EHN1 North Wall Dismantling Schedule Bastien Rae
2
EN-CV Task before end of CMS TaskStartDuration Install new cooling system Barrack BE-BIMon 20.07.151 day Reroute CMS cold box to raw waterMon 20.07.151 week Reroute Vertex cold box to raw waterMon 20.07.151 week Reroute Atlas cold box to raw waterMon 28.09.151 week Install scaffolding on Jura side (EN-MEF-SI?)Thu 01.10.152 days Cut drinking waterMon 05.10.152 days Cut Ventilation duct and pipe on Jura sideWed 07.10.151 day Remove drinking water from NW (Asbestos)Thu 08.10.152 days
3
EN-CV Task after CMS run TaskStartDuration Disconnect cooling system from CMS Barrack 902Mon 02.11.20151 day Install scaffolding on Salève side (EN-MEF-SI?)Mon 02.11.20151 day Cut and remove chilled water pipeWed 04.11.151 week Cut Ventilation duct and pipe on Salève sideWed 11.11.151 day Install new Chilled water pipe (Gallery + Barrack BE-BI)Thu 12.11.153 days Connect the new cooling system for Barrack BE-BITue 17.11.151 day Rerouted Gallery Pipes (2 demi water, 2 raw water, 1 compressed air)Mon 04.01.162 weeks
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.