Qualcomm Stadium Project Devin Cardoza July 12, 2004 GBA 573
2
Project Details: ► Install hard-wired consoles into all of Qualcomm Stadium’s 70,561 seats. Instant messaging Online voting Order from snack bar Access stats from other games View instant replays
3
Why? ► Qualcomm’s archaic design makes it harder to compete with newer, modern stadiums Reduced revenues due to lower attendance Can’t justify higher ticket prices Due to lack of revenues, Chargers may move. Good cost/benefit based on assumptions made
4
Scope: ► To install consoles in every seat in the stadium ► Installation must be completed by start of 2005 football season ► Start project after Superbowl (7 month period of performance)
5
3 Phases: ► Find and purchase hardware ► Installation Phase ► Test & Training phase
6
Assumptions: ► 3% increase in attendance 61,521 average in 2003 ► 5% increase in ticket prices $46.82 average in 2003 ► 5% increase in snack bar prices $10 average per person
7
Assumptions (contd.): ► $500,000 for hardware ► 2 weeks to search for vendor and place purchase order ► 15 People over 90 days to install ► 1 Week to test ► 2 weeks to train 700 employees ► $25,000/year for ongoing tech. support ► Management involvement for 7 months
8
Forecasted Costs Cause of ExpenditureCost Purchase Hardware$500,000.00 Supplier Selection$2,200.00 Installation$216,000.00 Testing Phase$10,000.00 Training$58,000.00 Ongoing Technical Support$25,000.00 Management Support$98,700.00 Total Costs:$909,900.00
9
Forecasted Annual Benefits BenefitIncreased Revenue 3% Increase In Attendance$725,849.37 5% Increase in Ticket Price$1,152,165.29 5% Increase in Price of Snack Bar Items$270,692.00 Total Increased Revenue:$2,148,706.65
11
ROI:
12
Risks: ► Schedule slippage causes implementation to be incomplete by ’05 season ► Budget rises due to unforeseen events ► Estimates are exaggerated ► Fans don’t use the new equipment
13
Mitigation: ► Use Earned Value Management ► Progress Payments ► Make consoles user friendly, electronic instructions to guide throughout the process ► Stick to a communication plan with the project team
14
Measures of Success: ► Attendance increases by 3% ► Snack bar revenue increases by 5% ► Project finishes before 2005 season & within budget ► ROI of at least 240% after 3 year period
15
Final Analysis: ► Great return on investment ► Enhanced experience for the fans ► Will create a higher revenue stream ► Will help to keep team in town until new stadium can be built