Download presentation
Presentation is loading. Please wait.
Published byNorah Barton Modified over 9 years ago
1
Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli, Bruno Puccio.
2
LHC status 2 18/01/2008 Objectives All required hardware systems tested All required instrumentation deployed and tested Machine Protection system tested & qualified. All software deployed and required functionality tested Control system integrity tested Full integration tests performed with all systems driven through operational cycles Clear that when we finally get beam we don’t want to waste time solving problems that could have been resolved before. Get ready for first beam
3
LHC status 3 18/01/2008 Conditions Cool-down of remaining sectors Extensive Hardware Commissioning of circuits Installation of remaining components Individual system commissioning Roll out of controls infrastructure Roll out of beam interlock system Roll out of beam instrumentation Software development and deployment, roll out of magnet model etc… Commissioning of access system (DSO tests etc.) While starting-up and operating SPS/PS etc.
4
LHC status 4 18/01/2008 HWC - baseline Cooling and Ventilation Cryogenics Plant Cryostat Instrumentation Electrical Network Beam Vacuum [warm & cold] QRL Vacuum Insulation Vacuum Powering Interlocks QPS and energy extraction QRL Instrumentation Access Survey/Alignment
5
LHC status 5 18/01/2008 Incoming this session Cryogenics Magnets/circuits Vacuum Injection system Beam Dump System Collimators RF Beam Instrumentation Machine protection … Some how pull this lot together to give us a operational machine
6
LHC status 6 18/01/2008 Approach Define objectives and prioritize (as usual) Individual System Tests/ Hardware Commissioning Equipment groups/HWC team Individual high level control tests From CCC using controls infrastructure and software Check the functionality of the individual systems Integration tests (dry runs) + HWC/PGC Partial machine checkout Machine Protection commissioning Full machine checkout Try and document it – something we’ll have to do every year
7
LHC status 7 18/01/2008 Approach
8
LHC status 8 18/01/2008 Comments There’s a lot going on the same time This not going to be particularly tidy or particularly easy Accept dry runs as a debugging exercise Accept it won’t be perfect first time Iterate [but at an appropriate frequency] Look for robust solutions that follow established standards.
9
LHC status 9 18/01/2008 Integration Tests (Dry Runs) Multi-system tests to check integration and readiness of all systems involved in a given phase of LHC operations: Check data acquisition chain Check all equipment control functionality Check timing and low synchronization Check functionality of the control system from CCC high level applications. Drive all relevant systems in a synchronized way through the standard operational sequence Check machine protection and interlock systems Organization Coordinated by Operations. Preparations for, and results of, dry runs to be discussed at LHCCWG. In close collaboration with equipment groups, technical issues to be discussed in ABCIS meetings. Seen as a prelude to full system tests to be performed before beam. Debugging – establishing control & integration from the CCC
10
LHC status 10 18/01/2008 Objectives- Instrumentation Priority Conc Settings State Logging PM SIS MCS Application FDisplay Daemon BPM [D,I] 1XXXXXX BLM 1XXXXXXX BCT [DC, FD, FR] 1XX BTV 1XXXXXX Rest Gas [BGI] 3XXXXX Sync. Rad [BSRA] 1XXXXXX Wire Scanners [BWS] 2XXXXX Luminosity [BRA,S,G] 1XXXX Tune [BQBBQ] 1XXXXXX Tune [BQHT] 2X AGM [BSRA] 2XX Schottky [BQS] 2XXX BST [BOB] 1
11
LHC status 11 18/01/2008 Application XPOC Analog Acquisition Alarms SIS MCS PM Timing RBAC INJECTION KICKERSXXXXXXXX BEAM DUMPXXXXXXXX POWER CONVERTERSXXXXXXX COLLIMATORSXXXXXXX RFXXXXXXXX TRANVERSE FBXXXXXX MAGNETSXXXX MKQA etcXXXXXX WARM MAGNETSXXXXX RADIATION MONITORSXX SPECTROMETERSXXX Objectives - Hardware
