Competitive Metering Working Group Market Readiness Update to the PUCT Second Quarter 2003
2
July 8, 2003 COMET FINAL v 1.02 CHARTER in regards to competitive meter ownership as approved by TAC on March 6, 2003 The Competitive Metering Working Group (COMETWG) will develop and recommend the business policies and procedures to implement competitive metering services that will become available to commercial and industrial customers beginning on January 1, 2004, in the competitive retail electric market in Texas, as proposed under the Public Utility Commission of Texas (PUCT) Rule 25.311
3
July 8, 2003 COMET FINAL v 1.03 Competitive Meter Ownership Deliverables with RMS and TAC Approval DRAFT Competitive Metering Ownership Timeline for managing activities related to successful implementation of PUCT Rule 25.311 –April 23, 2003 RMS meeting, RMS approved the draft Competitive Metering Ownership Timeline as presented by the COMET WG, subject to change as necessary –May 8, 2003 TAC meeting, TAC approved the draft Competitive Metering Ownership Timeline as presented by RMS, subject to change as necessary. Future changes recommended by COMET will first be approved by RMS and then by TAC. Standardized Lists of Three-Phase and Single-Phase Meters for Competitive Meter Ownership –April 23, 2003 RMS meeting, RMS approved the initial Standardized Lists of Three- Phase and Single-Phase Meters as presented by the COMET WG, as a deliverable to the PUCT on April 25, 2003. The Standardized Lists are subject to adding more meters to the list prior to January 1, 2004. –May 8, 2003 TAC meeting, TAC approved the initial Standardized Lists of Three-Phase and Single-Phase Meters as recommended by the COMET WG as a deliverable to the PUCT on April 25, 2003 and approved by RMS on April 23, 2003. The Standardized Lists are subject to adding more meters to the lists prior to January 1, 2004. Note: The COMET WG is currently discussing details that may be added to clarify the Standardized Competitive Meter Ownership List.
4
July 8, 2003 COMET FINAL v 1.04 Competitive Meter Ownership Deliverables with RMS Approval –pending presentation to TAC Competitive Meter Approval Process –May 15, 2003 RMS meeting, RMS approved the Meter Approval Process presented by the COMET WG, as modified by RMS –Pending presentation to TAC Meter Issue Resolution Process –May 15, 2003 RMS meeting, RMS approved the Meter Issue Resolution Process as presented by the COMET WG –Pending presentation to TAC ERCOT Competitive Meter Standards –May 15, 2003 RMS meeting, RMS approved the ERCOT Competitive Meter Standards as presented by the COMET WG –Pending presentation to TAC
5
July 8, 2003 COMET FINAL v 1.05 Competitive Meter Ownership Business Process Flows (work in progress) Business process flows have been developed by COMET and are in “draft” status, pending final review and consensus by the working group. Finalizing the business process flows will include the development of or verification that requirements needed to support the introduction of Competitive Meter Ownership are in place on January 1, 2004. –Identifying the information flows and data requirements between Market Participants –Completion of forms required to transfer data between Market Participants –Documenting the data transfer method between Market Participants –Documentation for any required manual processes
6
July 8, 2003 COMET FINAL v 1.06 Competitive Meter Ownership Transaction Impacts Identified (work in progress) Business requirements have been developed and delivered to TX SET for identified transaction changes necessary to implement Rule 25.311. –TX SET change control # 2003-512 Provide a mechanism where the TDSP will apply a re- occurring credit on the 810_02 invoice to the CR for meter ownership. –TX SET change control # 2003-513 Provide a mechanism where the TDSP can identify what type of entity owns the meter on the 814_20. –GAP The conveyance of meter ownership information to “new” CRs as the result of an enrollment or drop has not been included as an automated transaction. A process will be developed by COMET to address a temporary solution to the identified GAP.
