1 Ganda ERP Project | ERP Project Status Report for CFC Apr 2014

2 Ganda ERP Project | Current ERP Project Progress and Achievements 1 CG ERP Jan-2014 accounting period have been generate 1 st ERP Financial Report on 07 th - Mar-2014. Feb-2014 accounting period month-end activities have been completed, Now is processing Mar-2014 accounting period month-end activities. SAG ERP Jan-2014 accounting period month-end closing process was complete, now is doing cost value check and fine tune for Feb-2014. At the same time Mar-2014 month-end process have been started. Motive Mulia ERP project have already been kick-off on 11-Mar-2014 and complete operation process survey and diagnostic process on 14-Mar. The BI implementation process will be started on 17-Mar-2014. The EFGP implementation process will be started on 11-Apr-2014. CFC Core Process Module (list below) customization for 1 st Round Operation Simulation Testing have been delivered and do customization training on mid of Apr-2014 (Purchasing, Inventory, Sales & B2B, Logistic & FG Warehouse, Production, Financial) Key User Examination have been executed for Core Process Modules (Maintenance, QC, Elec Power, SMS will be May-2014, and HRM will be June-2014 ) CFC ERP 1 st Round Operation Simulation Testing will be start on 22-Apr-2014.

3 Ganda ERP Project | CG Month-end Closing 1. Check Up 2. Reconciliation & Report AprMay Aug June July Oct Sep 20/2 Jan Feb Mar Phase 2 development 1. Survey & Diagnosis 2. Application Training 3. Operation Training 4. S.O.P. Modeling 5. Gap Analysis & Customization 6. HRM Application Training /Gap Analysis Nov Dec ERP Project Milestone 2014 RMC & Transport 1. Design & Development 2. Basic data preparation 3. UAT 4. Training 5. Launch B I 1. Workshop 2. Design & Development 3. UAT 4. Launch Easy flow (EFGP) 1. Design & Develop 2. UAT 3. Launch AASTAR / WHI 1. Basic data preparation 2. Training 3. Launch HR 1. Payroll 2. ESS 20/315/410/505/605/720/815/805/8 RMC – Motive Mulia Kick off 11/3/2014 – Go-Live 1/10/2014 (All of RMC) Transport - ANP Kick off 10/6/2014 – Go-Live 1/11/2014 AASTAR / WHI K-off 12/05 – Go-Live 01/07 Business Intelligence Kick off 18/3/2014 – Go-Live 01/07 2014 (Pilot) Easyflow (EFGP) / Online approval Kick off 14/4/2014 Go-Live 01/07 2014 Payroll Kick off 05/2/2014 – Go-Live 01/06/2014 (CG) ESS (Employee Self Service) – Integrated with EFGP Kick Off 14/4/2014 – Go-Live 01/07/2014 CFC Cement 1. UAT & Training 2. Basic data preparation 3. Operation Simulation 4. Launch CFC – Cement Kick off 1/07/2013 – Go-Live 1/7/2014 (Operation Simulation Testing : 1 st Round 22/4 ; 2 nd Round 12/5) 2

4 Ganda ERP Project | Nov-2013Dec-2013Jan-2014Feb-2014Mar-2014Apr-2014May-2014June-2014July-2014Aug-2014 Purchasing Inventory Sales Logistic / FG Warehouse Production Maintenance Finance & Accounting Human Resouce Customization  Basic Data upload  Test / Simulation  End User Training Parallel Test Run GO - LIVEGO - LIVE ERP Go Live The Schedule to Go-Live for CFC ERP Go Live Simulation Testing 10% (22-Apr) Simulation Testing 50% (12-May) 3

5 Ganda ERP Project | Progress update Purchasing 4 Progress Update Next Plan Module / Function 1. All of Purchasing procedure have been trained and processed in CFC ERP environment. except GR integrated with LiGu weight-scale. (There are some outstanding issues and will be updated the status next session.) 2. Key User Examination have been done, Key user can process the system procedure well and smoothly by themselves. 3. Ready to execute 1 st Round operation Simulation Testing 1.Recheck all the basic data for CFC-TKP & CFC-HPGP. 2. Outstanding Issues should be solved or have work around solution. 3. Deliver GR (Good Receiving) integrated functions with LiGu with current confirmed spec on May-2014. Q : Does Item 3 LiGu Integration spec will be impacted by new LiGu database structure ? System Basic Data User Skill

6 Ganda ERP Project | Progress update Inventory 5 Progress Update Next Plan Module / Function 1. All of Inventory procedure have been trained and processed in CFC ERP environment. 2. Key User Examination have been done, Key user can process the system procedure well and smoothly by themselves. 3. Ready to execute 1 st Round operation Simulation Testing 1.Recheck all the basic data for CFC-TKP & CFC-HPGP. (Item’s CoA attribute should be maintained) System Basic Data User Skill

