Progress Photos March 2007. Construction Progress Park Station Portal Shaft Excavation 16 March 2007 View towards South 16 March 2007 General views of.

Similar presentations


Presentation on theme: "Progress Photos March 2007. Construction Progress Park Station Portal Shaft Excavation 16 March 2007 View towards South 16 March 2007 General views of."— Presentation transcript:

1 Progress Photos March 2007

2 Construction Progress Park Station Portal Shaft Excavation 16 March 2007 View towards South 16 March 2007 General views of construction activities

3 Construction Progress Rosebank General views of construction site, road diversion and pedestrian footbridge spanning Oxford Road and station site View towards South 16 March 2007 View towards North 16 March 2007 View towards South 16 March 2007

4 Construction Progress Rosebank Batch Plant 16 March 2007 Wheel Wash Pit 16 March 2007 Site establishment is ongoing

5 Construction Progress Shaft E5 Looking up from Platform 20 March 2007 Looking down from Platform 20 March 2007 Shaft depth 24 metres at 20 March 2007

6 Construction Progress Sandton Station Demolition of Old Taxi Rank 20 March 2007 New Taxi Rank 20 March 2007 Taxis were relocated to new rank on 9 March 2007 Official opening took place on 15 March 2007 Demolition of old taxi rank commenced on 12 March 2007

7 Construction Progress Sandton Station Diaphragm wall construction 4 D-Wall panels concreted on 16 March 2007 Completed Panels 20 March 2007 Cutter Excavation at North Shaft 20 March 2007

8 Construction Progress Mushroom Farm Park Blast Preparation 19 March 2007 Mucking Out 20 March 2007 Blast Protection Grids 19 March 2007 Shaft depth 15 metres at 20 March 2007

9 Construction Progress Marlboro Portal Third set of canopy tubes installed Arch ribs visible in preceding sections 29 metres of tunnel excavated by 23 March 2007 View from Portal 20 March 2007 Santa Barbara 20 March 2007

10 Construction Progress Marlboro Viaducts View towards South showing Marlboro Station site in foreground, Viaducts 1a and 11 in centre and clearing of alignment towards Marlboro Portal behind Piling (4 piles as at 23 March 2007) and foundations in progress View towards South 22 March 2007 Piling at Viaduct 11 22 March 2007 Foundations V11 and V1a 22 March 2007

11 Construction Progress Area 2 Marlboro to Depot Section View towards Depot 19 March 2007 View towards East (behind Linbro) 19 March 2007 View from Landfill 19 March 2007 Clearing and grubbing, topsoil stripped, and earthworks in progress from Linbro Junction to Depot

12 Construction Progress Depot Train Depot Earthworks Platform 20 March 2007 Bus Depot Admin Building 20 March 2007 Bulk earthworks to both Train and Bus Depot areas is complete

13 Construction Progress Depot Precast Yard Construction of M-Beam casting beds M-Beam Pits 20 March 2007 M-Beam Soffits 20 March 2007 M-Beam Pit Walls 20 March 2007

14 Construction Progress Viaduct 13 First lift of Pier 8 being backfilled Shutter erected for first lift of Pier 7 on the opposite side of Centenary Way

15 Construction Progress OR Tambo Station The station concourse shell is being constructed by ACSA above the new elevated drop- off road CJV site establishment at ORT will commence at the end of March Station Concourse Shell 22 March 2007


Download ppt "Progress Photos March 2007. Construction Progress Park Station Portal Shaft Excavation 16 March 2007 View towards South 16 March 2007 General views of."