Presentation is loading. Please wait.

Presentation is loading. Please wait.

PERT/CPM Chart David Nandigam 1. 2 PERT/CPM Chart Task. A project has been defined to contain the following list of activities along with their required.

Similar presentations


Presentation on theme: "PERT/CPM Chart David Nandigam 1. 2 PERT/CPM Chart Task. A project has been defined to contain the following list of activities along with their required."— Presentation transcript:

1 PERT/CPM Chart David Nandigam 1

2 2 PERT/CPM Chart Task. A project has been defined to contain the following list of activities along with their required times for completion: Activity No ActivityExpected completion time Dependency 1.Requirements collection5- 2.Screen design61 3.Report design71 4.Database design22,3 5.User documentation64 6.Programming54 7.Testing36 8.Installation15,7 a. Draw a PERT chart for the activities. b. Calculate the earliest expected completion time. c. Show the critical path.

3 3 PERT/CPM Chart (cont’d) a.Draw a PERT chart for the activities. Using information from the table, show the sequence of activities. 1 2 3 4 5 6 8 7

4 4 PERT/CPM Chart (cont’d) 1 2 3 4 5 6 8 7 b. Calculate the earliest expected completion time. 1. Using information from the table, indicate expected completion time for each activity. 5 6 7 2 6 53 1 2. Calculate earliest expected completion time for each activity (T E ) and the entire project. Hint: the earliest expected completion time for a given activity is determined by summing the expected completion time of this activity and the earliest expected completion time of the immediate predecessor. Rule: if two or more activities precede an activity, the one with the largest T E is used in calculation (e.g., for activity 4, we will use T E of activity 3 but not 2 since 12 > 11). T E = 5 T E = 11 T E = 12 T E = 14 T E = 20 T E = 19 T E = 22 T E = 23

5 5 PERT/CPM Chart (the end) 1 2 3 4 5 6 8 7 5 6 2 6 53 1 T E = 5 T E = 11 T E = 12 T E = 14 T E = 20 T E = 19 T E = 22 T E = 23 c. Show the critical path. The critical path represents the shortest time, in which a project can be completed. Any activity on the critical path that is delayed in completion delays the entire project. Activities not on the critical path contain slack time and allow the project manager some flexibility in scheduling.


Download ppt "PERT/CPM Chart David Nandigam 1. 2 PERT/CPM Chart Task. A project has been defined to contain the following list of activities along with their required."

Similar presentations


Ads by Google