Presentation is loading. Please wait.

Presentation is loading. Please wait.

2015 November 2015 Md. Abdur Rouf Director, Power Cell Use of Renewable Energy.

Similar presentations


Presentation on theme: "2015 November 2015 Md. Abdur Rouf Director, Power Cell Use of Renewable Energy."— Presentation transcript:

1 2015 November 2015 Md. Abdur Rouf Director, Power Cell Use of Renewable Energy

2 Vision for Power Sector: To provide quality & reliable electricity to all by 2021at an affordable price Vision for Power Sector: To provide quality & reliable electricity to all by 2021at an affordable price Vision 2021- To be a Middle-Income Country VISION-2021 2

3 Renewable Energy Development Renewable Energy Development 10% (2000 MW) of total energy generation from RE by 2020 3 10% (4000 MW) of total energy generation from RE by 2030 Policy Targets

4 4 RULE OF RE IN THE ENERGY SYSTEM  Off-grid electrification  Fuel diversification for grid power generation  Energy Security  Environment friendly  Green energy: Climate Change Mitigation  Green job creation

5 5 Potential Sources of Renewable Energy

6 Solar Energy 6

7 Solar Photovoltaic System Solar Radiation PV Module Electrical Energy

8 Component of Solar System  Sun  PV Module  Solar Charge Controller  Battery  Inverter  Load Light Fan TV Radio Refrigerator Computer Battery/ Inverter

9 Stand Alone Solar System PV Module Sun Battery Load

10 Stand-alone PV Power System (off-grid)

11 Grid connected PV system SUN TRACKING +-+- DC ACSMALL LOAD Load + + + + + - - - - - AC Initializing…Connected Load + - GRID FAILURE INCREASED LOAD + - DC GRID Connected INVERTER +-+- Rooftop PV Array Extended PV Array GRID + + - - Disconnected Emergency Load + + + + + - - - - - INVERTER LOAD IS TAKING POWER FROM SOLAR PANEL + - THE BASIC SYSTEM BLOCKLOAD IS TAKING POWER FROM THE GRIDINCREASED LOAD IS TAKING POWER FROM PV AND GRID LOAD SHEDDING MODEL

12 12 Wind Energy

13 13 Wind Turbine

14 Wind Power Projects Tender Processing Project Under Planning Tender Processing Project Under Planning Project Implemented 0.9 MW Grid Connected Wind Power Plant Feni 1 MW Wind Battery Hybrid Power Plant Kutubdia Island 60 MW Wind Power Plant Cox’s Bazar 15 MW Wind Power Plant

15 Wind Resource Mapping Project Under Implementation Tender Processing Project Under Planning Project Under Implementation Tender Processing Project Under Planning Project Implemented Feni Wind Resource Assessment Rajshahi Rangpur Mymensingh Mongla Mirzapur Sitakunda Rajapalong Parky Beach Mognamaghat Inani Beach Chadpur

16 16 82 m Tower at Parkey Beach

17 17 Contribution of Renewable Energy TypeTotal Solar Home System 160 MW Solar PV (Office Buildings) 12 MW Solar Irrigation 2 MW Solar Mini-Grid/Micro-grid 1 MW Wind 2 MW Biomass/Biogas 6 MW 6 MW Hydro 230 MW Total 415 MW 80,000 bio gas system are in place for cooking 5 million ICS sold to customers 80,000 bio gas system are in place for cooking 5 million ICS sold to customers

18  Private Sector Projects: Solar  Sarishabari: 3 MW;  Kaptai: 7.4 MW  Thakurgaon: 5 MW  Rangunia: 60 MW  Gangachora: 55 MW  Dharla: 30 MW  Sonagazi: 100 MW  Cox’s Bazar: 200 MW  Mymensingh: 50 MW  Sunamgonj: 32 MW  Panchagarh: 200 MW  Private Sector Projects: Solar  Sarishabari: 3 MW;  Kaptai: 7.4 MW  Thakurgaon: 5 MW  Rangunia: 60 MW  Gangachora: 55 MW  Dharla: 30 MW  Sonagazi: 100 MW  Cox’s Bazar: 200 MW  Mymensingh: 50 MW  Sunamgonj: 32 MW  Panchagarh: 200 MW 18 Ongoing Large Scale Projects 18 Wind  Cox’s Bazar: 60MW  Rajpalong: 15MW  Patuakhali : 100MW Wind  Cox’s Bazar: 60MW  Rajpalong: 15MW  Patuakhali : 100MW

19 19 Ongoing Large Scale Projects 19 BPDB APSC L EGCB NWPGC L RPCL CPGC L Total Solar (MW)100 5550 455 Wind (MW)100 600 Total200 155150 1055  Public Sector Projects:

20 Renewable Energy Development Plan-2021 Year wise generation plan to reach the targets Year2015201620172018201920202021Total (MW)773756805945524104153103 20

21 21 Renewable Energy Target (MW) Technology2015201620172018201920202021Total Solar75336421.752672292032081739.75 Wind020250350 200 1370 Biomass1166666647 Biogas (Biogas to electricity) 11111117 Hydro (mini/micro) 22 ---- 4 Total77 375 680.756245854104153167.7

22 22  High upfront cost for RE project  Scarcity of land for grid connected RE projects  Moderate potentials  Inadequate incentives for RE development  Low tariff mechanism  Lack of awareness among the people  Lack of R & D  Lack of Confidence of the investor  Lack of expertise  High upfront cost for RE project  Scarcity of land for grid connected RE projects  Moderate potentials  Inadequate incentives for RE development  Low tariff mechanism  Lack of awareness among the people  Lack of R & D  Lack of Confidence of the investor  Lack of expertise CHALLENGES IN PROMOTION RE

23 23 Thanks


Download ppt "2015 November 2015 Md. Abdur Rouf Director, Power Cell Use of Renewable Energy."

Similar presentations


Ads by Google