Download presentation
Presentation is loading. Please wait.
Published byHugo Blankenship Modified over 9 years ago
1
Mythical Man Month By Ryan Ruzich
2
More software projects have gone awry for lack calendar time than all other reasons combined.
3
Our techniques of estimating are poorly developed Our technqiues confuse effort with progress We are therefore uncertain of our time estimates, and thusly software managers lack stubbornness to stick to schedules. Our techniques of estimating are poorly developed Our technqiues confuse effort with progress We are therefore uncertain of our time estimates, and thusly software managers lack stubbornness to stick to schedules.
4
Schedule Progress is poorly monitored in most projects When schedule slippage is noticed, the gut reaction is to put more men on the task, which is the worst thing that can happen. Schedule Progress is poorly monitored in most projects When schedule slippage is noticed, the gut reaction is to put more men on the task, which is the worst thing that can happen.
5
Cost does indeed vary as the product of the number of men (X) and the number of months (Y). X*Y Progress does not. Hence, the man month as a unit for measuring the size of a project is flawed. Cost does indeed vary as the product of the number of men (X) and the number of months (Y). X*Y Progress does not. Hence, the man month as a unit for measuring the size of a project is flawed.
6
Men and Months can be interchanged when a task can be partitioned among many workers with no communication. When workers need to communicate, the formula changes to n(n-1)/2. Men and Months can be interchanged when a task can be partitioned among many workers with no communication. When workers need to communicate, the formula changes to n(n-1)/2.
7
A successful division of a total projects time is: 1/3 for Planning 1/6 for coding 1/4 for component and early systems test 1/4 for systems test A successful division of a total projects time is: 1/3 for Planning 1/6 for coding 1/4 for component and early systems test 1/4 for systems test
8
Adding Manpower to a late project *ONLY* makes it later. The number of months of a project depends upon its sequential constraints. The maximum number of men depends on the number of independent subtasks. Adding Manpower to a late project *ONLY* makes it later. The number of months of a project depends upon its sequential constraints. The maximum number of men depends on the number of independent subtasks.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.