7 Ganda ERP Project | Progress update Sales & B2B 6 Progress Update Next Plan Module / Function 1. B2B interface should have Vietnamese ( MIS will continue to replace Simplify Chinese to Vietnamese ) 2. All of Sales & B2B procedure have been trained and processed in CFC ERP environment. (There are some outstanding issues and will be updated the status next session.) 3. Key User Examination have been done, although TKP user can process the system procedure by themselves, but suggest to do continue practice to enhance the process speed. (not familiar) (Due to HPGP join the training from Logistic (L/N,…), so Sales & B2B still can not process) 4. Ready to execute 1 st Round operation Simulation Testing 1.Recheck all the basic data for CFC-TKP & CFC-HPGP. (especial for CFC-HPGP) 2. Outstanding Issues should be solved or have work around solution. 3. Sales Customization Report (6pcs) Spec will be provide on 30-Apr and need to be confirmed. 4. Develop Training Schedule for External user for new B2B interface (Agents, Carriers,..) System Basic Data User Skill

8 Ganda ERP Project | Progress update Logistic & FG Warehouse 7 Progress Update Next Plan Module / Function 1. All of Logistic and F/G Warehouse procedure have been trained and processed in CFC ERP environment. (There are some outstanding issues and will be updated the status next session.) 2. Key User Examination have been done, although TKP user can process the system procedure by themselves, but suggest to do continue practice to enhance the process speed. (not familiar) (Due to HPGP join the training from Logistic (L/N,…), the learning effect are no good for HPGP, they still need more practice to familiar new system and process) 3. Ready to execute 1 st Round operation Simulation Testing 1.Recheck all the basic data for CFC-TKP & CFC-HPGP. (especial for CFC-HPGP) 2. Outstanding Issues should be solved or have work around solution. 3. Logistic & Warehouse Customization Report (4pcs + 2pcs) will be provide on 25-Apr (4pcs) and 30-Apr (2pcs), and need to be confirmed. System Basic Data User Skill

9 Ganda ERP Project | Progress update Production 8 Progress Update Next Plan Module / Function 1. All of Production procedure have been trained and processed in CFC ERP environment. (There are some outstanding issues and will be updated the status next session.) 2. Key User Examination have been done, Both TKP & HPGP user can process the system procedure well and smoothly by themselves. 3. Ready to execute 1 st Round operation Simulation Testing 1.Recheck all the basic data for CFC-TKP & CFC-HPGP. 2. Outstanding Issues should be solved or have work around solution. 3. Packing and Production Customization Reports (7pcs+6pcs) Spec will be provide on 24-Apr (7pcs) and 30-Apr (6pcs), and need to be confirmed. System Basic Data User Skill

10 Ganda ERP Project | Progress update Equipment Maintenance 9 Progress Update Next Plan Module / Function 1. Maintenance Customization Module have been develop and deliver to CFC. 2. Maintenance Module Basic Data preparation had been explained on 19- Mar-204 by Mr. Nick. 3. Due to priority consideration (for 1 st Round Simulation Test), we postpone the Maintenance Module from Apr-2014 to May-2014. 1.Equipment Maintenance basic data preparation and upload into ERP DB. 2. Maintenance Module Training will be hold on May-2014. System Basic Data

11 Ganda ERP Project | Progress update Finance & Accounting Progress Update Next Plan Module / Function 10 1.Dual Currency have conclusion and already release to programming. 2.All of Financial & Accounting procedure can be process well in CFC ERP environment, except for Invoicing for shipment about 100% Deposit Order. 3.Key User Examination have been done, but the result are no good, AP & AR user still can not process the new procedure by themselves, still need more and more practice. 4. Ready to execute 1 st Round operation Simulation Testing 1.Recheck all the basic data for CFC-TKP & CFC-HPGP. 2.To revise program for Invoicing for shipment about 100% Deposit Order on May-2014. 3. Deliver Dual Currency Solution and do customization training on May-2014 (2 nd Round Testing) 4. FIN Customization for Vietnamese Description input (186) & Dual currency (250). Total costs about 416 programming hours ! System Basic Data User Skill

12 Ganda ERP Project | Progress update Cost Accounting Progress Update Next Plan Module / Function 11 1.Dual Currency Solution for Cost Accounting have been confirm and now developing customization spec. 2. Because of this additional level process need to auto generate related transaction from system. That will cause additional customization charge (88 hours). 1.Deliver Dual Currency Solution for Cost Accounting and do customization training on May- 2014 (2 nd Round Testing) 2.Additional customization charge for Cost Accounting 88 programming hours should be confirmed. System Basic Data