7
July 8, 2003 COMET FINAL v 1.07 Competitive Meter Ownership TXSET Version 1.6 Implementation (work in progress) Publish TX SET v1.6 Transactions The TX SET v1.6 Coordination Team has been formed to implement TX SET version 1.6 –Formalize a plan for Market Participant Readiness –Market Participant system changes Complete and finalize TTPT test scripts TX SET version 1.6 release scheduled for production implementation by 1/1/04
8
July 8, 2003 COMET FINAL v 1.08 Competitive Meter Ownership Meter Review Processes and Standards (work in progress) Qualified Meter List Posting –Details to be developed Firmware Versions Approved Meter Functionality Competitive Meter Approval Process –Application Form to be finalized –Process details to be finalized Meter Issue Resolution Process –Resolution Form to be finalized –Process details to be finalized ERCOT Competitive Meter Standards –Details to be developed Define standards and testing requirements for meter approval Develop communication standards Accuracy, security, programming, data integrity
9
July 8, 2003 COMET FINAL v 1.09 Competitive Meter Ownership Protocol Changes and Guides (work in progress) Protocol Revisions –Create PRRs to support competitive ownership –Task Force recommended the addition of the following statement in ERCOT Protocols Section 10 (subject to review by the working group): Competitive meter ownership is a subset of TDSP Metered Entities, excluding Generation or NOIE metering points. Competitive meter ownership shall meet all the applicable rules in the ERCOT Protocols, including requirements for TDSP Metered Entities and any other requirements as outlined in the Competitive Metering Guides. Competitive Metering Guides (CMG) –Create and document business process requirements necessary to implement/provide Competitive Meter Ownership
10
July 8, 2003 COMET FINAL v 1.010 Competitive Meter Ownership PUCT Meter Credit and Tariff Rulemaking (work in progress) PUCT approves TDSP competitive meter ownership credit and implementation guidelines –Can this credit be applied to price to beat customers? This affects TDSP System Design requirements PUCT approves TDSP competitive meter ownership discretionary tariffs –Meter programming –Meter installation and replacement for competitively owned meters –Other Gap analysis for any other action required by the Commission
11
July 8, 2003 COMET FINAL v 1.011 Competitive Meter Ownership I ssues to address (work in progress) Develop dispute resolution process Identify potential customer protection gaps Identify registration, certification & testing efforts Technical issues Other
12
July 8, 2003 COMET FINAL v 1.012 CHARTER in regards to other competitive metering services as approved by TAC on March 6, 2003 The Competitive Meter Working Group (COMET) will recommend a market structure and business policies and procedures necessary to implement other competitive metering services.
13
July 8, 2003 COMET FINAL v 1.013 Other Competitive Metering Services RMS Approval – TAC presentation pending Developed a high level view of a market structure for the introduction of the meter service provider functions as future competitive metering services. The provided market structure could be utilized by the Commission as a foundation for the next phase of rulemaking in the introduction of competitive metering services –June 12, 2003 RMS meeting, RMS approved the future competitive metering services market model (MSP phase) as presented by the COMET WG Meter installation, removal, maintenance, testing, and calibration –Pending presentation to TAC –Pending PUCT rulemaking process Market model for competitive metering services for functions surrounding meter reading for the purposes of determining TDSP billing determinants and the submittal of settlement data to ERCOT have been deferred by the COMET WG, per PUCT Staff guidance –Data Collection and Data Management
14
July 8, 2003 COMET FINAL v 1.014 Other Competitive Metering Services Future Issues to Address (work in progress) Develop a timeline for implementation of other competitive metering services Develop market business processes necessary to implement other competitive metering services Identify business requirements for transactional changes necessary to implement proposed market structure and deliver to TX SET Create Performance Measures required in new market Define process for certification & testing of Service Providers Identify Default Metering Services requirements Inventory Requirements for TDSPs and Service Providers Data requirements Define roles and responsibilities for each activity or service grouping identified in the market models Develop new definitions as appropriate
15
COMET Working Group Commission Requested Deliverables Recommendations as follows
16
COMET Working Group Presentation to and Approval by RMS 4-23-2003 Approved by TAC 5-8-2003 Recommendations for a Draft Timeline and Standardized List of Meters
17
July 8, 2003 COMET FINAL v 1.017
18
July 8, 2003 COMET FINAL v 1.018 Meter Type Meter IDRDemand RegisterWatt-Hour Register ABB Alpha+Must have remote capabilityNo Restrictions ABB Alpha 3Must have remote capabilityNo Restrictions GE KVMust have remote capabilityNot Available for kVA DemandNo Restrictions GE KV2Must have remote capabilityNot Available for kVA DemandNo Restrictions ION 8400Must have remote capabilityNo Restrictions ION 8500Must have remote capabilityNo Restrictions L&G S4Must have remote capabilityNo Restrictions L&G 2510Must have remote capabilityNo Restrictions SEI – SentinelMust have remote capabilityNo Restrictions SEI – VectronMust have remote capabilityNo Restrictions Transdata Mark VMust have remote capabilityNo Restrictions Standardized List of Three Phase Meters For Competitive Meter Ownership ***NOTE*** Programming specifications are subject to TDSP requirements; i.e. display sequence, measured quantities, etc.
