Takashi Matsushita On behalf of IC/Brunel team Imperial College T. Matsushita 1 Preparation for station five Construction/bundling/connectorisation.

Similar presentations


Presentation on theme: "Takashi Matsushita On behalf of IC/Brunel team Imperial College T. Matsushita 1 Preparation for station five Construction/bundling/connectorisation."— Presentation transcript:

1 Takashi Matsushita On behalf of IC/Brunel team t.matsushita@imperial.ac.uk Imperial College T. Matsushita 1 Preparation for station five Construction/bundling/connectorisation

2 T. Matsushita 2 Bundling New comb ready: Comb in use Fibres trimmed on rubber sheet with cutter knife: - align centre fibre on horizontal white line - trim fibres along vertical white line QA image for one connector (# of fibres in a bundle) Cut surface Polished surface

3 T. Matsushita 3 Connectorisation Bridge ready: Bridge in use Fibre radius guide during connectorisation QA image for one connector (# of fibres in a hole)

4 T. Matsushita 4 Check sheet – in preparation

5 T. Matsushita 5 Light source LED survey finished: EG-5UV405-15 from ETG Inc. - Peak 405 nm, range 400-410 nm - 12 mW output now in hand. Optics: - spherical lens for collimation is ready - cylinder lens for focusing is ready - preparing mount for lens - needs mechanical slits

6 T. Matsushita 6 Mechanical Connector: patch-panel connector for external waveguide revised to have gland URGENT: - go-nogo gauge to be made - station connectors to be made Carbon-fibre station - needs to be machined for connector holes Doublet-layer - want the first doublet-layer as soon as it is ready so that we can start work during manufacturing of the second/third doublet-layers. That’s all!