Information Technology Update ERCOT Board of Director’s Meeting October 18, 2005
2
page 2 Topics Program Management Review Market Redesign Project Flow Release 4 summary
3
page 3 Program Management Review The issue: Over 70 projects in 2005, more in 2006 Increased focus on project delivery Time to review the process Level-set on Program Management maturity The process KEMA engagement —Review current PMO process —Perform a Process Maturity Model assessment (PMI standards) —Provide a “best practice” model —Present a plan for moving forward Anticipated outcome Goal: Level 4 organization Plan to be delivered in two weeks Will show short term (quick hits) and long-term plan Will aggressively implement changes
4
page 4 Program Management Review Findings General observations —Some good processes are in place —Maturity level is at 2.1 —Some holes in existing maturity levels —At a stage where opportunity exists for improvement (stable) Maturity Assessment Five Levels 1: Initial 2: Repeatable 3: Organized 4: Managed 5: Optimized
5
page 5 Program Management Review Major Overall Issues Accountability and ownership Communications Tools
6
page 6 Program Management Review Maturity grade level 1’s Quality issues —Quality policies are lacking —No evidence of quality management Risk Management —No standard risk management practices —Little contingency planning done (budget focused)
7
page 7 Program Management Review Short-term tasks (Solidify existing level next 4-6 months) Revise the PMO and Business organizational structure Establish an effective project reporting structure Revise the resource utilization process Long-term tasks (to reach level three next 12-18 months) Resource management Establish a formal quality management process Establish formal SDLC and IT Governance integrated with PMO
8
page 8 Market Redesign Project Flow Protocols Business Requirements Conceptual Design BuildTest Detailed Design TAC Approval Implementation TAC Approval Issues Market Ready TAC Approval TPTF
9
page 9 Release 4 summary The Project Went live on October 5 Covered 9 PRR’s through 17 projects More than 85 ERCOT employees were involved in all phases ERCOT Hours 31,000 Areva Hours 23,000 60 servers were impacted Outcomes No impact to Frequency Control Application Minimal impact to Real Time Balancing Market (2 intervals missed) Anticipated market savings of $20.1 million year