 EVA Safety Considerations
Bill Hill

23 Extra-Vehicular Activities (EVA)
Included instrument and equipment exchange Done on each previous servicing mission New techniques and tools developed for on-orbit, in situ repairs of instrument Highly complex operations Required specially designed tools to enable delicate repairs to circuit boards tailored to crew needs Flight safety engineers participated in tool development beginning with design

24 EVA Timeline Five long days of EVA with four astronauts participating

25 Tool Development Process
Tools Developed and designed with crew and safety participation Design and development includes full review and verification

26 STIS Repair Tools

27 FCP After Removal On-orbit

28 Shuttle Specific Challenges
Patrick Mitchell

29 Shuttle-Specific Safety Challenges
ISS was not available for Safe-Haven Launch-on-need (LON) shuttle processed and available for rescue Enhanced Micro-Meteorite On-orbit Debris (MMOD) Risk Shuttle flew protected attitudes when HST specific operations permitted Shuttle inspections performed Tile inspections performed before and after servicing Insures no damage during ascent or from MMOD

30 Launch On Need STS-400

31 Solutions Applied Safety Systems Analysis Techniques Used
Initiating Event Tree Analysis (IETA) Barrier Analyses Fault Tolerance Analyses JSC Safety Requirements and Processes Safety engineer integration into hardware design teams resulted in safe hardware by design Successful application of System Safety techniques contributed to a successful Servicing Mission

32 HST After SM4 Deployment


Download ppt "Bob Dedalis, HST Payload Safety Manager"

Similar presentations


Ads by Google