SPIS-Elena - Tramways in Skåne Light rail day, 8 november 2011 Marcus Horning, project manager, SPIS-Elena
2
Background the SPIS collaboration Common study (2007). Region Skåne, Malmö, Lund, Helsingborg and the National Railway Administration Analyzing: Expected passengers Economy City development Physical conditions in the cities Environmetal effects Congestion Regional development
3
Background the SPIS collaboration Cooperation is formalized in 2010 with political steering committee Partners: The Region of Skåne and the cities of Malmö, Lund and Helsingborg, in Sweden. The SPIS investment programme consists of the coordinated planning and implementation of a new tramway network in Lund, Malmö and Helsingborg.
4
Why joint venture? Rather small systems in each city One common system in the future Common maintenance and operation in the future Joint procurement – larger volume, better price The same technique for track and vehicles The same design principles The same design guidelines
5
Main projects in the SPIS- collaboration New tramway line in Lund Number of lines: 1 line Number of stops: 9 New trams: 8 New tramway lines in Malmö Number of lines: 2 lines Number of stops: 35 New trams: 23 New tramway line in Helsingborg Number of lines: 1 line Number of stops: 13 New trams: 11
6
Elena application fall 2010 ELENA application sent to EIB December 2010. May 2011 – application granted 3,3 million euro til May 2014 90 % Elena 10% divided by all parties 25 times the leverage factor must be met before project period ends - this means an investment of 83 million euro Main purpose – to achieve energy efficient public transport!
7
Elena application fall 2010 – energy savings
8
Aims and goals - with SPIS-Elena Energy efficient light rail in Skane – sustainable development Optimize the cooperation of the partners involved and the implementation – save time and money Investigate common questions – create synergy, one plattform Collectively communicate the project - open source
9
Consortium organisation Tramways in Skane Political steering committee of SPIS Head of chief committe of SPIS WP 1 Project management of SPIS-Elena WP 2 Vehicles WP 3 Financing WP 4 Design WP 5 Main- tenance WP 6 Communication
10
Staff and SPIS-office Recruting staff Project manager (100%) Controller (50%) Tendering expert (100%) Tram expert (100%) Project strategist (50%) Communicator (100%) Project coordinator 1 (100%) Project coordinator 2 (100%) Project coordinator 3 (100%)
11
WP 1 Project management of SPIS-Elena Project plan - Content Coordinate and lead the work Define administative processes Budget and timeframe Reporting Budget - 142 000 euro
12
WP 2 Vehicles Project plan - Content Investigate system for – energy, technique, electricity etc Defining maintence approach Support for tendering preparation Tendering Ordering Budget - 310 000 euro
13
WP 3 Financing Project plan - Content Financial strategy Different financing alternatives Negotiation package Successive calculation Investigation – traffic, stages, financing sources, alternative costs etc Budget - 180 000 euro
14
WP 4 Design Project plan - Content Largest package Links all WPs Develop common standards – optimize together not seperatly Define the most energy effective design – support model split to energy efficient public transport Budget - 950 000 euro
15
WP 5 Maintenance Project plan - Content Long term package Joint maintenance system – energy and resource effective life cycle Innovative quality system – secures a reliable and attracitve system support the modal split 60 000 euro
16
WP 6 Communication Project plan - Content Joint communication strategy – better effect, exchange of knowledge, effective use of resources Strategy which connects goals, challanges and opportunites Communication plans – different target groups (Budget – 200 000 euro not Elena funding)
17
Time plan WP 1 Project managment WP 2 Vehicles WP 3 Finance WP 4 Design WP 5 Maintenance WP 6 Communication 2011201220132014 MajJuni Today EIB report
18
Thank you