13 Ganda ERP Project | Progress update Progress Update Next action Plan Module / Function 12 Electric Power Q.C Reports 1.All of Electric Power Spec have been confirmed on Feb-2014. 2.Current Electric Power customization module now is under programming and expect to deliver to CFC on 12-May-2014. 1. Electric Power Module will be hold on May-2014. 1.All of QC Spec have been confirmed on Mar-2014. 2.Current QC customization module now is under programming and expect to deliver to CFC on 12-May-2014. 1. QC Module will be hold on May-2014. Progress Update Next action Plan Module / Function System Basic Data System Basic Data

14 Ganda ERP Project | Progress update Progress Update Next action Plan Module / Function 13 Customization Reports SMS 1. SMS Customization Spec have already delivered to CFC on Mar-2014. 2. SMS Platform and SMS Service Message Program have been develop (and revised). 3. Now is testing SMS Modem integration function. 1. Have already provide 25 customization Reports Spec to CFC confirmed on 05-Apr. 2. There are some delay on remaining customization reports, and Digiwin should to catch-up the schedule. ( Original Plan (52 RPTs) : 28/3 : 25 RPTs ; 5/4 : 10 RPTs; 11/4 : 8 RPTs ; 18/4 : 5 RPTs ; 25/4 : 4 RPTs ) Progress Update Next action Plan Module / Function 1. Doing CFC SMS Modem Compatibility Testing on May-2014. 2. CFC SMS Customization Technical Transfer on June-2014. 1. To catch-up delay schedule and provide Cust. reports Spec as below: on 24-Apr : a. Packing Report (7pcs) b. Elec Power Report (4pcs) c. Logistic Report (4pcs) on 30-Apr : d. Sales Report (6pcs) e. Production Report (6pcs) f. Warehouse Report (2pcs) System Basic Data System Basic Data

15 Ganda ERP Project | Progress update Progress Update Next action Plan Module / Function 14 HRM & ESS 1. All of HRM confirmation spec have been provide except P/S Bonus Spec. 2. CFC Organization Data already upload into HRM System. 3. Basic Salary formula already been setting 4. Waiting CFC Sign-back customization Spec. (annual leave,…) 1. Provide P/S Bonus Spec to confirm before 02-May-2014. ( P/S Bonus will be separate into P/S bonus parameters P/S Bonus Calculation and P/S Bonus ) 2. HRM Customization Progress, and start to deliver from end of May-2014. 3. Checking HRM Go-Live Strategy : (1) HRM Go-Live first (01-July), then ESS Go-Live Second step. (2) HRM + ESS Go-Live at same time (will impact original HRM 01-July Go-live Schedule, the expect Parallel testing on Aug-2014, and go-live on Sep-2014) System Basic Data

16 Ganda ERP Project | Current Status of Customization and Issues ModuleCustomizationOutstanding Issue Purchasing 1. GR weight-scale & belt-scale Integration will be put on Phase-I (Plan to deliver on May-2014) 1. Goods Receiving Qty -> LiGu Scale -> Stock In -> QC Moisture -> Price Qty  Price Qty OK ! 2. PR Priority should can choose Urgent /Prompt /Ordinary/Overhaul  Will be provided before 05-May. 3. Please open the application for the new Vendor basic data.  will be setting before 02-May. Inventory 1. Warehouse Voucher Report customization already Finished ! 1.Please open the application for the new Item master.  will be setting before 02-May. 2. Please open the maintain Item application.  will be setting before 02-May. 15

17 Ganda ERP Project | ModuleCustomizationOutstanding Issue Sales 1. Sales Module Report 1 (Finish Goods,10Rpts) will be delivered before 15-May-2014. 2. Sales Module Report 3 (Marketing, 5 Rpts) Customization Spec will be provide 30-Apr, and those reports will expect to delivery on 10-June-2014. 1. Web user creation.  Can Use axmi250 can create Web user 2. B2B Toolbar how to change to the Vietnamese language  Checking now, will be reply before 01-May. 3. L/N input truck ID/Ship ID, providing query function  We suggest if want to provide Query, should create internal CFC truck data first. Current Status of Customization and Issues 16

18 Ganda ERP Project | ModuleCustomizationOutstanding Issue Logistic & Warehouse 1. Sales Module Report 2 (Logistics, 4 Rpts), Customization Spec will be provide 25-Apr, and those reports will expect to delivery on 10-June-2014. 2. The Warehouse Report (2 Rpts) will be delivery on 20-June-2014. (Raw material daily report (cimr101) & Daily report on receiving of material by belt scale (cimr102) 1. L/N document type (LNHP/ LNHN...) should be auto come base on schedule  this function so far can not provide. 2. Reference unit (detail part) should be default “BAG”  Now system according the setting of item Bag or Bulk in Item master. if Bulk, default use TON is make- sense. We suggest if bulk cement use TON as unit just the same with CG now. 3. Delivery date (in detail part) still could not be changed  for LN type = X (jetty), can change date in detail! the other LN type do not provide this function. Current Status of Customization and Issues 17