19
July 8, 2003 COMET FINAL v 1.019 Standardized List of Single Phase Meters For Competitive Meter Ownership Meter Type Meter IDRDemand RegisterWatt-Hour Register ABB – AlphaMust have remote capabilityNo Restrictions ABB – AB1Must have remote capabilityNo Restrictions GE KVSMust have remote capabilityNo Restrictions GE 170Must have remote capabilityNo Restrictions L&G – MXMust have remote capabilityNo Restrictions L&G – AltimusMust have remote capabilityNo Restrictions SEI – CentronMust have remote capabilityNo Restrictions SEI – VectronMust have remote capabilityNo Restrictions SEI – SentinelMust have remote capabilityNo Restrictions ***NOTE*** Programming specifications are subject to TDSP requirements; i.e. display sequence, measured quantities, etc
20
COMET Working Group Presentation to and Approval by RMS 5-15-2003 Pending Presentation to TAC Recommendations for Meter Approval Process Meter Issue Resolution Process Meter Standards
21
July 8, 2003 COMET FINAL v 1.021 1.New meter is requested for a specific customer’s location. 2.Application is filed by customer and/or the customer’s meter representative to ERCOT Settlement Metering Group. Document submittals shall include: –Certification of compliance with applicable ANSI standards. –Letter from manufacturer indicating that they will supply free programming software & adequate training to TDSP within 30 days of receipt of meters. 3.ERCOT reviews the application for completeness, and to determine if information to demonstrate ANSI compliance has been submitted. –If accepted, ERCOT forwards application to TDSP 4.ERCOT notifies the market of submittal. 5.TDSPs will test meter using applicable standards and share data with other TDSP’s and ERCOT. Information will be made available to other Market Participants upon request. 6.ERCOT approves application based on positive recommendation by a minimum of 80% of TDSP’s, otherwise application is rejected. –If approved, meter is added to list. –If rejected, ERCOT will provide TDSP documentation to the applicant of the specific reason(s) for rejection. Note: Appeal to PUCT is available for all parties. TDSP’s refers to TDSP’s where competitive metering is available Competitive Meter Approval Process
22
July 8, 2003 COMET FINAL v 1.022 1.TDSP notifies the manufacturer of product issue. 2.If the product issue involves non-compliance with ERCOT approved competitive meter standards, TDSP shall notify ERCOT of the issue and the manufacturer’s response to the issue. 3.ERCOT reviews issue. 4.ERCOT confirms non-compliant product issue. 5.ERCOT sends a notification to all TDSP's, and to the meter manufacturer, if issue is confirmed. 6.Manufacturer must resolve issue with TDSP's and ERCOT, during which time further meter installations may be placed on hold. If resolved, remove meter from hold status, and Meter Issue Resolution Process is complete. 7.If not resolved, ERCOT creates de-certification form based on unanimous recommendation from TDSP’s. 8.ERCOT removes meter from ERCOT approved competitive meter list. Note: Appeal to PUCT is available for all parties. TDSP’s refers to TDSP’s where competitive metering is available Meter Issue Resolution Process
23
July 8, 2003 COMET FINAL v 1.023 Meter functionality shall meet the latest revision of ANSI standards as approved by ERCOT. All meters shall meet C12.10 and either C12.1 or C12.20, without exceptions. Meters shall have a minimum of three password levels: a) Programming, b) Read only, demand reset, and time syncing, c) Read only Meets firmware functionality as defined by ERCOT and as documented by manufacturer. Meets TDSP billing determinate requirements Conforms to TDSP meter reading/operating/billing systems Note: TDSP’s refers to TDSP’s where competitive metering is available ERCOT Competitive Meter Standards
24
COMET Working Group Presentation to and Approval by RMS 6-12-2003 Future Metering Services: Market Recommendation for the Introduction of Meter Service Providers
25
July 8, 2003 COMET FINAL v 1.025 CONTENTS: COMET Working Group Recommendations FUTURE COMPETITIVE METERING SERVICES (MSP Phase): –General Description –Market Characteristics –Sequence of Events –Process Flow diagrams
26
July 8, 2003 COMET FINAL v 1.026 Competitive Metering Services Ownership Installation & Removal Maintenance Programming, including billing determinants Testing & Calibration Data Collection Data Management Other Activities Phase 1 January 1, 2004 Competitive Ownership Phase 2 Date TBD Meter Service Provider (MSP) Phase 3 Future Consideration Additional Market Participants (may overlap with other phases)
27
July 8, 2003 COMET FINAL v 1.027 New Market Participant: “METER SERVICES PROVIDER” MSP a.Installation & Removal b.Maintenance c.Programming, including billing determinants d.Testing & Calibration MSP must provide ALL of the above services for a competitively-owned meter to which it is contracted.
