Pinole Valley High School (PVHS) Project Status 1 Facilities Subcommittee Meeting February 10, 2015.

Similar presentations


Presentation on theme: "Pinole Valley High School (PVHS) Project Status 1 Facilities Subcommittee Meeting February 10, 2015."— Presentation transcript:

1 Pinole Valley High School (PVHS) Project Status 1 Facilities Subcommittee Meeting February 10, 2015

2 PVHS Project Overview 2 Project Efforts2010 - present – Design Concept Development with Site, Community – Traffic Impact Assessments and Coordination with City of Pinole – Hillside Evaluation and Design Efforts – Phasing Development & Coordination (5 Major Phases) – Offsite Projects (Parking, Ball Field Improvements) Building Size268,000 SF Student Capacity 1,600

3 PVHS Project Phase Status Phase Detention BasinCompleted Summer 2014 Temp HousingCompleted Summer 2014 Hillside ReconstructionCompletion Summer 2015 (E) Campus DemoCompletion Summer 2015 (N) Campus ConstructionCompletion Fall 2018 Remaining Phases: Pinole Valley Road Improvements, Temp Housing Demo, Sports Fields/Courts 3

4 PVHS Scheduled Tasks Constructability & District ReviewsJanuary – April 2015 Cost/Budget ReconciliationMarch 2015 DSA Back-check/Stamp-outMay 2015 Project Bid PeriodJune – July 2015 Construction StartAugust 2015 Buildings OccupiedFall 2018 4

5 PVHS Budget Considerations PhaseConstruction Cost/Estimate Detention Basin (Spring 2014)$3,121,600 Temp Housing, including offsite improvements (Summer 2014) $7,479,200 Hillside Reconstruction (Winter 2015)$1,890,800 (E) Campus Demolition (Winter/Spring 2015)$1,722,600 (N) Campus Construction & PV Road Improvements (Estimate – 06/19/13)$104,234,610 Remaining Phases: Temp Housing Demolition, Sports Fields/Courts (Budget) $18,300,000 Total (Construction)$136,748,810 Supporting Costs (25% Project Cost)$45,151,190 Board Approved Budget (February 6, 2013)$181,900,000 5

6 PVHS Next Steps 6 Completion of Constructability & Stakeholder Review Process Cost/Budget Reconciliation DSA Back Check & Stampout Project Bid* – * Contributions to uncertainty of project bid amount include: other projects of similar scale and/or scope bidding at same time; quantity of bidders; market fluctuations (e.g., material costs, transportation costs)


Download ppt "Pinole Valley High School (PVHS) Project Status 1 Facilities Subcommittee Meeting February 10, 2015."