Assembly Line Balancing Boeing Corporation
Due October 30th Homework Assignment Assembly Line Balancing Boeing Corporation MGMT E-5065 Operations and Logistics Management
2
Boeing Corporation Task Performance Time ( minutes )
Boeing wants to develop a precedence diagram for an electrostatic wing component that requires a total assembly time of 66 minutes. Task Performance Time ( minutes ) Precedence Relationship A 10 - B 11 C 5 D 4 E 12 F 3 C,D G 7 H I G,H
3
Boeing Corporation REQUIREMENT:
Calculate the maximum allowable cycle time, assuming 480 productive minutes of work available per day, and a daily production quota of 40 units each day. Balance the line under the lot assignment heuristic. Calculate the efficiency under the above.
4
Boeing Corporation REQUIREMENT:
Calculate the minimum allowable cycle time, assuming 480 productive minutes of work available per day, and a daily production quota of 40 units each day. Balance the line under the lot assignment heuristic. Calculate the efficiency under the above.
5
Boeing Corporation REQUIREMENT:
If Task ‘I’ requires 6 minutes ( instead of 3 minutes ) : Calculate the maximum allowable cycle time, assuming 480 productive minutes of work available per day, and a daily production quota of 40 units each day. Balance the line under the lot assignment heuristic. Calculate the efficiency under the above.
6
Boeing Corporation REQUIREMENT:
If Task ‘I’ requires 6 minutes ( instead of 3 minutes ) : Calculate the minimum allowable cycle time, assuming 480 productive minutes of work available per day, and a daily production quota of 40 units each day. Balance the line under the lot assignment heuristic. Calculate the efficiency under the above.
7
Boeing Corporation REQUIREMENT:
If Task ‘I’ requires 6 minutes ( instead of 3 minutes ) : Calculate the maximum allowable cycle time, assuming 480 productive minutes of work available per day, and a daily production quota of 40 units each day. Balance the line under the shortest operating time assignment heuristic. Calculate the efficiency under the above.
8
Boeing Corporation REQUIREMENT:
If Task ‘I’ requires 6 minutes ( instead of 3 minutes ) : Calculate the minimum allowable cycle time, assuming 480 productive minutes of work available per day, and a daily production quota of 40 units each day. Balance the line under the shortest operating time assignment heuristic. Calculate the efficiency under the above.