Construction Management new CCDC 5A, CCDC 5B and CCDC 17
19th Annual BC Institute PMAC Workshop "Circle of Excellence" Construction Management new CCDC 5A, CCDC 5B and CCDC 17 September 28 – 30, 2011 Presented by Roy Nieuwenburg CW
1
Outline today’s session: - overview of the new forms
- discuss the changes - discuss how to work with these new templates Jump to Conclusion Slide – tell you want the conclusion will be …
2
first, any burning questions?
3
As of May 2011, the CCDC (Canadian Construction Documents Committee) and CCA (Canadian Construction Association) phased out the former construction management standard documents and replaced them with the new CCDC 5A and CCDC 5B Construction Management Contracts and the related CCDC 17 Trade Contractor Contract.
4
CCDC 5A – previously was “CCA CANADIAN STANDARD CONSTRUCTION MANAGEMENT CONTRACT FORM BETWEEN OWNER AND CONSTRUCTION MANAGER” CCDC 5B – no previous equivalent. CCDC’s answer to “CM At Risk” or “CM converting to stip sum”. CCDC 17– previously was “CCA STIPULATED PRICE CONTRACT FOR TRADE CONTRACTORS ON CONSTRUCTION MANAGEMENT PROJECTS”
5
Context – where does cm fit in the bigger picture?
What is the best Project Delivery Method? What is the best Contracting Structure?
6
Construction Management Association of America
“An Owner embarking on a construction project must make an important decision regarding the method by which the project is designed and constructed - the project delivery method.” Some further discussion – TAB F. See Tab 5 “At Risk” Construction Management – Construction Business, September / October 2006
7
Context – continued e.g. design – bid – build design - build etc.
8
“species” - stipulated price (e.g. CCDC2 2008)
cost plus (e.g. CCDC3 1998) unit price (e.g. CCDC4 1982) construction management design build (e.g. CCA/CSC/RAIC )
9
“species” continued: EPC– “engineer, procure, construct” or EPCM “engineer, procure, construction manage” etc.
10
“varieties” of e.g. stipulated price contract:
- CCDC2 2008 - MMCD (Master Municipal) - Alberta Infrastructure prescribed forms - Civil Works Contract (CCDC18 – 2001) - Unit Price or lump sum stipulated price Province of BC Stip Price Contract (until 2002) many US examples (core of army engineers etc.) - many owners have their own forms – e.g. UBC PT, UBC, YVRAA, etc. Construction Owners Association of Alberta (COAA) published forms
11
back to construction management:
variants of construction management: straight cm (CCDC suggests CCDC5A) cm converting to stip sum aka CM at risk (CCDC suggests CCDC5B) hybrids (next slide)
12
hybrids (can achieve similar result)
variants of “cost plus” might be loosely considered to be akin to cm … stip sum contract with lots of cash allowances …
13
AIA [American Institute of Architects] equivalents
Tab G – akin to CCDC5A: AIA Document C132–2009 – akin to CCDC5B: AIA Document A133–2009 [with a Guaranteed Maximum Price] AIA Document A134–2009 [without a Guarantee Maximum Price]
14
some advantages of cm transpancy to the trades fast tracking
design assist direct control
15
disadvantages of cm pricing is “open ended”
(more on this – see slide below) “will strive” “buck stops here” – with owner (see Hudson quote, below)
16
pricing is “open ended”
Hudson’s on Building and Engineering Contracts: “Most of these management contract arrangements, when examined in detail …appear to be little more than thinly disguised collective cost-plus contracts in their ultimate final effect …”
17
“will strive” old CCA 5 said:
“The Construction Manager, along with the Owner and the Consultant, … shall strive to achieve Substantial Performance of the Project by …[date]” as an assurance - underwhelming! - even this meager assurance was not included in new CCDC templates!
