July 20, 2011 Coastal Protection and Restoration Authority Deepwater Horizon Early Restoration
2
Photo Credit: NOAA NRDA Overview
3
Photo Credit: NOAA Stages of NRDA Pre-Assessment /Assessment Restoration Planning Restoration Implementation
4
Photo Credit: NOAA Early Restoration Overview April 21, 2011 - Deepwater Horizon Natural Resource Trustees announced $1 billion down payment for early restoration Louisiana first made the request July 2010 Largest early restoration agreement ever reached Provides an opportunity to implement restoration projects prior to the completion of the natural resource damage assessment (NRDA) process
5
Photo Credit: NOAA Allocation of Funds $500M will be split equally among the Gulf State Trustees $300M will be used to fund state sponsored restoration projects based upon impacts. $200M will be split equally among the Federal Trustees Louisiana Alabama Florida Texas
6
Photo Credit: NOAA NRDA & Louisiana Criteria Consideration of comments received NRDA Criteria Project cost effectivenessProximity to affected areaScalability Extent of benefit to injured resources/services Technical feasibility and likelihood of success Avoidance of future injury resulting from project Degree to which project addresses multiple injuries Louisiana RRP Criteria Ability to implement project with minimal delay Degree to which project supports existing strategies/ plans Project urgency
7
ProjectApproximate Cost Oyster Re-establishment Program$15M Salt Water Hatchery$48M Shell Island Restoration$110M Chandeleur Islands Restoration$65M Biloxi Marsh Shoreline Protection$45M Lake Hermitage Additional increment$13.9M Coastal Restoration Projects “Louisiana Plan” Projects Projects continued on next slide.
8
ProjectApproximate Cost Grand Liard Marsh & Ridge Restoration$31.3M Cheniere Ronquille Barrier Island Restoration$44M Bay Side Segmented Breakwater at Grand Isle$3.3M West Grand Terre Beach Nourishment$9M West Grand Terre Stabilization$3M Barataria Basin Barrier Shoreline Restoration - Caminada Headland$75M Maintain Land Bridge Between Caillou Lake and Gulf of Mexico$71M APPROXIMATE TOTAL$533.5M Coastal Restoration Projects “Louisiana Plan” Projects
9
Oyster Reestablishment Program Approximate Cost: $15M Part 1 ($12M): Placement of Cultch Material on Public Oyster Seed Grounds 855 acres throughout coastal Louisiana Results expected in 17 months after cultch placement Part 2 ($3M): Upgrade to Existing Sea Grant Oyster Hatchery Provide a supplemental source of oyster larvae and oyster seed. Larvae can be released into the water directly over oyster beds with cultch material and/or be set on oyster cultch to create oyster seed.
10
Approximate Cost: $48M Louisiana Marine Fisheries Enhancement and Science Center 3 Fisheries Enhancement and Research locations Marine Fisheries Stock Enhancement Aquaculture Research and Enhancement Education and Science Facilities Three locations: 20-acre site in Plaquemines Parish Existing Marine Research Laboratory on Grand Isle, 90-acre site located along the coast in Southwest, LA Salt Water Hatchery
11
Shell Island Restoration Approximate Cost: $110M Background: Shell Island is part of the Barataria Basin Barrier Shoreline. It is a key barrier between Gulf of Mexico and Barataria Basin. Island fragmented by strong tropical storms and land subsidence Project Goals: Restoring geomorphic and hydrologic function of Shell Island is an important priority for the Barataria Basin.
12
Approximate Cost: $65M Background: Proposed with DOI and the State of Mississippi, this project will restore a portion of the Chandeleur Islands. These islands have been directly impacted from the spill. Project Goals: Restore dune and marsh habitat Stabilize remaining unvegetated portions Chandeleur Islands Restoration
13
Approximate Cost: $45M Background: The Biloxi Marsh complex provides important habitat in the Lake Pontchartrain Basin. The project area has lost approximately 15,640 acres between 1932 - 1990 Project Goals: Create a breakwater structure to protect the existing Biloxi Marsh habitat from erosion. Biloxi Marsh Shoreline Protection
14
Approximate Cost: $13.9M Background: This project involves an additional increment of 97.5 acres of marsh creation into a project known as the “Lake Hermitage Marsh Creation Project” Project Goals: Create 97.5 acres of new marsh habitat Lake Hermitage Additional Increment
15
Approximate Cost: $31.3M Background: An important land feature designed to decrease storm surge and slow salt water intrusion. Project Goals: Restore the eastern ridge of Bayou Grand Liard and the adjacent marsh habitat to the east of the Bayou. Restore 18,000 linear feet of ridge on the east bank of Bayou Grand Liard Grand Liard Marsh & Ridge Restoration
16
Approximate Cost: $44M Background: A protective barrier island of the Barataria Basin. Project Goals: Increase the longevity of Chenier Ronquille Island by restoring or creating dune and marsh platforms. Repair of breaches in the shoreline Prevent new breaches Cheniere Ronquille Barrier Island Restoration
17
Approximate Cost: $3.3M Background: The back-bay side of Grand Isle is subjected to wave action from strong north winds during winter cold front passages and when tropical storms or hurricanes make landfall east of the islands Project Goals: Reduce erosion on the bay side of Grand Isle Protect important residential and commercial infrastructure Bay Side Segmented Breakwater at Grand Isle
18
Approximate Cost: $3M Background: Important ecological and hydrologic divide between Gulf of Mexico and marsh habitat. West Grand Terre Island has some of the highest erosion rates in coastal Louisiana. Project Goals: Stabilize the bay side of southwestern West Grand Terre Island, using rock armament. West Grand Terre Stabilization
19
Approximate Cost: $9M Background: Important ecological and hydrologic divide between Gulf of Mexico and marsh habitat. Project Goals: Restore the beach on the southwest (Gulf) side of West Grand Terre Island using sediment pumped from an offshore source area. Total beach nourishment for this project is approximately 120 acres. West Grand Terre Beach Nourishment
20
Approximate Cost: $75M Background: Part of the Barataria Basin Barrier Shoreline, the Caminada Headland forms a key barrier between saline waters of the Gulf of Mexico and the fresher waters of the Barataria Basin Project Goals: Restore the Caminada Headland portion of the barrier shoreline Creation and restoration of back-barrier marsh Barataria Basin Barrier Shoreline Restoration: Caminada Headland
21
Approximate Cost: $71M Background: Designed to protect marsh habitat along the southern shores of Caillou Lake by minimizing saltwater intrusion and maintaining separation between Caillou Lake and the Gulf of Mexico Project Goals: Sustain the land barrier between Calliou Lake and the Gulf of Mexico Involves protection and restoration of approximately 1,600 acres of salt marsh Maintain Land Bridge between Caillou Lake and Gulf of Mexico
22
Photo Credit: NOAA Early Restoration Timeline April 21, 2011 Trustees announce $1B for early restoration June 13, 2011 Louisiana publicly releases master list of projects submitted to date June 20, 2011 Public meeting on early restoration projects June 25, 2011 Deadline for project submittals for initial phase of early restoration July 11, 2011 Governor Jindal announces “Louisiana Plan” for early restoration projects Summer 2011 Trustee Council to review projects for potential negotiation with BP Fall 2011 Negotiation s with BP and Public comment on early restoration plan(s)