www.cbelearning.com Wates CBE Learning Build: Plant interactive
2
www.cbelearning.com Building the new school will take place in stages Each slide gives you information about one stage Work out how long each stage will last Decide which machine is needed for which task Write down how long each one will be needed, and its weekly cost What is needed and when?
3
www.cbelearning.com Digging away uneven ground2 weeks THEN Levelling the surface1 week THEN Creating a firm surface1 week PLUS Removing waste materialsDuring last 2 weeks Dumper: £850 Grader: £950 Excavator: £1,250 Compactor: £900 1. Ground work
4
www.cbelearning.com Digging trenches2 weeks THEN Pouring concrete1 week Dumper: £850 Grader: £950 Excavator: £1,250 Mixer: £2,000 2. Foundations
5
www.cbelearning.com 3. Structure and roof Lifting steel beams into place2-6 weeks Hydraulic crane: £6,000 Forklift: £850 Piledriver: £1,500 Hint: How could you make this 2 weeks and not 6?
6
www.cbelearning.com Re-shape grounds2 weeks PLUS Remove wasteDuring re-shaping Dumper: £850 Grader: £950 Excavator: £1,250 Compactor: £900 4. Landscaping
7
www.cbelearning.com Use your notes to make a simple spreadsheet Work out: - the total time for the build - how much each piece of plant will cost Use a simple formula to help you add up times and costs Work out the time and costs