4 These are excavations that are 20 feet deep or greater. What are excavations that require a PE?

5 These are protective systems that must be marked and secured, to protect employees from falling. What are hole covers?

6 Screening installed from the toeboard to the toprail.. What is falling object protection?

7 This is the area that must be barricaded around the crane. What is the swing radius?

8 This must be within 25 feet of lateral travel. What is the means of egress from an excavation?

9 These protective systems must be capable of supporting a 5000# load. What are lanyards and anchorage points?

10 This is the person that must supervise erection, modification and dismantling of scaffolds. Who is the competent person?

11 Cranes must have one of these in the cab rated at 5BC. What is a fire extinguisher?

12 These must be removed or supported. What are utilities located underground?

13 This is installed at 42 inches, give or take three, and capable of supporting 200#. What is the top rail of a guardrail system?

14 Scaffolds must be capable of supporting their own weight and this. What is four times the maximum intended load?

15 This distance must be no more than ten feet. What is the minimum clearance from energized lines?

16 The person with the knowledge and the authority to promptly correct hazards. Who is the competent person?

17 Although it is required to be 4 inches wide, 3 ½ will do. What is a toeboard?

18 These must be used to support scaffolds set on soil or other unstable foundations. What are mud sills?

19 When these are not fully extended they can cause cranes to tip over. What are outriggers?

20 These are excavations that must be sloped at a 1 ½ to 1 angle. What are excavations made in type C soil?

21 The ends of this system should be “eye to eye” not spliced. What is a wire rope guardrail system?

22 This type of work allows 18” between the platform and the face of work. What are plastering and lathing operations?

23 This is the device that deactivates hoisting action. What is an anti-two-blocking device?