28
July 8, 2003 COMET FINAL v 1.028 Market Characteristics: Customer choice of competitive metering services remains optional MSPs will not be required to offer services in all TDSP territories MSPs will not be required to support all meters on the statewide list TDSPs will continue to offer advanced metering services per PUCT-approved tariffs, including new installations
29
July 8, 2003 COMET FINAL v 1.029 PUCT Rule: All competitively owned meters must be contracted to an MSP Competitive Metering Services -- MSP Phase Jan. 1, 2004 MSP eligible to enter the Market Competitive MSP market exists Completion of MSP rule writing process Protocol revisions System changes Operating Guides development Certification and qualification of new market entrants (MSP) TDSP continues to provide metering services for competitively-owned meters in its service territory if customer does not choose to acquire services from an MSP TDSP metering services shall be limited to competitive meter types installed in the TDSP service territory at the time of transition (“Transition List”), including new installations of those meter types Competitive meter owners who select a meter not on the Transition List for that specific TDSP service area must acquire MSP services for that meter Transition Period Owners of competitive meters may acquire meter services from an MSP Preparation Period TDSP provides all meter services
30
July 8, 2003 COMET FINAL v 1.030 Market Characteristics: TDSPs are the only entities that can connect or disconnect service TDSPs retain responsibility for instrument transformers (CTs, VTs) and associated wiring and socket MSP services must be coordinated with the REP/CR REP/CR must notify TDSP prior to competitive meter installation
31
July 8, 2003 COMET FINAL v 1.031 Meter Programming: A single entity (either the MSP or the TDSP) will possess the necessary password to program a meter for billing determinants Only the MSP or TDSP may program a meter for billing determinants A third party authorized by the meter owner may reprogram meters for data unrelated to billing as long as proper security protection is assured, based on future COMET recommendations
32
July 8, 2003 COMET FINAL v 1.032 Market Safeguards: TDSPs may provide emergency services on any meter in order to restore service or remedy unsafe conditions Market participants will communicate issues related to meter malfunctions or inaccuracy to the responsible party Substation access is determined by rules and policies of the substation owner A service provider selection process needs to be developed for situations when MSPs leave the market
33
July 8, 2003 COMET FINAL v 1.033 Certification & Compliance of MSPs: MSPs must be certified to perform competitive metering services in Texas PUCT is the recommended entity to serve as Certification and Compliance Agent (including financial requirements) ERCOT may provide technical qualification assistance Draft of recommended standards has been developed based on the NAESB Uniform Business Practices manual, and other states’ efforts
34
July 8, 2003 COMET FINAL v 1.034 Key Terms and Definitions: Market does not currently have adequate definitions for numerous terms related to competitive metering services –COMET WG is developing draft recommendations for standard market terms and definitions –PUCT is urged to include appropriate new definitions in future rulemakings
35
COMET WG Future Market Model TDSP ERCOT Customer or Customer Approved Third Party CRMSP Exchange of Meter Level Information (e.g., meter read-in/out) - new Meter Service Provider Notification – new Enrollment request processing for move in, move out and switch requests With MSP indicator flag added - new Service order completion initiated from MSP submittal of meter level information - new Enrollment request processing for move in, move out and switch requests With MSP indicator flag added - new Business Relationship New Information Flow Existing Information Flow