1
PHYSICAL FACILITIES UPDATE PURDUE ACADEMIC ADVISING ASSOCIATION December 11, 2014 Michael B. Cline, P.E., PTOE Vice President for Physical Facilities
2
PURDUE MOVES STEM Leadership Increase Expansion of the College of Engineering –Wang Tennant Improvements Transform the College of Technology into Purdue Polytechnic Strengthen Computer Science World-Changing Research Invest in Drug Discovery –Drug Discovery Facility Advance Plant Science Research 2
3
PURDUE MOVES Transformative Education Change the Way Learning Occurs Engage Students with International Experiences Increase Success and Value: Living on Campus Become a Year-Round University Affordability & Accessibility Control Costs 3
4
The Numbers A team of approximately 900 professionals Provide a range of services to customers on a campus of more than 380 buildings FY15 Operating Budget: $85M Units Buildings and Grounds Campus Planning Communications Energy and Construction PHYSICAL FACILITIES 4
5
PHYSICAL FACILITIES ORGANIZATION
6
RECENTLY COMPLETED PROJECTS Krach Leadership Center Third Street Suites Lyles-Porter Hall Ralph and Bettye Bailey Hall
7
ACTIVE PROJECTS Board of Trustees Approved Funding: $70M Phase 1 funding: $15M Demolition: 100% complete Construction: 11% complete Occupancy: 08/03/15 COLLEGE OF ENGINEERING STRATEGIC GROWTH RENOVATIONS – PHASE 1 (GRISSOM HALL) 7 ACTIVE LEARNING CENTER Board of Trustees Approved Funding: $79M Design: 57% complete Utility make ready: 95% complete Demolition: 60% complete Occupancy: 05/01/17
8
SOFTBALL Board of Trustees Approved Funding: $13M Construction Start: 02/03/14 Construction: 70% complete Occupancy: 03/02/15 ACTIVE PROJECTS 8 HONORS COLLEGE AND RESIDENCES Board Approved Funding: $90M GMP: $71M Construction Start Date: 01/05/15 Occupancy Date: 08/01/16
9
R&R EXPENDITURES FY10 – FY14 9
10
SYSTEM-WIDE TEN YEAR CAPITAL PLAN 10 Near Term FY16-17 Est. State FundingEst. Other Funding SPECIAL R&R PROJECTS West Lafayette Campus Brown Teaching Labs $30.4M Fort Wayne Campus South Campus Renovations Phase II $26.9M NEW CONSTRUCTION West Lafayette Campus Agricultural and Life Sciences Facility Phases 1, 2, 3 $30M $20M Interdisciplinary Research Facility - Flex Lab Facility (1) Phases 1, 2, 3 $54M Animal Disease Diagnostic Laboratory (BSL-3) $30M Automated Field Phenotyping Laboratory & Plant Seed Processing Facility $10M Innovation Design Center - Student Projects Facility Phase 1 $20M Jischke Hall Addition – Biomedical Engineering $14M Honors College and Residences $90M Zucrow High Pressure Research Test Cells and Control Center $8.2M Calumet Campus Emerging Technologies Building, including planning funds $40.5M Student Wellness and Recreation Center $17M Art Gallery $3M North Central Campus Central Power Plant Expansion & Replacement $3.8M TOTAL CAPITAL PROJECT BUDGET REQUEST $161.6M $236.2M 1 2 3 4 5 6
11
FIVE MASTER PLAN PRINCIPLES 1. Promote compact growth within the existing campus. 2. Establish State Street as a collaborative zone. 3. Create program synergies through mixed-use districts. 4. Encourage a simple, integrated transportation system with a perimeter parkway. 5. Preserve the western lands.
12
2009 LAND USE 12
13
INSTRUCTIONAL SPACE USAGE 13
14
SPACE USAGE BY ROOM TYPE 14
15
THANK YOU