1
SHDH Perimeter Radiation Improvements Town Hall Meeting – June 23, 2015
2
Review the scope of the project. Review the project schedule and all impacted suites/areas. Continued Communication Plan Q&A 2 SHDH Perimeter Radiation Improvements
3
Brief Explanation for Project Why are we doing this project? o To provide improvements to the perimeter radiation piping installed last summer with the Phase 2 portion of the Air Handling Unit #9 Upgrade project. 3
4
Scope of Project 4
5
Project Scope Perimeter Radiation Improvements (July 2015 – August 2015) o Upgrade existing piping to avoid potential future leaks. o All is occurring in the evening Monday through Thursday from 7:00 pm to 7:00 am. o Access will be needed to all perimeter areas of the building. 5
6
Project Update 6
7
Construction Work Update Proposed Schedule is from Monday July 6, 2015 through Friday August 21, 2015. Project set up/move schedule will be similar to last summers work. Work will occur at the perimeter radiation locations only. 7
8
Construction Work Update (cont.) Pictures of a faculty member’s office for the perimeter radiator work: Before After 8
9
Project Schedule/Impacted Areas 9
10
Project Schedule/Impacted Areas- Cont’d 10
11
Project Schedule/Impacted Areas- Cont’d 11
12
Project Schedule/Impacted Areas- Cont’d 12
13
Project Schedule/Impacted Areas- Cont’d 13
14
Communication with Building Occupants 14
15
Communication Plan Daily site walk-throughs. Communication with Business Administrators. Weekly email updates to building occupants providing the construction look ahead plan. Memos for faculty area offices. 15
16
Questions? 16