1
from why, to what, to how much FROM reality TOTO Kelley Horton
2
Contents About the Speaker Fantasy to Reality Can it really be that simple (and fun)? Prioritization Normalization Cost The Audience Challenge 2
3
SpecialtiesKelley Horton, SA Industrial / Manufacturing Engineer 20 + years in product development Silicon Valley start-ups Creating & Leading PMOs Contact: www.linkedin.com/in/kelleyhorton www.linkedin.com/in/kelleyhorton Program and Portfolio Management Enterprise Lean-Agile Practices Accelerating solution delivery Building / Coaching high-performing Agile Scrum teams Lean Agile Visual Controls Process Engineering Queen of ‘Sticky Notes’ Kelley Horton is a certified SAFe Agilist who specializes in Lean-Agile transformations About the presenter
4
Fantasy to Reality If you are attending this session … I am assuming you have some level of lean agile practice underway in your organization And you have some working knowledge of Fantasy Football 4
5
Fantasy to Reality Traditional Challenges with Strategic Planning Pulling people off work in progress to do big estimation efforts with little input Funding projects versus funding teams Giving a false sense of estimation accuracy based on that little input Being held to the estimates / dates from this process once funding is approved Funding never materializes for the things you took the time to estimate 5
6
Can it really be that simple? Prioritizing work based on cost of delay Normalizing Estimation techniques Knowing your cost per unit of value delivered 6
7
Can it really be that simple…. Prioritization – Why? Fantasy - Football Draft Player Selection Criteria Skills / Availability / Quantity Sequence for selecting Running Backs Wide Receivers Tight Ends QBs Defense / Special Teams Kicker Reality – Feature Prioritization Weighted Shortest Job First User / Business Value (e.g. increased Sales Volume) Time Criticality (e.g., first to market) Risk Reduction / Opportunity Enablement (e.g., regulatory compliance) Executive Mandates How Much What Why 7 *WSJF - Don Reinertsen and SAFe
8
League A Scoring Rules vs.League B Scoring Rules Can it really be that simple…. Normalization – What? How Much What Why 8
9
Can it really be that simple? Normalization – What? How Much What Why Player Scoreboard across Leagues League A League B 9
10
Fantasy = A vs. B LeaguesReality = Normalized Story Points Agree on estimation approach for story points An‘ideal developer day = 6 hours = 1 SP’ Never look back (don’t worry about recalibrating) Make solid commitments in terms of plan dates and cost estimates for your delivery teams Can it really be that simple? Normalization – What? How Much What Why 10
11
X-Sm 10 Story Points Sm 25 Story Points Med 50 Story Points Lg 100 Story Points X-Large 150 Story Points XXL 200+ Story Points Can it really be that simple….. Normalization – What? How Much What Why Jersey-Sizing Features 11
12
Can it really be that simple? Cost / Unit of Value *Source – Forbes – The Business of Football 2015 12 How Much What Why
13
Fantasy = Football WinsReality = Value Delivered (SPs) Can it really be that simple? Cost / Unit of Value How Much What Why 13 Quarterly Run Rate ($) Quarterly SPs Delivered = Cost / SP
14
How Much What Why Things that impact Cost / SP Lack of ‘persistent’ teams (unpredictable velocity) Changing priorities after work is in progress (lost capacity / wasted effort) Poor dependency management with external teams (blocks work) UX process & capacity mismatch (can block work or cause changes to WIP) Poor quality (need more production support resources) High process overhead Can it really be that simple? Cost / Story Point 14
15
How Much What Why X-Sm 10 Story Points Sm 25 Story Points Med 50 Story Points Lg 100 Story Points X-Large 150 Story Points XXL 200+ Story Points T-Shirt SizeStory Point SizeApprox. Cost ($2000 / SP) XS10$20,000 S25$50,000 M50$100,000 L100$200,000 XL150$300,000 XXLMinimum 200$400,000 Can it really be that simple….. Cost / SP 15
16
How Much What Why Strategic Planning Simplification Can it really be that simple? Do the math…. 2016 Funding $$ Cost / Story Point = $20 MM $2,000 In 2016 we can deliver 10,000 SPs Allows Business partners to make informed trade off decisions based on high level of transparency Allows Technology team to make firm / fixed price estimates at the beginning of each fiscal year 16
17
How Much What Why Can it really be that simple? Do the math…. A backlog of discrete, releasable features representing the needs of multiple LOBs Business value articulation & relative scoring, with “mandate” multiplier to facilitate external influences on sequencing Rating & ranking appreciates job size Don’t forget to include an allocation for Tech Debt, Arch Runway; 10% tech debt, 10% Arch Runway 17
18
Back to your‘reality’ If you could implement one technique, which would be the most valuable with the least amount of effort? 1.Why – Prioritization (WSJF) 2.What - Story Point Normalization 3.How Much - Cost / Story Point The Audience Challenge How Much What Why 18
19
Recap 1.In Reality - Keep it simple 2.In Fantasy - Always pick……… 19
20
THANK YOU! M: 704-965-3658 LinkedIn: www.linkedin.com/in/kelleyhortonwww.linkedin.com/in/kelleyhorton 20
21
FROM WHY… TO WHAT… TO HOW MUCH… FROM reality TO