19 Ganda ERP Project | ModuleCustomizationOutstanding Issue Logistic & Warehouse (continue) 4. In detail part – commit 2 nd line still need typing (could not select as 1st line) some items (Product No., Warehouse,)  So far not yet provide this f unction. Suggest do this fine tune on May. 5. L/C – Cxmp220t have 2 remain minor Issues email at 21-Apr  Checking now, will be reply before 01-May. 6. D/N – Cxmt628 have 2 remain minor Issues email at 21-Apr  Checking now, will be reply before 01-May. Current Status of Customization and Issues 18

20 Ganda ERP Project | ModuleCustomizationOutstanding Issue Production 1. Production Daily Report Part 1 (3Rpts) will be delivered on 15-May. 2. Production Daily Report Part 4 (Packing, 4Rpts) cust. spec will be provide 25-Apr, and those reports will expect to delivery on 30-May-2014. 3. The Other Production Reports (including HPGP, 6 Rpts) ) cust. spec will be provide 30-Apr, and those reports will expect to delivery on 20-June-2014. 1. Factor figure should have special authorized then can changed. & R/C ( RM/Clinker ) radio figure should have special authorized then can changed.  Suggest not do like this way because now just input one time each day. 2. Kiln feeding Qty can write back to the raw mill material issue qty.  if no any concern, Will provide this function soon. 3. Down time will not limited one day 1440 min., but when print out the report will show up the total down time and operation time.  Conclusion no need to do this in last week meeting Current Status of Customization and Issues 19

21 Ganda ERP Project | ModuleCustomizationOutstanding Issue Production (continue) 4. Insert one column for the currently storage Qty in the WIP interface  OK, we will provide this. 5. Production schedule input should provide the Replicate function..  OK,we will provide this. Current Status of Customization and Issues 20

22 Ganda ERP Project | Current Status of Customization and Issues ModuleCustomizationOutstanding Issue Financial & Accounting 1. Dual Currency Customization Spec have been confirmed. 2. Dual Currency Customization will be delivery on 12-May-2014. 3. Dual memo for Accounting transaction customization will be delivered from 12-May-2014 to 20-May-2014. 4. Tax Declaration customization will be expected to delivered on June-2014. 1. FIN Customization for Vietnamese Description input (186) & Dual currency (250). Total costs about 416 programming hours ! Cost Accounting 1. Dual Currency Cost Accounting Spec will be provide on 05-May, and will be expected to delivered on 30-May-2014. 1.Additional customization charge for Cost Accounting 88 programming hours should be confirmed. 21

23 Ganda ERP Project | ModuleCustomizationOutstanding Issue Maintain 1. Customization Module have been developed, Waiting Training. (May-2014) None Electric Power 1. Customization Program will be delivered and trained on May-2014. (12-May) None QC Report 1. Customization Program will be delivered and trained on May-2014. (12-May) None SMS Module 1. Customization Module have been developed, Waiting Integration Test. (May-2014) None Customization Reports (50 reports) 1. Customization Report will be delivered from May-2014 to June-2014. None Current Status of Customization and Issues 22

24 Ganda ERP Project | Current Status of Customization and Issues ModuleCustomizationOutstanding Issue Human Resource 1. HRM system upgrade will be complete on mid-of-May (1 week delay) 2. HRM Operational function customization will be delivered from 19-May-2014 to 16-June-2014, except Shift Table Upload (will be delivered on Aug-2014) 3. HRM Customization Report will be delivered from 16-June-2014 to 18- July-2014. 1. P/B Bonus Spec will be provide on 02-May. 2.Signed back the customization documents for Annual Leave related customization. 3.Currently procedure in HRM Training Module will be revised into another way after September, so we have to make sure do we need to customize it before change the procedure, or we want to move the training modules on Sep-2014. 4.Do we need to launch ESS+ Easyflow on first of the July? If yes, we need to reschedule the implementing plan of HRM. 5.ESS can't handle the function to upload shift table, so it will be change to Easy Flow upload the shift table. But we got some issue have to confirm, that's customization period and go live period. 23

25 Ganda ERP Project | Current Status of Customization and Issues ModuleCustomizationOutstanding Issue Human Resource (Continue)6. After requirements meetings, we found that remain 37 reports need to customize, so if those report are necessary please help us to confirm and signed back the confirmation documents. 24

26 Ganda ERP Project | Major Activities of CFC on May-2014 25 Maintenance, QC, Elec. Power, SMS customization Training and Testing Dual Currency Solution Training and Testing 2 nd Round Operation Simulation Testing (50% transaction Volume) ERP Go-Live and Opening Plan Developing Production Environment Preparation End User Training

27 Ganda ERP Project | THANK YOU