1
The Wody Group now proudly presents their Mission Statement and Mission Plans Class Project Fall 2000 ECE 6276
2
Mission Statement To provide ISA for different profiles of a reconfigurable DSP and to assist and support other groups to perform tasks in a speedy and most efficient way
3
How Wody fits in the Big Picture To create ISA for different profiles of DSP To provide ISA to the datapath 2 group To assist algorithm and architecture group in testing the decoders and profiles
4
Overall Mission Plan TaskEstimated Date of Completion Regroup Modules into Profiles11/3 (Done) Create ISA for Each Profile11/6 (Done) Create Mission Statement and Mission Plan11/10 (Done) Assist Decode Group with Design of Decoder 11/10 Prepare for Preliminary Design Review11/15 Verify Functionality of ISA11/22 Support Test Program Run11/29 Create and Maintain Website12/6 Prepare for Final Design Review12/6
5
Mission Plan Specifics Regroup Modules into Profiles PlanWork with algorithm and architecture groups to create profile definitions through examination of the algorithm and examination of other DSPs RiskPoor profile definition will affect efficient DSP design DeliverableDefinition of Profiles Status of TaskDone Estimated Completion Date 11/3
6
Mission Plan Specifics Create ISA for Each Profile PlanExamination of the algorithm and examination of DSP architecture RiskNeed may rise where additional instructions must be added to ISA DeliverableISA definitions Status of TaskDone Estimated Completion Date 11/6
7
Mission Plan Specifics Create Mission Statement and Mission Plan PlanExamination of past work and future work to determine deliverables, completion dates, plan of record, and risk analysis RiskNot all group members will be available at 11/10 presentation to field questions DeliverableMission Statement and Mission Plan Status of TaskDone Estimated Completion Date 11/10
8
Mission Plan Specifics Assist Decode Group with Design of Decoder PlanAssist decode group when requested RiskDecoder may not be ready by 11/10 DeliverableCode for decoder Status of TaskUnknown (ask decode group, have not been requested to assist in design process) Estimated Completion Date 11/10
9
Mission Plan Specifics Prepare for Preliminary Design Review PlanPresent ISA and receive feedback from other groups on ISA RiskNeed may rise where additional instructions must be added to ISA DeliverableISA definitions Status of TaskOn Schedule Estimated Completion Date 11/15
10
Mission Plan Specifics Verify Functionality of ISA PlanUse Altera Max+Plus II to simulate SOC and send binary test vectors to test ISA and analyze what combination of instructions are need for a non-exhaustive test each profile RiskDSP not ready yet DeliverableResults of ISA testing Status of TaskOn Schedule Estimated Completion Date 11/22
11
Mission Plan Specifics Support Test Program Run PlanUse Altera Max+Plus II to simulate SOC and assist in troubleshooting of SOC RiskDSP not ready yet DeliverableResults of testing and any problems with SOC Status of TaskOn Schedule Estimated Completion Date 11/29
12
Mission Plan Specifics Create and Maintain Website PlanBegin construction of website now with continual refinements such that the ISA website is coherent in appearance and function with entire class’ website RiskNoncoherent web design DeliverableWebsite HTML Status of TaskOn Schedule Estimated Completion Date 12/6
13
Mission Plan Specifics Prepare for Final Design Review PlanPresent ISA definitions and results of SOC testing and report any problems with SOC RiskDSP not ready yet or decision of CDR is NO GO DeliverableISA definitions, results of SOC testing, and any problems with SOC Status of TaskOn Schedule Estimated Completion Date 12/6