E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 1 Cavity string assembly at KEK for S1-Global Eiji Kako (KEK, Japan)
2
E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 2 Cavity Assembly Team for S1-Global FNAL Tug Arkan (Leader) Brian Smith Marco Battistoni DESY Axel Matheisen (Supervisor, not come) Manuela Schmoekel Patrick Schilling KEK Shuich Noguchi Eiji Kako
3
E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 3 Cavity Assembly Team for S1-Global FNAL DESY Tug Arkan Manuela Schmoekel Brian Smith Patrick Schilling Marco Battistoni Arrival date in Japan ; FNAL 13 th Jan. 2010 DESY 14 th Jan. 2010 Departure date from Japan ; 24 th Jan. 2010 Stay in Urban Hotel for 11 nights (FNAL) 10 nights (DESY)
4
E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 4 Present Status of Cavities Two DESY cavities (Z108 & Z109) arrived at KEK in 4th, December. ACC011 cavity will arrive at KEK in Dec. 25th. AES004 cavity will depart for KEK in Dec. 24th. Both cavities will delivered at KEK by the end of December ??
5
E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 5 11 Mon; National Holiday 12 Tue; am. Check of tools and jigs for assembly pm. Rinsing of 9 support posts by car washer Setup of support posts in class-1000 13 Wed; am. Cleaning by wiping of 2 FNAL cavities Installation of 2 FNAL cav. on support in c-1000 pm. Cleaning by wiping of 2 DESY cavities Installation of 2 DESY cav. on support in c-1000 14 Thu; am. Rough alignment of 4 cavities in c-1000 am. Arrival of FNAL colleagues at KEK pm. Arrival of DESY colleagues at Hotel night Welcome dinner with beer Schedule of Cavity String Assembly (1)
6
E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 6 15 Fri ; am. Meeting for cavity string assembly planning pm. Start-up of assembly work at STF 16 Sat. ~ 21 Thu. ; (for 6 days) am./pm. String assembly of 4 cavities in c-10 22 Fri; am. Final leak check of string cavities Start-up of Ar slow leak in c-1000 night Farewell dinner with beer 23 Sat; Spare day for safety margin 24 Sun; Departure of DESY & FNAL colleagues 25 Mon; am. Movement of string cavities to outside of clean room Schedule of Cavity String Assembly (2)
7
E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 7 S1-Global Cryomodule Overview No connection No beam tube No gate-valve Closed by Blind Flange Gate-valve Pumping system Pumping system Up stream Down stream FNAL#1,#2 AES004, ACC011 DESY#1,#2 Z108, Z109 KEK#1,#2 MHI05, MHI06 KEK#3,#4 MHI07, MHI09
8
E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 8 Eight Cavities for S1-Global 1. AES-004 (27./25 MV/m) ; Blade tuner (center) 2. ACC-011 (33. MV/m) ; Blade tuner (center) 3. Zanon-108 (31.3 MV/m) ; Saclay tuner (end) 4. Zanon-109 (30.7 MV/m) ; Saclay tuner (end) 5. MHI-05 (27.1 MV/m) ; Slide-Jack tuner (center) 6. MHI-06 (27.7 MV/m) ; Slide-Jack tuner (center) 7. MHI-07 (33.6 MV/m) ; Slide-Jack tuner (end) 8. MHI-09 (27.0 MV/m) ; Slide-Jack tuner (end) MHI (Japan), Zanon (Italy), AES (USA), ACCEL/RI (Germany) All cavity vendors in the world !!
9
E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 9 Clean Room at KEK-STF Clean room at STF To cryomodule assembly area Air Shower Entrance HPR Pass-box Water Shower 16.2 m 5.4 m 7 m 2.2 m Class 1000 Class 10 He Leak Detector Pumping System Pumping Line Between c-10 and c-1000
10
E. KAKO (KEK) 2009' Dec. 2 5 STF Meeting for S1-G Global Design Effort 10 Tug, Could you make your assembly plan in clean room at KEK from 15 th (Fri.) to 21 st (Thu.) for confirmation of our works ? Request.......