Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Paper 0622 TOWARDS SELF-HEALING POWER DISTRIBUTION BY MEANS OF THE ZONE CONCEPT Antti Kostiainen, ABB Oy, Finland, Presenter Pekka Manner, Fortum Oyj, Finland Kari Koivuranta, Fortum Oyj, Finland Göran Wiklund, ABB Oy, Finland
2
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Principles of the Zone Concept Network control center
3
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Self-healing network IEC 61850 Network topology Communication Fault location Remote controllable devices
4
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Power reliability indices of the pilot case Power reliability indices of the two pilot feeders in 2010 MAIFI 10,78 pcs /customer SAIDI 7,2 h /customer SAIFI 18,85 pcs /customer
5
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Feasibility of the pilot (ph.1) investment Total investment of the pilot case is 134 000 € * Customer Interruption Costs YearsTotal CIC* savings in € Profitability in € 128 000- 106 000 255 000- 80 000 379 000- 56 000 4101 000- 33 000 5122 000- 12 000 6142 0007 000 7159 00025 000
6
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Case: System operation during a fault Masala area has 20 remote controlled disconnector zones (red areas) Masala area has two remote controlled re- closer protected zones (blue areas) 110 kV 20 kV
7
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 [0 s] A fault occurs Case: Fault occurs 110 kV 20 kV
8
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Case: Re-closer tries to clear out the fault [0 s] A fault occurs [1 s] remote re-closer operates 110 kV 20 kV
9
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Case: The system locates the fault [0 s] A fault occurs [1 s] remote re-closer operates [10 s] The system analyses and localizes the fault 110 kV 20 kV
10
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Case: The fault is isolated in 1 min [0 s] A fault occurs [1 s] remote re-closer operates [10 s] The system analyses and localizes the fault [1 min] remote controlled disconnectors isolate the end of the feeder 110 kV 20 kV
11
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Case: Back-up restoration in 2 min [0 s] A fault occurs [1 s] remote re-closer operates [10 s] The system analyses and localizes the fault [1 min] remote controlled disconnectors isolate the end of the feeder [2 min] remote controlled disconnector restores the power from another feeder 110 kV 20 kV
12
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Case: The service crew fixes the fault [0 s] A fault occurs [1 s] remote re-closer operates [10 s] The system analyses and localizes the fault [1 min] remote controlled disconnectors isolate the end of the feeder [2 min] remote controlled disconnectors restore the power from another feeder [~100 min] the service crew fixes the fault 110 kV 20 kV
13
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Case: Results 3 zones suffered an outage of <2min 1 zone suffered an outage of ~100 min Without the advanced system, the fault would have been located with time consuming trial & error method total outage ~200 min ~1 min ~2 min ~100 min 0 min 110 kV 20 kV ~1 min
14
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Accurate fault location, including also earth faults, is crucial for fast fault isolation Fast fault isolation enables fast power restoration SAIDI improvement Local automation confines the impact of a network fault to the limited area SAIFI improvement Utilize all ”senses” and use them to support each other. Conclusive statements
15
Frankfurt (Germany), 6-9 June 2011 KOSTIAINEN– FI – S3– 0622 Thank You for your attention