Download presentation
Presentation is loading. Please wait.
Published byDaisy Randall Modified over 9 years ago
1
STATUS REPORT: ALIGNMENT OF COLLIMATORS P. BESTMANN /O. ABERLE Collimation Working Group 26/09/2011
2
Overview Situation today Planned for Winter stop 2011/12 To be done in LS 1: 2013/14 To be done for LS2 Questions and Discussion 26/09/2011 2 CWG
3
Situation today 26/09/2011 3 CWG Alignment in general: Lower support part is aligned in the tunnel (with a dummy collimator (1/10 in weight); Every collimator is prepared on surface to reference values Flange centre is the reference Aligned to the three supporting points Alignment transferred to fiducials on top of the collimator Phase 1 installed and running since 2 years Checks with beam based alignment procedure twice a year Three versions: Ring collimators in IR 3 and 7 (for remote handling and survey) Ring collimators with “low” dose levels, not remote handling Transfer line collimators (no plug-in system)
4
Situation today 26/09/2011 4 CWG In March 2011, some collimators have been identified to need re-alignment. (an angular misalignment >1.9mrad on TCLA.A7R7.B1, TCTH.4L2.B1 and TCSG.A5L3.B2). Reasons identified as: conflict with adjacent vacuum chamber Installation protection added on the support IR extremities, dead end extrapolation
5
Situation today 26/09/2011 5 CWG IR 3 and IR 7, warm section 8 + 22 TCSM locations prepared: 1. Base support installed 2. Cables up to the last few meters ready (No BPM!) 3. Rack space reserved, has to be reorganized 4. Vacuum replacement chambers ok TCSM + TCS slots
6
Situation today 26/09/2011 6 CWG IR 7 is prepared for TIM manipulation IR 3 will be equipped equally (stretched wire, additional targets) Re-alignment upon request, two smoothening campaigns since first installation LHC Smoothing should be followed by systematic collimator realignment in the future All installed supports are “pre-aligned” but all installed new collimators need to be checked
7
Situation today 26/09/2011 7 CWG EMPTY PHASE II TCSM SLOT (30 IN TOTAL) PHASE I TCSG SLOT
8
Situation today – IR 2 26/09/2011 CWG 8 Current situation 4L2, part of VACSEC A4L2.C Insertion of a TCTVA Arc 1-2 IP2: ALICE Collimator areaID800 area Courtesy Eric Page
9
To be done in WS 2011/12 26/09/2011 9 CWG IR 2 (if ECR is approved) 2 new TCTVA’s (TCLP collimators) Layout change with new alignment (ca. 40 m on each side) Use of mobile cryo-protections
10
To be done in LS 1: 2013/14 26/09/2011 10 CWG IR 3 in 2013/14 (combined betatron/momentum cleaning in IR3 ) 8 locations of phase 2 (TCSM) ok Use Scraper location for additional TCP, Layout modification (Cooling and cables ok, supports and vacuum chambers to do) IR 7 in 2013/14 22 locations to be equipped with phase 2 plug-ins. Alignment of supports for phase2. Points to work on: Pull cables for BPMs (IR3, other points, TCT?) Work on flow rate/distribution for the final system (flow-fix?), upgrade of CV pumping system. Auto retraction – clutch?
11
To be done in LS 1: 2013/14 26/09/2011 11 CWG Produce and install cryo-protections? IR 6 (Beam dump line modification (TCDQ, TCS...later?) 2 new TCSP’s BPM cables Start replacing TCT’s with TCTP’s (with BPM), IR with priority? Pull cables for BPM’s to defined positions?
12
To be done/prepared for 2017? 26/09/2011 12 CWG IR 1 and 5 4 TCLP’s (at Totem location) Install supports, alignment Produce and install cryo-protections? Mobile as for IR 2? Replace all TCT’s with TCTP’s (with BPM) Replace other collimators with BPM version Cryo-solution?
13
Questions and Discussion 26/09/2011 13 CWG Number of new collimators to be produced?: What type? Change scraper locations (2) in IR 3 to TCP? Integration Change scraper locations (6) in IR 7 to hollow ebeam-lense? Integrate TCT‘s into the Layout (IR 2 under study, IR 6, IR 8?) Remove Roman Pots and install TCLP‘s to Point 1 and 5. When? Keep and align Phase 2 slots? Transfer lines? Dump line?
14
Questions and Discussion 26/09/2011 CWG 14 Any alignment related observations during operation? Tolerance for realignment IR7 and IR3 (OP needs vs. RP) What can be compensated by the collimators (transversal offsets, rotations) Requests for LS1
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.