C-4 Canal Bank Improvements Belen Phase 2 Flood Protection Berm & Wall John Mitnik, P.E. Engineering & Construction Bureau Chief John Mitnik, P.E. Engineering.

Similar presentations


Presentation on theme: "C-4 Canal Bank Improvements Belen Phase 2 Flood Protection Berm & Wall John Mitnik, P.E. Engineering & Construction Bureau Chief John Mitnik, P.E. Engineering."— Presentation transcript:

1 C-4 Canal Bank Improvements Belen Phase 2 Flood Protection Berm & Wall John Mitnik, P.E. Engineering & Construction Bureau Chief John Mitnik, P.E. Engineering & Construction Bureau Chief Governing Board Meeting December 12, 2013

2 C-4 Canal Bank Improvements Belen Phase 2 Flood Protection Berm & Wall

3 Bid Summary  RFB Advertised: October 15, 2013  Bid Opening: November 15, 2013  Number of Bids received: 8  Bid Range: $1,120,000 – 2,223,000  Engineer’s Estimate: $1,429,549 to $1,580,028

4 Resolution  A Resolution of the Governing Board of the South Florida Water Management District to authorize entering into a 358 day contract with Arbor Tree & Land, Inc., the lowest responsive and responsible bidder, for C-4 Canal Bank Improvements Belen Phase 2, Flood Protection Berm & Wall Project, in an amount of $1,360,250.00, for which $1,110,892.00 in ad valorem funds are budgeted in FY14 Engineering & Construction Bureau's capital improvement program and the remainder is subject to the Governing Board approval of the FY15 budget; providing an effective date.


Download ppt "C-4 Canal Bank Improvements Belen Phase 2 Flood Protection Berm & Wall John Mitnik, P.E. Engineering & Construction Bureau Chief John Mitnik, P.E. Engineering."

Similar presentations


Ads by Google