CS-EE 481 Spring 2007 1February, 2007 University of Portland School of Engineering Project ZigZag Team Adam Russell Will French Matt Heye Advisor Dr. Rylander Industry Representatives Glenna Van Duzer, Lorie Gordon Harland Financial Solutions
2
CS-EE 481 Spring 2007 2February, 2007 University of Portland School of Engineering Overview Introduction Accomplishments Plans Issues/Concerns Conclusions
3
CS-EE 481 Spring 2007 3February, 2007 University of Portland School of Engineering Introduction Project ZigZag searches for images by examining what data is actually presented in the images How this differs from Google image search
4
CS-EE 481 Spring 2007 4February, 2007 University of Portland School of Engineering Accomplishments Submit Theory of Operations, revisions 0.95 and 1.0 Done Implement our working website layout on the application piece of our software. Done Implement search by URL of image Done Continue to meet regularly to discuss and further plan our project. Accomplished Last Month’s PlansStatus
5
CS-EE 481 Spring 2007 5February, 2007 University of Portland School of Engineering Additional Accomplishments Implemented Lightbox open-source software to enhance image results. Put together a working demonstration to demonstrate at Program Review.
6
CS-EE 481 Spring 2007 6February, 2007 University of Portland School of Engineering Plans Finalize CSS styles and integrate them into our website. Implement a paging system for the result set. Develop a testing plan. Complete our Alpha release.
7
CS-EE 481 Spring 2007 7February, 2007 University of Portland School of Engineering Screenshot: Design Layout
8
CS-EE 481 Spring 2007 8February, 2007 University of Portland School of Engineering Screenshot: Design Layout
9
CS-EE 481 Spring 2007 9February, 2007 University of Portland School of Engineering Milestones NumberDescriptionOriginal Date 10/30/06 Previous Date 1/29/07 Present Date 2/27/07 1Product Approval9/15/06 2FS Approval10/07/06 3Plan Approval11/10/06 4Select PL11/11/06 5Database Design11/18/06 6Basic Website11/21/06 7Website Gallery11/30/06 8Setup Server12/7/06 9Create Image DB1/21/07 10Working Algorithm2/7/07
10
CS-EE 481 Spring 2007 10February, 2007 University of Portland School of Engineering Milestones NumberDescriptionOriginal Date 10/30/06 Previous Date 1/29/07 Present Date 2/27/07 11Website Algorithm Implementation 2/20/07 12TOP Approval2/24/07 2/08/07 13Develop Testing Plan 3/1/07 3/4/07 14Alpha Release3/15/07 15Testing and Debugging 3/31/07 16Prototype Release4/7/07 17Founder’s Day4/17/07 18Final Report4/28/07
11
CS-EE 481 Spring 2007 11February, 2007 University of Portland School of Engineering Concerns/Issues None at this time.
12
CS-EE 481 Spring 2007 12February, 2007 University of Portland School of Engineering Conclusions Completed & Submitted our Theory of Operations document On track to complete the project in time for Founder’s Day Have a working demonstration to show…
13
CS-EE 481 Spring 2007 13February, 2007 University of Portland School of Engineering Questions Any questions?