1st Pert / CPM Problem. Pert / CPM Crashing Problem Activity Normal TimeCrash TimeNormal CostCrash Cost Immediate Predecessor A4320002600- B2122002800-

Similar presentations


Presentation on theme: "1st Pert / CPM Problem. Pert / CPM Crashing Problem Activity Normal TimeCrash TimeNormal CostCrash Cost Immediate Predecessor A4320002600- B2122002800-"— Presentation transcript:

1 1st Pert / CPM Problem

2 Pert / CPM Crashing Problem Activity Normal TimeCrash TimeNormal CostCrash Cost Immediate Predecessor A4320002600- B2122002800- C33500 - D8423002600A E639001200B F3230004200C G4214002000D,E 2 nd Pert / CPM Problem

3 Pert / CPM Crashing Problem Start A BE CF D FinishG

4 Pert / CPM Crashing Problem REQUIREMENT : (a) What is the project completion date? (b) What is the total cost required for completing this project on normal time ? (c) If you wish to reduce the time required to complete this project by one (1) week, which activity should be crashed, and how much will this increase the total cost ?