18
Supplementary Conditions for new CCDC:
The Construction Manager, along with the Owner and the Consultant, shall strive to achieve Substantial Performance of the Project by the target date specified therefor by the Owner in the preliminary Project schedule approved by the Owner as it may be varied or amended from time to time with the approval of the Owner. [Substantial Performance of the Project – not even defined in new CCDC5A]
19
Another factor – Ministries and MASH entities
AIT, TILMA (New West Partnership Trade Agreement), and Core Policy Manual, CAMF Capital Procurement Audit Checklist etc.: question - with cm, does each trade contractor have to be posted on BC Bid, tendered etc. {might prefer hybrid model}
20
Comparison – CCDC5A and CCDC5B
CCDC 5A – for services CCDC 5B – for services and construction (i.e. “cm at risk” or “cm converting to stip sum”)
21
Comparison – CCDC5A and CCDC5B – cont’d
Who do you want to enter into the contracts with the Trade Contractors? CCDC 5A – the Owner does … CCDC 5B – the Construction Manager does …
22
Comparison – CCDC5A and CCDC5B – cont’d
Is the Construction Manager an agent or not? Must act in the best interests of the Owner? CCDC 5A – agent: See GC 2.1.4 CCDC 5B – not agent. see GC 1.5.2 See proposed SC 1.2” … shall carry out and perform the Services in a proficient and diligent manner and in accordance with any directions and instructions from time to time given by the Owner. … and at all times shall be candid and forthright with the Owner and act in the best interests of the Owner.
23
changes – new CCDC5A/5B versus old CCA5
old CCA5 – cm was agent (see above) “strive” – see above CCDC5B now contemplates converting to stip sum (old CCA5 did not)
24
changes – new CCDC5A/5B versus old CCA5 - continued
Fees: time-based rates for personnel: Old CCA5: time-based rates for personnel employed by the Construction Manager was under of “Reimbursible Expenses” Now: – isolated as a separate heading – see paragraphs and 5.3 on page 4 of CCDC5A.
25
changes – new CCDC5A/5B versus old CCA5 - continued
chart listing services – must select and deselect services, and indicate – “how paid” [Roy – open CCDC5A – demonstrate Schedule A1]
26
changes – new CCDC5A/5B versus old CCA5 - continued
Own Forces Work – formerly Article A-7 of CCA5 - deleted under new CCDC5A could include Own Forces Work as “ADDITIONAL SERVICES” under SCHEDULE B1 of CCDC5A – need to remember to do this, if you want the right to require this (e.g. temporary work, trailers, etc.)
27
changes – new CCDC5A/5B versus old CCA5 - continued
Insurance Owner must maintain wrap policy for not less than $10mil.
28
changes – new CCDC5A/5B versus old CCA5 – cont’d
GC No deductions shall be made by the Owner from amounts payable to the Construction Manager other than those for which the Construction Manager is proven to be responsible …”.
29
Keep in mind PART 9 [INDEMNIFICATION AND WAIVER OF CLAIMS] - for colleges and institutes and universities not insured by CURIE, see requirements prescribed by Risk Management Branch.
30
Keep in mind - continued
payment certifier – see paragraph of the General Conditions. note, whatever it says in the cm document, the actual operative document, for this purpose, is the actual agreement with each individual Trade Contractor (i.e. the CCDC17).
31
Keep in mind - continued
Unlike architects and engineers (who are exempted under Section 4(6) of the Builders Lien Act), Construction Managers are not exempted. Under the Builders Lien Act, must holdback 10% form construction manager. Also, unless an exempt entity, or if under the $100,000 threshold (applies to the improvement), must establish holdback savings account.
32
CCDC17 Basically, the new CCDC17 updates the old CCA to bring it in line with changes brought in with CCDC2 2008
33
CCDC5B Appendix for conversion – looks very much like Supplementary Conditions. we’d be doing “Supplementary Conditions to the Supplementary Conditions”! My inclinations would be – if you want “cm converting to stip sum”, use simple format of CCDC5A and go from there. My inclinations would be – if you want cm converting to stip sum, use simple format of CCDC5A and go from there. WYSIWYG
34
Conclusion The base documents have changed.
As before, can customize the base documents to get to where you need to be. Underlying issues are still the same. Need to update Supplementary Conditions for use with these forms.
35
THANK YOU ran@cwilson.com | 604.643.3112 www.cwilson.com
Questions or Comments: Roy Nieuwenburg, Clark Wilson LLP | Thank you option #2 Content on this page is flexible, i.e. if a lawyer wants it to read differently, fine … this is a starting point. Some may prefer to have the heading “Questions or Comments” followed simply with their contact info. Our website should always be included on the last slide. To print this presentation: Take the usual steps (i.e. file – print) … select the printer and format you want (i.e. slides, handouts, notes pages, etc.) … make sure the black & white option is NOT selected. Generally, people want the three slides per page option so they have space to take notes.