Download presentation
Presentation is loading. Please wait.
Published byScott Cross Modified over 9 years ago
1
Big Pipeline Crossing Protection Project for Williams on the Guadalupe River, South of Victoria, TX. (near the harbor) 1.3 Million Dollars Took 3 crews 6 weeks to build!! Summer 2005
2
DEEP PLANTING HUNDREDS OF UNROOTED WILLOW POLES WHEN THE COLDEST DAY WAS 103 DEGREES
3
Bank erosion (lateral erosion) has exposed over 100 ft of pipeline, threatening pipeline integrity Co-designed by River Research & Design, Inc. & Submar, Inc. Contractor: Submar, Inc. Not a flashy stream, stays on the flood for months at a time Bed material: sand-silt-clay, not incised, rural. Pool-riffle-pool regime, slope < 1% Average width 100-150 ft, 10-18 ft tall banks Guadalupe River @ Williams Pipeline Crossing, South of Victoria, TX (near the harbor)
4
PRE-PROJECT PHOTOS: OCTOBER 2004 TO FEBRUARY 2005
5
PRE-PROJECT Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004 PRE-PROJECT- Looking US at the exposed pipeline, flow splits around island. Split flow always brings its own challenges!!
6
PRE-PROJECT Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004 PRE-PROJECT-Looking DS at the exposed pipeline.
7
Flow
8
THREE BENDWAY WEIRS
9
Bendway Weir #1 BW #2 BW #3
10
6 MONTHS LATER-Looking US. Bendway Weirs managing the thalweg. 6 MONTHS LATER-Guadalupe River-Mark Bordelon -3-14-2006
11
WILLOW PLANTING
12
Very hot down in Victoria, TX {103 degrees}. This was the coldest day, it hit 112 degrees some days. We cut several hundred willow branches & small trunks (3/4” to 1.5” butt diameter, 6’ to 8 ft long, soaked them for 10 days, then planted & watered them in (July-Aug time frame). CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-July 2005
13
CONSTRUCTION- The constructed soaking pool for the willows. Pumps kept it full. Willows were cut & soaked for 10 days. CONSTRUCTION-Guadalupe River @ Pipeline-Derrick – June 3, 2005
14
Live Siltation above LPSTP Longitudinal Peaked Stone Toe Protection
15
CONSTRUCTION-Looking US. LPSTP in. Prepping bank for willows CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-July 2005
16
CONSTRUCTION-Looking down slope @ row of willows above LPSTP, 2/3 in ground, 1/3 out. Riprap above willows. CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-June 17, 2005
17
CONSTRUCTION-Looking US. Watering in live willow poles CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-July 2005
18
CONSTRUCTION-Looking DS @ rows of willows & stone protection. CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-June 17, 2005
19
13 MONTHS LATER-High water. Looking downhill @ riprap & rows of willows starting to flush (grow leaves). 13 MONTHS LATER-Guadalupe River Mark Bordelon 10-12-05
20
THE BEFORE & AFTERS LOOKING FROM UPSTREAM TO DOWNSTREAM
21
PRE-PROJECT-Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004 PRE-PROJECT-From US project limit, looking DS @ exposed pipe & vertical bank, thalweg slamming straight into bank
22
26 MONTHS LATER-From US project limits, looking DS. Three Bendway Weirs aligning thalweg along flow arrow 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
23
PRE-PROJECT Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004 PRE-PROJECT-Looking DS at the exposed pipeline, thalweg impacting bank.
24
26 MONTHS LATER-Looking DS @ the protected pipeline, thalweg redirected & willow growth 8 to 16 ft tall after 2 years. 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
25
PRE-PROJECT Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004 PRE-PROJECT-Looking DS at the exposed pipeline. Debris on pipeline, thalweg flowing under pipe.
26
26 MONTHS LATER-Looking DS @ the protected pipeline, great willow growth US & DS of pipeline right-of-way (hydraulic roughness). 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
27
26 MONTHS LATER-Looking DS, good sediment deposition on stone under dense 8 to 16 ft tall, 2”- 4” diameter willows. 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
28
26 MONTHS LATER-Uphill from large willows, great deposition on top of riprap 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
29
26 MONTHS LATER-Uphill from willows, grasses growing on deposited sediment 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
30
26 MONTHS LATER-Close-up on deposition and grasses (not planted). 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
31
26 MONTHS LATER-Thick ridge of deposition DS of willows (shadow). 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
32
26 MONTHS LATER-Thick deposition around planted willow. 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
33
26 MONTHS LATER-Native willow seedlings growing on deposition on top of riprap. We have turned a vertical eroding bank into a depositional area with volunteer tree growth!!! Success & long-term stability!! 26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07
34
This PowerPoint presentation was developed & built by Dave Derrick. Any questions or comments, call my personal cell @ 601-218-7717, or email @ d_derrick@r2d-eng.com Enjoy the information!! d_derrick@r2d-eng.com
35
Peyton & Fred the Aku
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.