12
LHC status 12 18/01/2008 Objectives - Controls Slow timing, fast timing, synchronization Alarms, logging, post mortem, fixed displays Equipment control & access Real-time feedback system Analogue acquisition Software: measurements, trajectory acquisition and correction, ramping etc. etc. Controls infrastructure: servers, databases etc. Software Interlock System Management of Critical Settings Role Based Access Control
13
LHC status 13 18/01/2008 Objectives – Deploy and Test LSA Core Functionality Optics, ramp, squeeze, magnet model (transfer functions etc.) Equipment Instrumentation Measurements Operational exploitation Timing On-line Models MADX, FIDEL, Aperture Mode, data distribution Applied LSA applications Orbit, luminosity scans etc. Data exchange
14
Proposed Integration Tests
15
LHC status 15 18/01/2008 Injection/Transfer Dry Run Kickers control, monitoring, logging, settings, FD Timing & synchronization Events, tables, telegrams, injection requests RF pre-pulses Instrumentation Acquisition, logging, control, FD, timing etc. for Screens, BLMs, BPMs, BCT Applications YASP (threading, etc) Injection Quality Checks Modes Injection and dump, Circulate and dump, Nominal Injection TDI Controls RBAC, MCS, Mode, DIP BIS
16
LHC status 16 18/01/2008 Injection & Transfer
17
LHC status 17 18/01/2008 Injection, Ramp & Squeeze Dry Run Injection, ramp, squeeze, ramp-down, pre-cycle Settings - full LHC parameter space Power converters, RF, Collimators FIDEL Bumps, experiments’ magnets Trims Actual and function – full parameter space Control RF units, cavities, loops etc., FGCs… Collimator – set, functions, limits etc. Applications & Tools YASP, sliding bumps Multi-turn acquisition and analysis Instrumentation Sequence, mode Power converters in SIM_VS
18
LHC status 18 18/01/2008 Beam Dump Dry Run LBDS Monitoring, GUI, trigger, IPOC XPOC BETS Timing Sequence Re-arm Monitoring Logging, fixed displays, alarms, MCS BIS Permit loops, PM suppression etc. Dump line and point 6 instrumentation Abort gap, RF TCDQ/TCS settings and control
19
LHC status 19 18/01/2008 Instrumentation Every BI SW responsible will organize the continuous assessment of its instruments, ie find/organize time slots, also outside official dry runs, where conditions allowing to test functionality [see JJG] Maintain the dashboard info up to date (color scheme and details on the box dedicated page) and prepare battle field for the next iteration
20
LHC status 20 18/01/2008 Beam Loss Monitors - acquisition & concentrationroll out Beam Loss Monitors - XPOC, Post mortem, study bufferstest, test, test Beam Loss Monitors - Loggingroll out and test Beam Loss Monitors – OP displayops Beam Loss Monitors – expert applicationTo spec Beam Loss Monitors – MCS – configuration & tests – threshold management MCS, application and test Bunch Current Transformers acq & display BCTDCLHC & BCTFDLHC & BCTFRLHC Acq, log, FD Instrumentation - DR 1/3 Find/organize time slots, also outside official dry runs where conditions allow testing of required functionality Play simulated injection, ramp etc… Plus dedicated dry runs
21
LHC status 21 18/01/2008 Instrumentation – DR 2/3 BPM: acquisition & concentration & publish All modes: capture, FIFO, orbit Logging, SDDS, roll out and test BPM: acquisition, log, displayRoll out BPM: trajectory and orbit correctionYASP BPM: multi-turn analysisApplication - test BPM: beta beating analysisApplication – deploy and test BPM: real time feed backDeploy and test BPMDLHC - dump line BPMXPOC BPMITLHC – interlocked BPMsAcq/BIS, XPOC BTVI/BTVMLHC Screens (matching monitors)Acq, Control, BIS
22
LHC status 22 18/01/2008 Instrumentation – DR 3/3 Tune/kickers (tune, aperture, AC dipole) control- acq – timing- applications – deploy and test Radmon (TW)acq – conc - display BQHTLHC – head-tail Chromaticity BSRALHC Abort gap monitorDeploy & test BSRTFLHC/BSRTSLHC Synchrotron radiation monitors Deploy & test BGILHC – Rest Gas MonitorDeploy & test BWSLHC Wire ScannerDeploy & test Wall Current Monitors (RF)Talk to Andy BQSLLHC - SchottkyDeploy & test BRASCLHC/BRASGLHC - Luminosity monitorsApplication++ +LSA
