Download presentation
Presentation is loading. Please wait.
Published byMitchell Brown Modified over 9 years ago
1
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation Forward trigger detectors installation Muon shielding Commissioning of forward muon detectors
2
Forward Muon Detector Upgrade Forward trigger: scint counters Shielding Forward tracker: mini- drift tubes Completely new forward muon system for Run II
3
1 < | | < 2 A,B,C-layers Forward Muon System u 5,000 scintillation counters u 50,000 mini-drift tube channels u Each plane consists of 8 octants Total detectors weight is ~100ton with coordinate accuracy of 1mm/10m
4
Mini-drift Tubes Here will be individual mini- drift tube picture
5
Pixel Picture Here will be individual pixel picture
6
Forward Muon Trigger System Assembly Status u All parts for all 48 octants are at Fermilab: counters, mounting brackets, etc. u 43 out of 48 octant frames are made u Calibration system production is keeping pace with octants assembly u 30 out of 48 octants assembled and tested and ready for installation: s all tubes, fibers, cables are tested s calibration with r/a source and LED calibration system is performed and documented u On schedule
7
Octant assembly High quality picture of assembled octant will be here
8
Forward Muon Tracking Assembly Status u All 2300 mini-drift tubes for A layer are tested at Fermilab, all 2100 C layer tubes are at Fermilab, tests are under way u Production of B layer tubes continues at JINR: 50% completed u Assembly of A layer octants u Critical items for installation s keep A layer octants assembly and testing on schedule s finish B/C layers drawings and procure all materials Tests of assembled octant in Lab F
9
Installation of Mini- drift Tubes Octants are mounted individually on 3 supports, which are attached to magnet (A and B layers) or C layer trusses Required accuracy of installation is 10mm, required accuracy of octant survey is 0.5mm After octants are installed u survey u connection to gas system u connection to slow control system u connection to front-end electronics u connection to high voltage system Current status: design of octants mounts is finished, production started
10
MDT Mounts Slide of C layer MDT mounts on C trusses
11
Scintillation Trigger Counters Installation Each plane of counters consists of 8 octants Octants are bolted together to form planes (A and B layers) or “half” planes for C layer Planes are installed on supports mounted on magnet (A and B layers) or C layer trusses (C layer) Required installation accuracy is 10mm, required survey accuracy is 2mm After installation u survey u connections to high voltage system u connections to front-end electronics
12
Pixels Installation Drawing of pixels A layer plane installed will be here
13
Shielding and C Layer Trusses While C layer trusses exist from Run I considerable modifications are required to support 100 ton shield The shield u 20” iron, 6” polyethylene, 2” lead Operating the shield u Data-Taking Position u Transport Position Design is finished, production of parts is underway with assembly to follow
14
Data Taking Position
15
Transport Position
16
Shielding C truss reinforcement going on at MAB u C North truss pieces delivered to Lab G for preass’y & survey u C South truss ass’y underway Stacking Lead + Poly into boxes at DAB Poly & Boxes in High-bay. EF Plug core
17
Time Schedule for Installation Resource loaded schedule for forward muon detectors installation is developed Assembly of C layer trusses and forward shielding starts in November 1999 and ends in February of year 2000 Installation of forward tracking detectors starts in April and ends in August 2000 Installation of forward trigger detectors starts in May and ends in September 2000
18
Installation Schedule Here will be forward muon part of Bill’s schedule
19
Technician Manpower “All” - refers to effort assigned to all tasks in the schedule “Install.” - refers to effort assigned to a subset of installation tasks
20
Commissioning of Mini-drift Tubes Commissioning of each mini-drift tubes octant includes the following major tasks u gas leaks test and operation of gas flow monitors u high voltage system check and dark current measurement u commissioning of front-end electronics u muon detection efficiency measurement using cosmic rays Most of the tasks are similar to tests of mini-drift tubes octants in Lab F Commissioning will be done by joint efforts of physicists from JINR (6), Fermilab(1), NIU(1), PNPI(1), UW(1) and other D0 Collaboration groups
21
Cosmic Ray Tests at Lab F Here will be event display picture of cosmic muon in Lab F per Mont’s request
22
Commissioning of Forward Trigger Detectors Commissioning of each scintillation counters octant will include u test of high voltage system operation u light leak test u response of counters to r/a source u operation of calibration system u commissioning of front-end electronics u determination of high voltage for each group of counters and settings for electronics thresholds Most of the tasks are similar to tests performed in Lab F during tests of assembled octants The commissioning will be done by joint efforts of physicists from IHEP (5), NeU(1), Fermilab (1), NIU(1) and other D0 Collaboration groups
23
Results of Scintillation Counters Commissioning in Lab F Distribution of 96 counters response to r/a source Stability of PMT gain over 6 months period for single octant RMS is about 10% Gain stability over 6 month is 3%
24
Manpower for Commissioning Total number of detectors to be commissioned u 50,000 channels of mini-drift tubes and front-end electronics u 5,000 scintillation counters and same number of TDC/ADC electronics channels The time for commissioning is short and determined by detector roll-in schedule 8-9 physicists will be required to perform each of the above tasks with help from electronics engineers and technicians Most of these physicists are visitors from IHEP and JINR
25
Summary We have good understanding of all installation aspects, but detailed engineering drawings and safety reviews have to be done: 1 additional engineer for ~ half a year At some point techs participating in detector assembly come free, but to keep installation running in parallel with detectors production we need ~4 additional techs Commissioning heavily relies on visitors from IHEP, JINR and PNPI, their presence and support
26
Mini-drift Tubes Eight 1*1cm 2 cross section cells mounted in a single gas volume Tubes length is from 1m to 6m Fast gas mixture of CF 4 (90%)+CH 4 (10%) provides maximum drift time of 60ns Coordinate accuracy is ~0.5mm High detection efficiency Tubes are produced at JINR (Dubna) and delivered to Fermilab where they are assembled into octants
27
Trigger Scintillation Counters Bicron 404A scintillator with Kumarin WLS bars along two edges 1” diameter fast PMT with resistive base About 45 different sizes from 15cm up to 1.2m Minimum number of photoelectrons is 60 for largest counter Time resolution is 1ns Counters are produced at IHEP (Protvino) and delivered to Fermilab for assembly into octants
28
MDT Mounts Here will be slide of MDT A layer installation scheme
29
Data Taking Position
30
Transport Position
31
Open Position
33
Assembly Plan Shielding boxes ass’y Assemble & install North + South EF plugs Assemble/Test North/South C bottom truss and shield Assemble/Test North/South C top truss Installation of North+South C truss components Installation of mini-drift tubes and scintillation counters Assembly trusses and shield on the sidewalk Move trusses into collision hall
34
Test Results of Mini- drift Tubes in Lab F Summary of test results of 2300 mini-drift tubes in Lab F u Total measured 2302 (100%) u Rejected during tests 64 (2.8%) Out of 64 rejected tubes the statistics is the following u Gas leaks 47 (73%) u Broken damping resistors 9 (14%) u Wire tension 7 (11%) u High dark current 1 (2%) We expect low detector failure rate during commissioning
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.