1 Slide For Introduction PEMANTAUAN KEMAJUAN KERJA.

Similar presentations


Presentation on theme: "1 Slide For Introduction PEMANTAUAN KEMAJUAN KERJA."— Presentation transcript:

1 1 Slide For Introduction PEMANTAUAN KEMAJUAN KERJA

2 2 Responsibilities to monitor project activities have to be done in details to ensure it is in order as planning. In most cases, human are fail to plan rather than the failure of planning. Project manager has to ensure that the process of monitoring and controlling were practices on constructions site.

3 3 3 steps of monitoring process: 1. Planning or Standard 2. Comparison between planning and actual 3. Correction action where necessary

4 4 There are methods in project monitoring: 1. Time measurement 2. Cost measurement 3. Labour measurement 4. Work Break down measurement

5 5 One of popular utilised method. One of popular utilised method. Must have agreement from 2 parties. Must have agreement from 2 parties. ãFigure showed monitoring activities for week 4 to week 8 ã Week 4 showed 25% planning progress, whilst actual achievement was only 17%. Delay of work progress was 8%. ãFigure showed monitoring activities for week 4 to week 8 ã Week 4 showed 25% planning progress, whilst actual achievement was only 17%. Delay of work progress was 8%.

6

7

8

9 Most popular method used by contractors Figure shows the planning cost and it’s cumulativeFigure shows the planning cost and it’s cumulative S CurveS Curve ‘baseline’ concept used ‘Microsoft Project’‘baseline’ concept used ‘Microsoft Project’

10 Application of this method have to identify earlier the man-hours, man-days or man-weeks Can be divided in average based on suitability of the activities.Can be divided in average based on suitability of the activities.

11

12 This method only suitable for a certain organization. Work planning scheduled following their activities: ‘spray tiles’, ‘ceiling’, ‘earthwork’.Work planning scheduled following their activities: ‘spray tiles’, ‘ceiling’, ‘earthwork’. Helps in understanding to computer planning software.Helps in understanding to computer planning software.

13 13 Identified a project planning & scheduling that involved 1.Client/ Project Manager 2. Project Engineer 3.Contractor Next Lecture – task Group 4 Show to the class the techniques of scheduling applies in the project and the relation of it development to resources management. The scheduling also have to consider : General Schedule by Client / Project manager Detail Schedule by Contractor Show to the class the techniques of scheduling applies in the project and the relation of it development to resources management. The scheduling also have to consider : General Schedule by Client / Project manager Detail Schedule by Contractor