The City of Orlando Orlando Police Department Headquarters, Crime Scene Facility and Equestrian Center
2
Project Facts Three separate projects
Orlando Police Department Headquarters Crime Scene Facility Equestrian Center H. J. High Construction
3
The Design Build Team H. J. High Construction
4
Project Facts The Orlando Police Department Headquarters
Approximately $30 million Located on the corner of Orange Blossom Trail and South Street Scope of work includes demolition of existing buildings and construction of new facility H. J. High Construction
5
Project Facts H. J. High Construction
6
Project Facts Crime Scene Facility Approximately $10 million
Located on Andes Avenue at the Orlando Executive Airport Scope of work includes renovations and remodeling of existing facilities H. J. High Construction
7
Project Facts Equestrian Facility Approximately $500,000
Located on Andes Avenue at the Orlando Executive Airport adjacent to the Crime Scene Facility Scope of work includes new horse stables and training area H. J. High Construction
8
Project Facts M/WBE Participation is encouraged
18% MBE, 6% WBE requirements Living Wage requirements LEED Silver Compliance Every subcontractor will be prequalified H. J. High Construction
9
Schedule Bid: Construction: Jan/Feb 2015 March 31, 2015 Bid:
Dec Jan Feb Mar Apr 2015 OPD Headquarters Facility Crime Scene Facility Equestrian Center Bid: Jan/Feb 2015 Construction: March 31, 2015 Bid: Dec/Jan 2015 Construction: Feb. 25, 2015 Bid: Dec/Jan 2015 Construction: Feb. 25, 2015 H. J. High Construction
10
How to Be Involved Contact H. J. High Construction to receive a Prequalification Form Cheri Grayson, Estimating Assistant H. J. High Construction