23
LHC status 23 18/01/2008 Physics/Experiments Dry Run Luminosity Acquisition and display, BRA application Optimization, trims, bumps etc. Scans Experiment Instrumentation & signals BCMs, Lumi etc. Experiment communication DIP – to & from Vetos Interlocks Beam abort, injection inhibit Magnets Alice/LHC dipoles and compensation
24
LHC status 24 18/01/2008 Physics
25
LHC status 25 18/01/2008 Beam Interlock System Complete the IST of the BIS by April. This will be carried out by the BIS team (independently of the HWC). Perform the Commissioning of the BIS in // with the HWC. Tricky - involves all LHC systems: Experiments, COLL, VAC, BLM, other Beam Instrumentation, RF, Access, and so on... BICs are installed either side of IP, done for each one of the 8 points. 8 periods of ~5 days (or twice 2,5 days) during the HWC. Either inserted before the Powering tests or just after them. The possibility to have a sector(s) test is going to be taken into account in trying to give priority to points 8, 7 and 6 (or 2,1,8). Perform a final test- dedicated week during the cold-check period. Concerning dry-runs, we have recently installed 2 more BICs in point 6 in order to participate to the LBDS dry-runs in // with our BIS commissioning. The goal is to do NOT disturb our commissioning and move ahead with the interfaces with you, the Timing and the Kickers. c/o Bruno Puccio
26
LHC status 26 18/01/2008 Machine Protection Dry Runs As part of other dry runs Injection kickers LBDS – link to BIS, protection devices Integration in machine cycle Resets, tests, SBF, SBP, BPF Interface to timing system/BST PM suppression Link-Unlink Injection inhibit Experiments
27
LHC status 27 18/01/2008 PGC as part of circuit HWC Allows us to test & check: LSA settings generation Optics Injection - Ramp - Squeeze - Ramp-down - Pre-cycles Parameter space (Q, Q’, bumps, harmonics…) Magnet Model (FIDEL) Calibration curves Harmonics, decay, snapback Corrections Sequencing machine cycle Power converter functionality Power converters Tracking, control, ramping, squeezing (constraints), real-time
28
LHC status 28 18/01/2008 Collimation Dry Runs Full control system functionality Machine cycle Injection versus intensity Ramp, limits, Squeeze Trim Parameter space, limits Interface to BIS Monitoring, logging, FD, alarms etc Optimization procedures Interface to BLMs etc.
29
LHC status 29 18/01/2008 Partial Machine Checkout Possible pre-cursor to sector test Injection & dump N sectors through full machine cycle plus RF & Collimators All distributed instrumentation from N sectors All available stand alone instrumentation All relevant software/controls Beam Interlocks One week given extensive dry runs
30
LHC status 30 18/01/2008 Integration & commission Good for sector test/first turn
31
LHC status 31 18/01/2008 Full Machine Checkout
32
LHC status 32 18/01/2008 So far… Injection dry run – December 2007 Beam dump dry run – February 2008 PGC 4-5 – February 2008 LHCb – November 2007 Alice – February 2008 Acknowledgements: BT, BI, ATB, OP, CO, PO, HWC
33
LHC status 33 18/01/2008 Injection Dry Run – December 2007
34
LHC status 34 18/01/2008 Beam Dump Dry Run – February 2008 Verena Kain
35
LHC status 35 18/01/2008 PGC – “HWC shadowing” – February 2008
36
LHC status 36 18/01/2008 Residual Saturation MDC Geometric PGC – deployment of FIDEL
37
LHC status 37 18/01/2008 Plans - March
38
LHC status 38 18/01/2008 Plans - April ++
39
LHC status 39 18/01/2008 Conclusions Individual system commissioning from CCC Integrations tests (Dry Runs) Partial machine checkout Full machine checkout When the going gets tough, the tough get operational. We have a plan…
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.